Updated Standard Commercial Principles
Transcrição
Updated Standard Commercial Principles
Guidance Material - April 2008 Updated Standard Commercial Principles The Secretary Department of Treasury and Finance 1 Treasury Place, Melbourne Victoria 3002 Australia Telephone: +61 3 9651 5111 Facsimile: + 61 3 9651 2062 Website: www.partnerships.vic.gov.au Published by the Department of Treasury and Finance © State of Victoria 2008 First published 2005 Updated edition April 2008 This book is copyright. No part may be reproduced by any process except in accordance with the provisions of the Copyright Act. ISBN 1 921337-22-2 Published April 2008 by authority For more information on this publication and for other information on Partnerships Victoria, visit the website www.partnerships.vic.gov.au The State of Victoria acknowledges the kind permission given by: Civic Nexus to use and reproduce the computer generated image of Spencer Street Station. Vivendi Water Australia to use and reproduce the photograph of the Coliban Water Treatment Plant, Bendigo Victoria. Partnerships Victoria Detailed Guidance Material Updated Standard Commercial Principles April 2008 Treasurer’s Foreword I am pleased to announce the release of the updated Partnerships Victoria Standard Commercial Principles. When the Standard Commercial Principles were first published in 2005, the then Treasurer undertook to review and revise the principles periodically in light of the continually evolving Public Private Partnership (PPP) market at a state, national and international level. This effort was taken to ensure Partnerships Victoria continues to represent best practice policy and deliver the best possible outcomes. With the release of the attached updated principles, the Brumby Government has delivered on this commitment and reinforced its position as a leader in infrastructure delivery in partnership with the private sector. We believe the update will generate further efficiencies in the procurement of Partnerships Victoria projects, leading to further reductions in private sector bid costs. This is a significant development in the PPP landscape across Victoria and Australia at a time when PPP’s can assist in meeting Australia’s growing demand for infrastructure to address capacity constraints and secure future productivity growth and prosperity. I look forward to using this update as a significant contribution to a national dialogue on consistent, best practice PPP guidelines. JOHN LENDERS MP TREASURER i Table of Contents Updated Standard Commercial Principles Table of Contents Introduction ............................................................................................................1 Summary table of key revisions ...........................................................................3 1. Contractual Issues ........................................................................................7 1.1 1.2 1.3 1.4 1.5 1.6 2. 2.1 2.2 2.3 2.4 3. 3.1 3.2 3.3 3.4 4. 4.1 4.2 5. 5.1 5.2 6. 6.1 6.2 6.3 7. 7.1 7.2 7.3 7.4 8. 8.1 8.2 8.3 8.4 9. 9.1 9.2 9.3 9.4 9.5 9.6 9.7 Introduction ............................................................................................................... 7 Contracting party ...................................................................................................... 7 Authority to make contracts ...................................................................................... 7 Delegated powers and functions .............................................................................. 8 Enforceability of the contract .................................................................................... 8 State facilitation ........................................................................................................ 9 Conditions precedent .................................................................................11 Overview................................................................................................................. 11 Conditions precedent bond..................................................................................... 11 Requirements of conditions precedent................................................................... 12 Termination............................................................................................................. 13 Contract term...............................................................................................14 Expiry date.............................................................................................................. 14 Extension ................................................................................................................ 14 Liquidated damages ............................................................................................... 15 Earlier termination................................................................................................... 15 Site conditions and suitability ...................................................................16 Site suitability.......................................................................................................... 16 Site conditions ........................................................................................................ 16 Environmental issues .................................................................................19 Environmental approvals ........................................................................................ 19 Contamination......................................................................................................... 20 Native title and artefacts.............................................................................25 Native title ............................................................................................................... 25 Artefacts.................................................................................................................. 26 Memorandum of Understanding ............................................................................. 26 Planning and other approvals....................................................................27 Commonwealth approvals ...................................................................................... 27 State planning approvals ........................................................................................ 27 Other site approvals................................................................................................ 27 Compliance............................................................................................................. 28 Site access...................................................................................................29 Availability............................................................................................................... 29 Third party occupants ............................................................................................. 29 Access for government and third parties................................................................ 30 Utilities .................................................................................................................... 30 Tenure ..........................................................................................................31 Ownership............................................................................................................... 31 Reservation of project land..................................................................................... 31 Construction licence ............................................................................................... 32 Tenure during the operating period ........................................................................ 32 Government access rights...................................................................................... 33 Other licences or sub-leases .................................................................................. 33 Improvements ......................................................................................................... 34 ii Table of Contents 10. Design ..........................................................................................................35 10.1 10.2 10.3 10.4 11. 14.7 14.8 Monitoring obligations........................................................................................ 65 Additional performance monitoring rights.......................................................... 66 Auditing.............................................................................................................. 66 Operating committee ......................................................................................... 67 Intervening events during the operational phase ....................................69 17.1 17.2 17.3 17.4 17.5 17.6 17.7 18. Maintenance and refurbishment during the operating phase............................ 62 Asset management plan.................................................................................... 62 Funding maintenance and refurbishment obligations ....................................... 63 Monitoring performance of maintenance and refurbishment obligations .......... 63 End-of-term arrangements ................................................................................ 64 Performance monitoring and review .........................................................65 16.1 16.2 16.3 16.4 17. Provision of contracted services........................................................................ 54 Service standards and specifications ................................................................ 55 Service Failures................................................................................................. 56 Performance monitoring .................................................................................... 57 Abatement and default ...................................................................................... 58 Delivery of core services does not relieve the private party of its contractual obligations....................................................................................... 59 Utility services.................................................................................................... 59 Government relief for private party failure to comply with service obligations .. 60 Maintenance and refurbishment ................................................................62 15.1 15.2 15.3 15.4 15.5 16. Liquidated damages .......................................................................................... 51 Performance bonds ........................................................................................... 52 Parent guarantees ............................................................................................. 53 Service requirements and specifications .................................................54 14.1 14.2 14.3 14.4 14.5 14.6 15. Form of relief...................................................................................................... 44 Time relief .......................................................................................................... 44 Compensation relief........................................................................................... 48 Protection against late or insufficient service delivery ...........................51 13.1 13.2 13.3 14. Construction and commissioning obligations .................................................... 38 Construction updates and reports ..................................................................... 38 Project committee.............................................................................................. 38 Inspections......................................................................................................... 39 Commissioning, operational and commercial acceptance ................................ 39 Defects............................................................................................................... 42 Relief for construction delays....................................................................44 12.1 12.2 12.3 13. Design obligations ............................................................................................. 35 Fitness for purpose warranty ............................................................................. 35 Mandatory design guidelines............................................................................. 35 Design development process ............................................................................ 36 Construction and commissioning....................................................................38 11.1 11.2 11.3 11.4 11.5 11.6 12. Updated Standard Commercial Principles Intervening Events............................................................................................. 69 Threshold requirements..................................................................................... 71 Relief for Intervening Events ............................................................................. 71 Compensation ................................................................................................... 72 Alternative arrangements .................................................................................. 73 Cessation of the Intervening Event ................................................................... 74 No effect on government's step-in rights ........................................................... 74 Payment provisions ....................................................................................74 18.1 18.2 18.3 18.4 18.5 18.6 18.7 Service payment................................................................................................ 74 Payments........................................................................................................... 75 Indexation .......................................................................................................... 76 Service payments for phased completion ......................................................... 76 Service fee adjustment principles...................................................................... 76 Variations to financial model.............................................................................. 78 Taxes ................................................................................................................. 79 iii Table of Contents 19. Review and market testing of Services.....................................................80 19.1 19.2 19.3 20. Insurance generally ......................................................................................... 112 General insurance obligations ......................................................................... 114 Changes in insurance costs ............................................................................ 114 Uninsurability ................................................................................................... 117 Default ........................................................................................................119 27.1 27.2 27.3 27.4 28. Obligation to repair or reinstate ....................................................................... 109 Direction by government not to reinstate or repair .......................................... 110 Direction by government to reinstate to different specifications...................... 111 Insurance ...................................................................................................112 26.1 26.2 26.3 26.4 27. Qualifying events ............................................................................................. 105 Form of relief.................................................................................................... 106 Temporary measures and alternative arrangements ...................................... 107 Financial relief ................................................................................................. 107 Termination...................................................................................................... 108 Reinstatement and repair .........................................................................109 25.1 25.2 25.3 26. Scope of Change in Law ................................................................................... 98 General Change in Law..................................................................................... 99 Project-specific Change in Law ....................................................................... 101 Form of relief.................................................................................................... 103 Threshold requirements................................................................................... 104 Inconsistency with performance standards ..................................................... 104 Force majeure............................................................................................105 24.1 24.2 24.3 24.4 24.5 25. Government-initiated modification to the facility................................................ 91 Private party initiated modification works .......................................................... 95 Government-initiated modifications to service standards.................................. 96 Minor works ....................................................................................................... 97 Change in Law .............................................................................................98 23.1 23.2 23.3 23.4 23.5 23.6 24. Warranty as to Control....................................................................................... 88 Change in Control of private party..................................................................... 88 Consent may be withheld .................................................................................. 89 Modifications ...............................................................................................91 22.1 22.2 22.3 22.4 23. Subcontracts - generally.................................................................................... 84 Additional material subcontract requirements ................................................... 85 Amendments to material subcontracts .............................................................. 86 Side deed........................................................................................................... 86 Subcontractor requirements .............................................................................. 86 Private party's obligations in respect of subcontracts ....................................... 87 Subcontractors appointed by financiers ............................................................ 87 No relief to private party by subcontracting obligations..................................... 87 Probity................................................................................................................ 87 Change in Control .......................................................................................88 21.1 21.2 21.3 22. Reviewable services.......................................................................................... 80 Review of soft services...................................................................................... 80 Market testing .................................................................................................... 81 Subcontractors............................................................................................84 20.1 20.2 20.3 20.4 20.5 20.6 20.7 20.8 20.9 21. Updated Standard Commercial Principles Events of Default ............................................................................................. 119 Cure periods and remedies for Events of Default ........................................... 121 Extension of cure period.................................................................................. 123 General remedies ............................................................................................ 123 Termination................................................................................................124 28.1 28.2 28.3 28.4 28.5 Default Termination Event ............................................................................... 124 Force Majeure Termination Events ................................................................. 126 Voluntary termination....................................................................................... 126 Procedure ........................................................................................................ 127 Consequences................................................................................................. 127 iv Table of Contents 29. Termination payments ..............................................................................128 29.1 29.2 29.3 29.4 29.5 30. Restrictions on business.................................................................................. 157 Restrictions on amending certain documents ................................................. 157 Restrictions on assignment ............................................................................. 157 Restrictions on sale or lease ........................................................................... 158 Records ......................................................................................................159 36.1 36.2 36.3 36.4 36.5 36.6 36.7 36.8 36.9 37. Private party indemnity .................................................................................... 153 Representations and warranties...................................................................... 154 Non-exclusivity of remedies............................................................................. 156 Restrictions on private party....................................................................157 35.1 35.2 35.3 35.4 36. Government consent ....................................................................................... 149 Notice and re-financing details ........................................................................ 149 What is a re-financing?.................................................................................... 149 When may government withhold its consent................................................... 150 Sharing a re-financing gain.............................................................................. 151 Calculating the re-financing gain ..................................................................... 151 Payment of the re-financing gain..................................................................... 151 Government audit rights .................................................................................. 152 Acting in good faith .......................................................................................... 152 Funder's direct agreement............................................................................... 152 Termination payments ..................................................................................... 152 Indemnities, warranties and contractual claims ....................................153 34.1 34.2 34.3 35. Panel................................................................................................................ 146 Independent determination.............................................................................. 146 Independent expert.......................................................................................... 147 Arbitration ........................................................................................................ 147 Fast-track process ........................................................................................... 148 Legal rights ...................................................................................................... 148 Obligation to continue to perform .................................................................... 148 Re-financing gain ......................................................................................149 33.1 33.2 33.3 33.4 33.5 33.6 33.7 33.8 33.9 33.10 33.11 34. Return conditions at contract expiry ................................................................ 141 Other private party rights and obligations........................................................ 143 Dispute resolution.....................................................................................146 32.1 32.2 32.3 32.4 32.5 32.6 32.7 33. Circumstances of step-in ................................................................................. 137 Rights and obligations on step-in .................................................................... 138 Costs of step-in................................................................................................ 138 No liability or limitation on government's rights ............................................... 139 Stepping-out .................................................................................................... 139 End-of-term arrangements .......................................................................141 31.1 31.2 32. Default Termination Payment .......................................................................... 128 Force Majeure Termination Payment .............................................................. 132 Payment for voluntary termination by government.......................................... 134 Mitigation ......................................................................................................... 136 Transfer of debt obligations ............................................................................. 136 Step-in ........................................................................................................137 30.1 30.2 30.3 30.4 30.5 31. Updated Standard Commercial Principles Maintenance of audited records ...................................................................... 159 Availability of audited records.......................................................................... 159 Accounting records.......................................................................................... 159 Provision of other details ................................................................................. 160 Warranty .......................................................................................................... 160 Financial audit.................................................................................................. 160 Maintenance of non-financial records ............................................................. 161 Period for retaining records ............................................................................. 161 Confidentiality .................................................................................................. 161 Probity ........................................................................................................162 37.1 37.2 37.3 Notification of a probity event .......................................................................... 162 Meaning of probity event ................................................................................. 162 Consequences following notice of a probity event .......................................... 162 v Table of Contents 37.4 37.5 37.6 38. Costs of cure.................................................................................................... 163 Probity investigations....................................................................................... 163 No appointment without government consent ................................................. 164 Confidentiality and disclosure .................................................................165 38.1 38.2 38.3 39. Updated Standard Commercial Principles State disclosure ............................................................................................... 165 Confidentiality .................................................................................................. 165 Legislative disclosure obligations .................................................................... 166 Intellectual property ..................................................................................167 39.1 39.2 39.3 39.4 39.5 39.6 39.7 39.8 Warranties ....................................................................................................... 167 Grant of licences.............................................................................................. 167 Obligation......................................................................................................... 168 Moral rights ...................................................................................................... 168 Survival of rights .............................................................................................. 168 Indemnity ......................................................................................................... 168 IP rights passed from government .................................................................. 168 Rights to IP on expiry of term .......................................................................... 169 vi Partnerships Victoria Updated Standard Commercial Principles Introduction The Brumby Government is committed to improving the way it does Partnerships Victoria projects. Ensuring that we identify and incorporate into our principles (as appropriate), the lessons being learnt across the landscape of PPP projects is critical to the long term success and viability of PPPs. With this long-term objective in mind, the Brumby Government has continued to review the Partnerships Victoria Standard Commercial Principles since their release in 2005, in light of the evolving PPP market at a State, national and international level. That review has culminated into these updated Standard Commercial Principles, which replace the 2005 published version. The updated principles have been developed against a background of continual dialogue across government departments and agencies and the private sector. All comments and suggested positions arising from these dialogues were given due consideration in preparing the updated principles, even where they have not been adopted in the attached document. The updated principles are not a shift in Partnerships Victoria policy. We believe that they continue to strike a fair balance between the public and private interest. We have either updated or provided clarification and further guidance on those principles, where project experience or other evidence has shown that doing so would deliver better value for money. Key revisions and application The key areas that have been amended or in respect of which further guidance has been issued, are: • • • • • • • • • Relief for Construction Delays (section 12) and Intervening Events during the operating phase (section 17); Service failures/abatement and default (paragraphs 14.4 and 14.5); Government relief for private party failure to comply with service obligations (paragraph 14.8); Utility services (paragraph 14.7); Modifications (section 22); General Change in Law (paragraph 23.2); Force majeure (section 24); Default (section 27); and Termination payments (section 29). Further details of the key variations are summarised in the following summary table. The summary table has been provided to assist practitioners to work through the detail of the revised principles. It does not identify all the changes made to the 2005 document and should not be relied on for compliance purposes. The Partnerships Victoria website contains both a final copy of the updated principles and a revised copy showing the changes to the 2005 published version. The updated principles will apply to all future Partnerships Victoria projects. They will not apply retrospectively to Partnerships Victoria projects that have closed. April 2008 1 Partnerships Victoria Updated Standard Commercial Principles The updated principles provide a consistent and efficient risk allocation framework, while recognising the need for flexibility for individual project needs. However, any derogation from the updated principles for sector or project-specific issues must be documented and agreed with the Department of Treasury and Finance when approval is sought to issue the project brief. Consistent with the assumptions underlying the 2005 published principles, the updated principles apply to core services/accommodation type Partnerships Victoria projects, where the site has been chosen by government, payment is based on availability and the facility reverts to the State at no cost at contract end. However, many of the principles will also be applicable to other Partnerships Victoria projects, including economic infrastructure projects. Next steps Victoria is committed to the ongoing process of refining and developing the principles, to ensure Partnerships Victoria projects sustainably deliver best possible outcomes. We aim to develop them further into standard contractual clauses, to help reduce the cost and time of contractual negotiations. We will consult with PPP market participants, both in Victoria and nationally, on our draft standard clauses before they are finalised. I look forward to continuing our dialogue across government departments and agencies and the private sector, as part of this process. David Asteraki Director, Partnerships Victoria April 2008 2 Partnerships Victoria Updated Standard Commercial Principles Summary table of key revisions Section / Paragraph Reference Principle Description of Revision Paragraph 4.2.2 Relief for latent geotechnical conditions Further guidance is provided requirements for provision of relief. Paragraphs 4.2.3 and 5.2.3 Site condition and contamination due diligence Further guidance is provided around the basis for the carrying out of any government due diligence and the terms on which the benefit of any government due diligence reports will be provided to the private party. Paragraph 5.2.2 High Risk and Low Risk Sites Clarification is provided on what constitutes a High Risk Site (formerly referred to as a ‘Brownfield Site’) and a Low Risk Site (formerly referred to as a ‘Greenfield Site’). The distinction reflects the fact that specific sites will have different likelihoods of contamination and other latent conditions occurring and therefore different risk allocations. Paragraph 5.2.5 Unidentified preexisting contamination Further guidance is provided on the circumstances and conditions on which government will share the risk of pre existing contamination. Paragraph 6.2.3 Artefacts risk Whether and the period for which the private party will be required to carry any artefacts risk will be determined on a project-specific basis depending on the likelihood of artefacts being discovered. Paragraph 10.2 Fitness for purpose warranty The fitness for purpose test will be referenced to the requirements of the project brief and the project agreement, as at the Date for Commercial Acceptance not the date of the project agreement. Paragraph 11.5.6 Consequences of a failure to achieve Technical Completion and Commercial Acceptance An Event of Default has been introduced where a look forward test finds a reasonable prospect of the private party not achieving Technical Completion and Commercial Acceptance by the relevant due dates. The Events of Default around a failure to reach Technical Completion may in certain circumstances be waived. Paragraph 11.6.1 Rectification of identified defects Clarification of government’s requirements for the rectification of deferred defects. April 2008 on the 3 Partnerships Victoria Section / Paragraph Reference Principle Updated Standard Commercial Principles Description of Revision Paragraph 12.2.1 Threshold requirements for the giving of time relief Time relief may be given if the relevant relief event affects a critical activity on the critical path and directly causes a delay to achievement of completion of the facility. Relief will not be limited to circumstances where the final date for completion has been affected by the delay. However, strict reporting obligations will need to be complied with and relief will be provided on the basis of the updated ‘as bid’ master works program. Paragraph 12.2.2 and 12.3 Extension of time events and compensation events Further guidance has been provided on what will constitute a time relief event and a compensation event. Some new extensions of time events and compensation events have been introduced. Paragraph 12.2.4 Concurrent delays The circumstances in which the private party will be given relief for concurrent delays have been extended. Paragraph 12.3.3 Compensation amount Further guidance has been provided on the basis for determining the compensation amount. Paragraphs 14.3 and 14.5 Service failures and the abatement regime Further clarification and guidance has been provided on the categorisation and financial impact of service failures. Paragraph 14.7 Utilities The risk allocation previously applying just to electricity has been extended to all utilities. Also, further clarification has been provided on the circumstances and basis on which government will seek to share utility volume risk. Paragraph 14.8 Abatement as the sole remedy Government has amended its position so that abatement will be the sole remedy except in certain specified circumstances. Paragraphs 17.1 and 17.4 Intervening Events and compensable Intervening Events Further guidance has been provided on what will constitute an Intervening Event and a Compensable Intervening Event. Some new Intervening Events and Compensable Intervening Events have been introduced. Further guidance has also been provided on the form of and conditions on which relief for these events will be provided. Paragraph 18.7 April 2008 Allocation of tax and rates liability Government has recognised the need in certain circumstances to reimburse the private party for these costs. 4 Partnerships Victoria Section / Paragraph Reference Section 19 Principle Review and market testing of services Updated Standard Commercial Principles Description of Revision Government has modified the process (consistent with market practice) so that soft services will not be benchmarked but the private party will be given the opportunity to submit an offer to deliver the services on a competitive basis (before moving to a market testing process). Further guidance has been provided on the required procedures for market testing. Section 21 Change in Control Minor drafting changes for consistency in terminology. Further guidance has been provided around the basis on which government can withhold its consent to a change in control and the effect of a breach of change in control obligations (in respect of the private party and key subcontractors). Section 22 Modifications Revisions to the process for implementing government initiated modifications (e.g., the parties will need to agree the cost of preparing a proposal before any work is undertaken). Further guidance has been provided around basis on which government will compensate the private party for the cost of modification works including requiring the private party to bid maximum margins and other on-costs. Clarification has been provided around what works do not constitute modifications and the concept of a minor works regime has been introduced. Section 23 Change in Law Although there have been no changes to this principle, government has provided clear guidance around the principles to be adopted for setting suitable percentage sharing thresholds for general change in law risk. There will be no relief for soft operating costs arising from general changes in law. Section 24 Force majeure Further guidance has been provided on what will constitute a Force Majeure Event and the basis on which relief will be provided (particularly where the risk is insurable or should have been insured against). Some new Force Majeure Events have been introduced. The basis on which the private party can terminate for a Force Majeure Event has been clarified. April 2008 5 Partnerships Victoria Section / Paragraph Reference Paragraphs 26.3 and 26.4.2 Updated Standard Commercial Principles Principle Sharing changes in insurance costs and treatment of uninsurable risk Description of Revision Further guidance has been provided on how government will share increases in insurance costs (including any process requirements). Government has moved away from the existing retrospective approach to compensating insurance cost increases, to an annual forwardlooking basis. The test for determining whether insurance is unavailable has been revised. Sections 27 and 28 Section 29 Default and termination Termination payments Further guidance has been provided on: • what will constitute an Event of Default and Default Termination Events. Some new Events of Default and Termination Events have been introduced; and • the process for dealing with Events of Default not capable of cure. Guidance has been provided around: • termination payments for bond financed deals; and • the process for determining a fairmarket-value where government chooses to tender the project in a liquid market in the event of a default termination. Further clarification has been provided on the basis for determining termination payments (in particular, on appropriate deductions) and methods for payment. Paragraph 30.3 April 2008 Costs for step-in The amount by which the service fee will be reduced during a government step-in has been revised. There has also been a minor change to government’s potential liability in the event of step-in. 6 Partnerships Victoria Updated Standard Commercial Principles 1. Contractual Issues Principle Special characteristics and powers of government give rise to particular issues which the project agreement will address in seeking to equalise the relationship between the parties and place the relationship on a commercial footing. 1.1 Introduction The key issues for the private party when contracting with government are as follows: • Is the contracting party the State of Victoria or an entity created by legislation? • Does the person who will sign the project agreement for the government party have the requisite authority to bind the State? • Is the project agreement enforceable against the Crown? • What can reasonably be expected of government in the exercise of statutory powers and discretions which impact on the project? 1.2 Contracting party Depending upon the nature and scale of the project, the contracting party may be: (a) the State of Victoria; or (b) a statutory body or statutory corporation. 1.3 Authority to make contracts 1.3.1 Contracts within portfolio Ministers have authority to make a contract on behalf of the State in connection with any matter which comes within their portfolio and departmental responsibility. In many instances department heads also have this authority. 1.3.2 Legislative authority Parliament may pass legislation to support a government contract. Legislation is only needed where the subject matter of the contract requires a regulatory framework or other amendments to existing law are required. This is not generally necessary for accommodation-based projects and is usually restricted to linear projects (e.g. toll roads, where the private party requires authority to fix charges and tolls). Such legislation may specify the types of contract that can be made and who has authority to make and sign the contract. April 2008 7 Partnerships Victoria 1.3.3 Updated Standard Commercial Principles Warranty of authority Where there is any reasonable basis for doubt, the government party entering the project agreement will warrant that it has the power to enter into the project agreement and that its obligations under the project agreement are valid and binding obligations enforceable against it. 1.4 Delegated powers and functions 1.4.1 Instruments of delegation In the absence of express statutory delegation, government's delegation of its powers, functions or responsibilities in respect of the project agreement will take place through instruments of delegation separate from the project agreement.1 The project agreement will acknowledge that government is entitled to revoke or change any such delegation at any time. 1.4.2 Rights of private party The private party is entitled to know the identity of the current delegate or receive a copy of any current instrument of delegation. 1.5 Enforceability of the contract 1.5.1 Scope of power to contract If the State of Victoria enters into the project agreement under its executive power then the State will be bound because the State's executive power to contract is unlimited2. If there is legislation for the project agreement there must be compliance with the requirements of that legislation. If the project agreement does not observe these requirements then it will be void. 1.5.2 Waiver of State immunities Traditionally, government parties to a contract had the benefit of certain immunities from legal proceedings for breach of contract. However, this has been largely eroded. To resolve any question as to the existence or application of these immunities, government will agree to waive any right to its traditional immunities (in addition to the statutory effect of section 23 of the Crown Proceedings Act 1958 (Vic)). 1 Chapter 9 and Appendix G of the Partnerships Victoria Contract Management Guide discuss issues that should be considered by government in establishing delegations. 2 Unless the contract deals with an area for which the Commonwealth has exclusive responsibility under the Constitution. April 2008 8 Partnerships Victoria Updated Standard Commercial Principles 1.6 State facilitation 1.6.1 Limitations on government Government cannot contract out of an existing obligation under legislation or fetter its future exercise of a statutory power or discretion. If the project agreement contained a provision requiring government to do so, the provision would be ineffective. The project agreement will recognise these limitations on any express or implied facilitation obligations assumed by government. 1.6.2 Government not in breach Anything done by government pursuant to its executive or legislative powers and functions, even if directly contrary to the outcomes envisaged by the project agreement, will be deemed not to constitute a breach of the project agreement. 1.6.3 Acknowledgment The private party will also be required to acknowledge that government, in performing any of its duties and obligations, is not obliged to exercise any power, function or duty within the responsibility of any other government agency, or to influence, override or direct any government agency in the proper exercise of its legal duties and functions. For these purposes a government agency includes a government, semi-governmental, municipal, statutory or other public entity or authority. In addition, the parties will acknowledge that the project agreement may depart from the guidance materials that underpin the State's Partnerships Victoria policy and that no importation of those materials into the project agreement is implied or intended. 1.6.4 Right to compensation However, while not technically fettering its discretion, government may assume specific obligations under the project agreement with respect to the exercise of its powers and functions. This will be on the basis that it will be liable to pay compensation or allow the private party an extension of time (or both) if, in the free exercise of its discretion, it3 acts contrary to outcomes specified in the project agreement. Compensation for the consequences of a government act or omission contrary to its obligations under the project agreement will be payable under a specific regime in the project agreement4 and will be payable regardless of whether such act or omission occurred pursuant to a positive duty. 1.6.5 • 3 'Best endeavours' Government will not agree to open-ended 'best endeavours' or 'reasonable endeavours' clauses. It will define these obligations by reference to specific matters and no wider than strictly necessary. But only in its capacity as the contracting party, rather than its role of being responsible for the general administration of government affairs. 4 See section 12 (Relief for construction delays) and section 17 (Intervening Events during the operational phase). April 2008 9 Partnerships Victoria Updated Standard Commercial Principles • If the term is used in the project agreement, it will be accompanied by an acknowledgment that to the extent that government has any such obligations it will take steps to bring about the relevant outcome so far as it is reasonably able to do so, having regard to its resources and other responsibilities. • The project agreement will state expressly that by undertaking to exercise reasonable or best endeavours government does not agree to: (a) interfere with or influence the exercise by any person of a statutory power or discretion; (b) exercise a power or discretion or otherwise act in a manner that it regards as not in the public interest; or (c) develop policy or legislate by reference only or predominantly to the interests of the project. 1.6.6 Extent of duty of good faith Government, as a contracting party, will be subject to any implied good faith obligations that arise as a matter of law in commercial contracts. However, the project agreement will specifically disclaim that there is implied, whether from the concept of 'partnership' or the Partnerships Victoria guidance materials or otherwise, any general duty of good faith on the part of government towards the project or the project parties beyond the meeting of those obligations expressly assumed by government under the project agreement. April 2008 10 Partnerships Victoria Updated Standard Commercial Principles 2. Conditions precedent Principle The project agreement (other than specified parts of the agreement including the conditions precedent) does not commence until each of the conditions precedent has been satisfied or waived. 2.1 Overview In the normal course of events, certain conditions will be required to be satisfied prior to the project agreement becoming effective (conditions precedent). The date of satisfaction of these conditions precedent is known as financial close. On financial close: (a) obligations of each party to the project agreement become binding (other than those that become binding on contract signing); and (b) the interest rate setting protocol is implemented, the base case financial model is reset to reflect the rate set and the service fee is fixed. 2.2 Conditions precedent bond 2.2.1 Requirement The private party may be required to provide a conditions precedent bond to a specified value5 by the date of execution of the project agreement. Whether or not a conditions precedent bond is required will depend on factors such as: (a) project size; (b) market environment; (c) timing issues (e.g. whether there is likely to be a significant interval between contractual and financial close); (d) the nature and complexity of the conditions precedent and whether a process bond was lodged during the bid phase; (e) other incentives to reach financial close, such as the structure of the term or payment mechanism; and (f) the consequences of failure to reach financial close. 5 This will depend on the value of the individual project and the risk of the private party failing to achieve the conditions precedent. April 2008 11 Partnerships Victoria Updated Standard Commercial Principles Although government is mindful of not unnecessarily requiring conditions precent bonds, this may be a requirement for certain projects (in light of the above factors). 2.2.2 Demand Government may make demand under the conditions precedent bond if any of the conditions precedent are not satisfied or waived by the specified date6 (unless government causes the condition not to be fulfilled). 2.3 Requirements of conditions precedent 2.3.1 Content • • The following conditions precedent, as a minimum, will generally be required of the private party:7 (a) delivery of executed8 copies of relevant project documents not already provided to government;9 (b) delivery of certified copies of all finance documents duly executed, and evidence that all conditions precedent to funding have been satisfied (or waived) in accordance with the finance documents; (c) effecting of required insurance policies and providing certificates of currency; (d) provision of any required corporate or consortium details; and (e) submitting a design which incorporates government's requirements. Government may also require that a binding private tax ruling in relation to the operation of Div 250 of the Income Tax Assessment Act 1936 (Cth) and the Income Tax Assessment Act 1997 (Cth), be provided as a condition precedent. More specifically, government will seek greater comfort around the areas of project financing and ownership structures. 2.3.2 Obligations The private party must, at its cost, use reasonable endeavours to ensure that each of the conditions precedent that it is responsible for satisfying is met by the specified date. 2.3.3 Waiver Only the beneficiary of a condition precedent may waive the condition precedent. 6 See paragraph 2.4(d). 7 The conditions precedent will depend on the nature of the project, structure of the consortium and any other specific government requirements. 8 Excluding execution by government. 9 Generally the key subcontracts will have been entered and submitted at the date the project agreement is signed - see section 20 (Subcontractors). April 2008 12 Partnerships Victoria 2.4 Updated Standard Commercial Principles Termination If each of the conditions precedent is not satisfied or waived by the specified date: (a) government may terminate each of the contracts between the private party and government; (b) neither party will be entitled to claim against the other in respect of these contracts except those parts expressly said to take effect despite conditions precedent; (c) all future rights and obligations of the parties under the project agreement and otherwise in connection with the project are terminated; and (d) government may call upon the conditions precedent bond.10 Government will have the right to extend any target date for the satisfaction of conditions precedent. 10 See paragraph 2.1. April 2008 13 Partnerships Victoria Updated Standard Commercial Principles 3. Contract term Principle The term of the contract will depend on the best value for money solution for government and will reflect: (a) the period to financial close; (b) the anticipated construction period; and (c) the desired operating period. The contract term will be subject to earlier termination in certain circumstances. 3.1 Expiry date The expiry date of the project agreement will be the last day of the operating term. Generally, the operating term will be defined as a fixed period (e.g. 20 or 25 years) commencing from the Date for Commercial Acceptance. The expiry date (and therefore, the maximum length of the operating term) will be fixed by reference to factors such as: (a) the anticipated duration of government's need for the services; (b) the expected economic life of the asset and anticipated timing of major upgrade or refurbishment; (c) the expected technological life of the asset; (d) the minimum term considered necessary to deliver a reasonable return to the private party on its investment and amortise the capital value of the asset such that the asset can be transferred to government without further payment;11 and (e) the need not to unduly limit government's flexibility in the longer term. Subject to paragraph 3.2, failure by the private party to achieve Commercial Acceptance by the Date for Commercial Acceptance will effectively shorten the operating period (with resulting loss of projected income). 3.2 Extension Where failure to achieve Commercial Acceptance by the Date for Commercial Acceptance occurs as a result of a Relief Event or Compensation Event,12 the Date for Commercial 11 Or, if the private party is to retain the asset, amortise the capital value of the asset, to the extent necessary to enable the private party either to make economic alternative use of the asset or abandon it as redundant. April 2008 14 Partnerships Victoria Updated Standard Commercial Principles Acceptance will be extended. Whether or not this results in an extension of the expiry date (and therefore the operating term) will depend on the project-specifics and whether there is any special need for the project to terminate at a particular time.13 3.3 Liquidated damages • Erosion of the operating period as a result of late achievement of Commercial Acceptance is the preferred incentive for timely delivery. Although government will generally not seek to charge liquidated damages for late delivery in addition to erosion of the contract term, this may be necessary in circumstances where government’s potential delay costs are greater than the aggregate service payments it will not incur as a result of the erosion of the operating period. • Where the operating period is fixed from the Date of Commercial Acceptance but the project agreement provides that both the Date for Commercial Acceptance and the expiry date are extendable as a result of a Relief Event or Compensation Event (i.e. there is in practice no erosion of the contract term), liquidated damages may again be payable for the period of delay to defray government's delay costs.14 3.4 Earlier termination The agreement may terminate earlier than the expiry date as a result of various events,15 including as a result of breach, force majeure and voluntary termination by government. 12 See section 12 (Relief for construction delays). 13 The same considerations will apply to extensions of term consequent on Intervening Events during the operational phase - see section 17 (Intervening Events during the operational phase). 14 Subject to value-for-money considerations - see paragraph 13.1.1 in section 13 (Protection against late or insufficient service delivery). 15 See section 28 (Termination). April 2008 15 Partnerships Victoria Updated Standard Commercial Principles 4. Site conditions and suitability Principle The private party accepts overall responsibility for site conditions, including the adequacy of the site for delivering the project, regardless of whether the project site is selected by government. An exception may be made for latent geotechnical conditions and unidentified soil or groundwater contamination on a government selected High Risk Site where due diligence by the private party is physically or commercially impractical. 4.1 Site suitability 4.1.1 Onus on private party As part of the bid process, the private party must satisfy itself as to the commercial viability of delivering the proposed services from the site in accordance with the project specifications. 4.1.2 No representation or warranty While government may select the project site, it makes no express or implied warranty or representation with respect to the site, the site conditions or the adequacy of the site for the project. 4.1.3 Independent assessment The private party will be given opportunity to undertake its own due diligence as to site suitability and will acknowledge reliance on that independent assessment when entering the project agreement. 4.2 Site conditions 4.2.1 Private party responsibility • 'Site conditions' is very broadly defined to mean all circumstances and conditions on, in, around and affecting, the land, whether latent or otherwise. • Subject to very limited exceptions identified below, the private party will be responsible for, and will not be entitled to make any claim against government in connection with, the site or site conditions. • The cost of any necessary rectification or upgrade identified prior to execution of the project agreement will be reflected in the bid price. The risk of: April 2008 16 Partnerships Victoria Updated Standard Commercial Principles (a) costs exceeding what has been priced;16 or (b) unidentified site conditions, rests with the private party. 4.2.2 Exception Exceptions may be made for: (a) artefacts;17 and (b) latent geotechnical conditions and contamination18 at High Risk Sites.19 unidentified soil and groundwater Relief for latent geotechnical conditions will be limited to site areas: (a) which are inaccessible during the tender period for independent due diligence by either the private party's consultants and/or an independent consultant appointed by government; or (b) in respect of which, it is otherwise not reasonable or practical to expect the private party to perform its own full investigative surveys. The risk for such conditions will be shared: (a) by reference to an agreed schedule of rates for specified eventualities20 (with the private party bearing the risk of costing the unit price)21; or (b) by government and the private party each taking a percentage share of liability22 for items and eventualities not included in the schedule or where a schedule of rates is not used, over and above the site conditions assumed by the tender documentation. Relief under this paragraph will only be allowed where the private party has promptly notified government of the existence of the latent geotechnical conditions within a 16 The cost of bringing service infrastructure (such as water, electricity or telecommunications infrastructure) to a project greenfield site in order to deliver the contracted services, is an example of such a cost. Government effectively pays for it up-front (through the bid price) but the risk of the costs exceeding the price allowance on the bid is borne by the private party. 17 This is discussed in section 6 (Native title and artefacts). 18 See section 5 (Environmental issues) and in particular, paragraph 5.2.5 for sharing unidentified pre-existing contamination. 19 See paragraph 5.2.2 in section 5 (Environmental issues) for definition of High Risk Sites and Low Risk Sites. 20 The schedule of rates will be bid by the private party and will generally cover variable costs within the private party’s control eg, labour, cranage and truck movements. 21 To the extent it would not be value for money for certain components of that cost (e.g. landfill charges) to be priced up front, a competitive process will be agreed as part of the project agreement for pricing those components at the time of the request for relief. 22 The percentages will be determined by reference to factors such as the comprehensiveness of government's due diligence and the nature of the site. April 2008 17 Partnerships Victoria Updated Standard Commercial Principles reasonable period (to be agreed on a project-specific basis) after becoming aware of such conditions. The private party must consult with government and undertake all reasonable and proper steps necessary to best manage and limit the effects arising from the latent geotechnical conditions in a timely and effective way.23 4.2.3 Due diligence • Government will usually appoint independent consultants to undertake due diligence on the proposed site and relevant site conditions and prepare a site assessment report. • Government will make every attempt to ensure that the report is appropriately detailed and informative in documenting the nature and levels of site risk. However, government will not itself warrant the accuracy or completeness of the assessment and will disclaim making any representation based on the report. • Government will endeavour to either novate or otherwise procure the benefit of the report in favour of the private party.24 However, provision or novation of the report by government to the private party will be conditional upon the private party acknowledging that the report has been provided by government for information purposes only. The private party must expressly release government from any liability arising from the private party's receipt and future use of the report. • The private party may engage its own experts to peer review the report and advise it on the need for any additional assessment to be undertaken by the private party at its own cost. Government will cooperate with the private party and endeavour to give such access to the site as is reasonable and necessary for the carrying out of any additional assessment. • Where the private party is given the opportunity to undertake its own investigations and assessments as to site suitability it will, except for the exclusion in paragraph 4.2.2, be required to acknowledge that it has had such an opportunity and has acted in reliance on its own assessments and not on any report provided by government.25 • The private party must promptly advise government upon becoming aware of a site condition that differs materially from a site report and of measures proposed to be taken by the private party to deal with that site condition. 23 Prompt notification and express obligation to take steps to mitigate the effects are intended to encourage efficient management of latent geotechnical conditions. 24 To this end, government will seek to ensure that any consultancy agreement with the independent consultant allows for the benefit of the report to be novated or otherwise provided to the winning bidder. 25 Any rights in a government due diligence report that have been secured for the winning bidder will be exercisable by the private party against the independent consultant outside the project agreement and will not alter the acknowledgments as between government and the private party. April 2008 18 Partnerships Victoria Updated Standard Commercial Principles 5. Environmental issues Principle The private party will be responsible for environmental compliance. However, in most circumstances government will obtain environmental approvals fundamental to the use of the site for the project and, depending on the nature of the site, may share liability for unidentified pre-existing site contamination. Bidders are expected to factor into the bid price any necessary clean up costs for identified contamination. 5.1 Environmental approvals 5.1.1 Environmental impact assessments26 Depending on their nature and location, projects may trigger either or both Commonwealth and State requirements for environmental impact assessment. The significance of these processes is that they may be extensive, time-consuming and costly and, more importantly, they are fundamental to the ability of the site to be used for the project. 5.1.2 Commonwealth assessments • If the nature or location of the site raises the prospect that the project may impact on matters of national environmental significance under the Environment Protection and Biodiversity Conservation Act 1999 (Cth), government will refer the conceptual design for the project to the Minister for Environment and Heritage for determining whether it is a controlled action and, if so, submit the project for assessment under that Act. • Any further assessment that may be required as a result of departure from the conceptual design must be obtained by the private party. 5.1.3 • State assessments If the nature or location of the site makes such action relevant, government will approach the Minister for Planning prior to the request for tenders to ascertain whether a State environmental impact assessment (in the form of an Environment Effects Statement (EES), under the Environment Effects Act 1978 (Vic)) is required. If so, and if time permits, government will undertake the assessment based on a conceptual design to ensure that environmental considerations will not preclude the use of the site for the project. 26 Environmental impact assessment is a statutory process akin to an approval, but is in a separate category because of the potential length and breadth of the assessment process and resources it may consume. April 2008 19 Partnerships Victoria Updated Standard Commercial Principles • If for any reason27 an EES or supplementary EES is required after financial close, the private party will be required to accept the reasonable risk of the EES process, including delay to, or modification of, the project.28 • Government may agree to cap the private party's exposure to such risk beyond a specified time threshold for delay and financial threshold for modifications, but will do so only at a high level where delay and/or cost is inordinate and unforeseeable. 5.1.4 Other environmental approvals The private party bears the risk of obtaining all other environmental approvals required by the bid design, e.g. approvals under the Environment Protection Act 1970 (Vic). 5.2 Contamination 5.2.1 Required condition of site While the private party assumes liability for pre-existing contamination as part of its risk assumption in relation to site conditions generally, it may not be necessary for a project site to be pristine. So long as soil and groundwater standards appropriate to the nature of the land use are met, low level contamination may be present without triggering a need for remediation. In practice, therefore, the cost to the private party of actively managing contamination may be significantly less than the theoretical scope of its liability under the risk allocation.29 The project agreement will define contamination to exclude pre-existing low level contamination that is compatible with site usage and is not required to be remediated for the purposes of that project. It will also acknowledge that the private party may return the site at the end of the contract term in original condition in respect of such pre-existing low level contamination unless the measure of Contamination has changed over the contract term, in which case the Change in Law provisions will apply.30 5.2.2 High Risk and Low Risk Sites31 • Different risk allocations are appropriate for High Risk Sites and Low Risk Sites, given their differing degrees of risk. These are detailed below. • Low Risk Sites may be identified by reference to any of the following characteristics: (a) sites which would ordinarily be referred to as greenfield sites; 27 For example, delay in commencing the above process, significant reconfiguration of the project or a major variation to the conceptual design in the bid accepted by government. 28 The risk of such delay or modification is chiefly confined in the Partnerships Victoria context to large items of linear infrastructure. 29 Allocating contamination risk to the private party in a competitive context helps to ensure that clean-up occurs to commercially reasonable standards rather than placing a broad and unnecessary onus on government to deliver a pristine site. 30 See section 23 (Change in Law). 31 The distinction between High Risk Sites and Low Risk Sites is intended to reflect that specific sites will have different likelihoods of contamination and other latent conditions occurring and different risk allocation may therefore be appropriate depending on the nature of the specific site. April 2008 20 Partnerships Victoria • Updated Standard Commercial Principles (b) previous land use limited to rural, residential, light commercial or light industrial (e.g. office or warehouse); (c) minimal structures on site; (d) long-standing pre-existing reservation for the project; or (e) accessible for private party due diligence investigation. High Risk Sites may be identified by reference to any of the following characteristics: (a) sites which would ordinarily be referred to as brownfield sites; (b) previous industrial, heavy commercial or hospital land use likely to give rise to contamination and with existing structures or other site users compromising accessibility for due diligence; and (c) sites where extensive contamination or latent geotechnical conditions are likely and a full investigative survey is commercially impractical. 5.2.3 Due diligence • Consistent with the general approach to site deficiencies, government will usually commission an independent site assessment by qualified environmental consultants and provide the assessment to bidders. Government will make every attempt to ensure that the report is appropriately detailed and informative in documenting the nature and levels of site risk. However, government will not itself warrant the accuracy or completeness of the assessment and will disclaim making any representation based on the report. Government will endeavour to either novate or otherwise procure the benefit of the report in favour of the private party.32 • However, it will not be liable for any loss or liability arising from bidders relying on or using information contained in the independent site assessments. Provision and/or novation of these assessments to bidders shall be conditional on bidders acknowledging to government they have been provided for information purposes only and expressly releasing government from any liability or loss arising from the bidders receipt and use of the assessment. • The private party may wish to conduct its own review of any environmental report provided by government to assess the cost of any additional risks and/or work required to be undertaken.33 Government will cooperate with the private party and endeavour to give such access to the site as is reasonable and necessary to carry out any additional assessment. • Where independent site assessment is possible by the private party, it will be required to acknowledge that it has had an opportunity to conduct its own investigations and assessments and that it has acted in reliance on its own assessment (and not on any government-commissioned assessment). 32 To this end, government will seek to ensure that any consultancy agreement with the independent consultant allows for the benefit of the report to be novated or to otherwise be provided to the winning bidder. 33 See paragraph 4.2.3 in section 4 (Site conditions and suitability). April 2008 21 Partnerships Victoria • Updated Standard Commercial Principles Where independent assessment of a High Risk Site is not possible or is commercially impractical a mechanism for sharing risk may be substituted for exhaustive due diligence.34 5.2.4 Identified pre-existing contamination The anticipated costs of cleaning up identified contamination on a government-selected site (to the extent appropriate to the land use) will effectively be passed through to government through the bid price. 5.2.5 Unidentified pre-existing contamination • The risk of unidentified pre-existing35 contamination being discovered and requiring remediation during the contract term rests with the private party. • However, to keep bid costs down and save the costs of exhaustive due diligence, government may share the risk of unidentified pre-existing contamination in relation to High Risk Sites. Government will only share the risk if the contamination is located in an area of the site: (a) which is inaccessible during the tender period to the private party's consultants and/or any independent consultants engaged by government; or (b) in respect of which, it is otherwise not reasonable or practical to expect the private party to perform its own full investigative surveys. • To be eligible to receive any compensation for pre-existing contamination, the private party must have promptly notified government of the existence of the contamination within an agreed period of becoming aware of it (to be determined on a project-specific basis). • To the extent government shares unidentified pre-existing contamination risk, it will do so by: • (a) reference to an agreed schedule of rates for specified eventualities36 (with the private party bearing the risk of costing the unit price);37 or (b) sharing (on a percentage basis to be agreed) the actual costs of remediation for items and eventualities not covered by the schedule or where a schedule of rates is not used. In circumstances where government shares pre-existing contamination risk on a percentage basis, it will consider the following when determining an appropriate percentage share:38 34 See paragraph 5.2.5. 35 The fact that contamination was 'pre-existing' can be determined to a high level of probability by reference to the location and characteristics of the contamination and its probable historical source. 36 The schedule of rates will be bid by the private party and will generally cover variable costs within the private party’s control (e.g labour, cranage and truck movements). 37 To the extent it would not be value for money for certain components of that cost (e.g.. landfill charges) to be priced up front, a competitive process will be agreed as part of the project agreement for pricing those components at the time of the request for relief. April 2008 22 Partnerships Victoria Updated Standard Commercial Principles (a) comprehensiveness of site assessment by qualified environmental consultants commissioned by the State; and (b) ability of the private party to undertake due diligence of the site assessment report commissioned by the State and/or ability to undertake its own testing (where feasible). • A cost-sharing arrangement is preferable to government capping the private party's liability in that it incentivises efficient environmental management of the site and cost-effective clean up at all stages of the project, while significantly limiting the private party's exposure. • Upon becoming aware of the existence of any unidentified pre-existing contamination, the private party must consult with government to best manage and limit any effects and undertake all reasonable and proper remediation steps necessary to manage and clean-up the contamination and any effects arising from it in a timely and effective way. • Where government requires the private party to clean up any site to a standard which is higher than the level mandated under the project agreement,39 government shall bear 100 per cent of the cost difference between cleaning up the site to meet the mandatory requirements arising under the project agreement and cleaning up the site to meet the higher standard being required by government.40 5.2.6 Contamination during the contract term • Any contamination (low level or otherwise) resulting from on-site pollution during construction and operation will be the liability of the private party (unless directly caused by government in a core services model and not subject to private party management under the project agreement). • In conjunction with a general obligation to comply with environmental laws41 the private party must not: (a) use the site or allow it to be used so that any industrial waste or hazardous substance is abandoned; (b) allow any industrial waste to be dumped on the site or handled in a manner which is likely to cause an environmental hazard; or (c) release or emit anything (including noise) from the land into any part of the environment other than in accordance with a relevant approval. 5.2.7 • Claims and indemnities The private party cannot claim compensation in respect of the presence of contamination and must release government from any claim by it associated with any contaminant existing at, or emanating from, the site during the contract term, except to 38 By way of example, government has, on recent projects, shared on an 80 (government) : 20 (private party) basis. 39 See also paragraph 5.2.1. 40 This will generally be treated as a government initiated modification. 41 See paragraph 5.2.9. April 2008 23 Partnerships Victoria Updated Standard Commercial Principles the extent government has agreed to share contamination risk42 or the contamination is caused by a co-located core service not subject to private party management under the project agreement. • Subject to any cap on the private party's liability for claims and losses,43 the private party must indemnify government against all third-party liability arising in relation to any contamination existing on, over, under or emanating from, the site, except to the extent that government has agreed to share remediation costs44 or the contamination is caused by a co-located core service not subject to private party management under the project agreement. If government elects to cap the private party's liability, this cap will not limit the private party's liability to third parties.45 5.2.8 Clean up notices • The private party must comply with any Clean Up Notice46 issued in relation to the site or any pollution or environmental hazard caused by the private party. • Except to the extent that contamination is caused by a co-located core service and the private party has no management responsibility for it under the project agreement, the private party must not exercise any statutory power of recovery to recover its costs of compliance with a Clean Up Notice against government or its associates. • Ultimate liability for clean up costs will be allocated under the project agreement in accordance with the principles set out above. Reimbursement of the private party's costs will be limited to government's share (if any) of the remediation cost and will not include delay or disruption costs. 5.2.9 General environmental compliance The private party will be required to covenant that it will comply with all environmental laws. Environmental Laws are comprehensively defined to include statutes, regulations and other subordinate instruments relating to the environment (such as State environment protection policies and industrial waste management policies) and refer to mandatory legal requirements. Compliance with specific non-mandatory standards, guidelines and policies may be separately required as a term of the project agreement. 42 On the basis discussed in paragraph 5.2.5. 43 See paragraph 34.1 in section 34 (Indemnities, warranties and contractual claims). 44 On the basis discussed in paragraph 5.2.5. 45 Refer to paragraph 34.1.1 in section 34 (Indemnities, warranties and contractual claims). 46 A Clean Up Notice is any notice issued by the Environment Protection Authority under the Environment Protection Act 1970 (Vic) requiring investigation, remediation or monitoring of a site at which pollution or any other environmental hazard has occurred or is likely to occur. April 2008 24 Partnerships Victoria Updated Standard Commercial Principles 6. Native title and artefacts Principle Government will assume responsibility for native title and provide some relief in relation to the discovery of artefacts. The private party will not be able to claim delay or disruption costs except where it is directed to cease the contracted service. 6.1 Native title 6.1.1 Risk allocation • Government will be responsible for dealing with any application or claim made under any law relating to native title and for payment of compensation to native title holders (and in respect of which, it will indemnify the private party).47 • If there is a native title application, the private party must continue to perform its obligations under the project agreement (except to the extent prevented by the native title application)48 and, at government's cost, provide all reasonable assistance in connection with dealing with such application.49 • The private party will not have any claim against government for loss or damage suffered as a result of any native title application. However, the private party will be entitled to an extension of time and compensation relief where delays arise or additional costs are incurred (by the private party), as a result of any government or court direction to suspend or cease all or any part of the works or services because of a native title claim or application. 6.1.2 Due diligence • The report of site conditions issued with the request for tender will include information concerning the existence or potential existence of native title and any application on the register of the Native Title Tribunal. • Government will not, however, make any representation or warranty in respect of the existence or otherwise of native title.50 47 It is generally both more effective and less costly for government to assume the greater part of native title risk. This is because native title potentially subsists only over Crown Land and Aboriginal Affairs Victoria is ordinarily more able than the private party to nominate and communicate with indigenous representatives for the purpose of meeting notification and consultation requirements under the Native Title Act 1993 (Cth) and its State counterpart. 48 This includes being directed by government to suspend execution of the works and services and being required to cease performance by any applicable law or order of a court or tribunal. 49 See section 12 (Relief for construction delays). 50 See paragraph 4.2.3 in section 4 (Site conditions and suitability). April 2008 25 Partnerships Victoria 6.2 Artefacts 6.2.1 Damage minimisation Updated Standard Commercial Principles If an artefact is discovered at the site, the private party must, at its own cost and expense, take every reasonable precaution to prevent the artefact from being damaged or removed until appropriate arrangements (including the obtaining of approvals) have been made for dealing with, or removing, the item.. 6.2.2 Continuation The private party must continue to perform its obligations under the project agreement (except to the extent prevented by a requirement to properly manage the discovered item and subject to any relief referred to in paragraph 6.2.3).51 6.2.3 Compensation Government will not be liable to the private party for any loss or damage which the private party suffers or incurs as a result of the discovery of artefacts at the site. However, the private party will be entitled to an extension of time and compensation relief52 where a delay for any given event occurs or additional costs are incurred (by the private party) as a direct result of a government or court direction to suspend or cease all or any part of the works or services because of the discovery of an artefact (provided the cessation order does not result from a private party breach of its obligations in dealing with discovered artefacts).53 6.2.4 Property in artefacts All artefacts discovered on or under the surface of the site will, as between government and the private party, be the absolute property of government. 6.3 Memorandum of Understanding For projects where there is a high likelihood of significant Aboriginal artefacts being found, there may be a requirement that the private party enter into a Memorandum of Understanding with respect to protection of Aboriginal artefacts, including engaging or permitting Aboriginal monitors to attend the site during any excavation and providing for immediate stop work and site re-assessment if an artefact is discovered. 51 This includes being directed by government to suspected execution of the works and services and being required to cease performance by any applicable law or order of a court or tribunal. 52 See section 12 (Relief for construction delays). 53 The private party may be required to carry the artefacts risk for a specified period in projects where there is a high likelihood of artefacts being discovered. Whether the private party will be required to carry this risk and the length of any specified period will be considered on a project-specific basis depending on government's assessment of the nature of the site, the likelihood of the event occurring and the value-for-money obtainable if the private party prices the risk of such event occurring into its price. April 2008 26 Partnerships Victoria Updated Standard Commercial Principles 7. Planning and other approvals Principle Government will take responsibility for securing the foundation planning approval necessary to enable use of the site for the project. The private party is responsible for obtaining and complying with all other approvals (at its own cost). 7.1 Commonwealth approvals Subject to any approval or other determination under the Environment Protection and Biodiversity Conservation Act 1999 (Cth) obtained for a conceptual design,54 the private party is responsible for obtaining all relevant Commonwealth approvals and bears the risk of delay occasioned by legal challenges to the approvals. 7.2 State planning approvals 7.2.1 Use and development approvals Planning approval has two aspects, approval of the proposed land use (use) and approval of the proposed scale, design and configuration of buildings and works (development). 7.2.2 Permission for use Government will ensure that use of the land for the project is permitted under the planning scheme. Where the use is not already in existence or not permitted by the planning scheme, government will assume the risk of amending the planning scheme, prior to bid stage, to enable the land use to take place at the site. 7.2.3 Development approval Consistent with the private party's assumption of design risk, obtaining 'development' approval for the buildings and works (where a planning permit is required for such development) is the responsibility of the private party. 7.3 • Other site approvals Other site-based approvals such as permits and consents to disturb under the Heritage Act 1995 (Vic) or Archaeological and Aboriginal Relics Preservation Act 1972 (Vic) and works approvals and licences under the Environment Protection Act 1970 (Vic) are also the responsibility of the private party.55 54 As discussed at paragraph 5.1.2 in section 5 (Environmental issues). 55 Refer to paragraph 5.1 April 2008 Environmental approvals issues) for relevant environmental approvals. 27 Partnerships Victoria • Updated Standard Commercial Principles Similarly, obtaining any necessary industry accreditation is the responsibility of the private party. 7.4 Compliance The private party must, at its own cost, comply with the requirements of all approvals. April 2008 28 Partnerships Victoria Updated Standard Commercial Principles 8. Site access Principle While government will deliver the site for the project, third party use of the site may continue. The private party is primarily responsible for ensuring that it has the necessary access to the site to enable it to deliver the project, although government may, if it considers it necessary, negotiate a base-case access regime for inclusion in the project brief. Government will also retain rights of access sufficient to exercise its rights under the project agreement. 8.1 Availability Government will, if necessary, exercise its powers (including compulsory acquisition) to deliver the site for the purposes of the project and will bear the costs and risks of the acquisition process. 8.2 Third party occupants 8.2.1 Impact on private party Although government will deliver the site for the project, there may be other parties that are co-located on, or otherwise have access rights to, the site and whose interests impinge on the private party's ability to access the site to deliver the contracted services. 8.2.2 Access regime • Consistent with the allocation of design, construction, commissioning and operations risk to the private party, government will generally require the private party to negotiate and implement (and therefore, take the risk on) an access regime necessary to enable it to deliver the contracted services in accordance with the project agreement. • However, before going to the market government will, on a project-by-project basis, give due consideration to the importance and complexity of the access regime, the identity of the third parties (e.g. whether access is dependent on government-related entities) and any timing constraints and other barriers to the private party's ability to negotiate a commercially acceptable access regime with the relevant third parties (particularly during the bidding phase). This may lead government to negotiate a basecase access regime for inclusion in the project brief. • The base-case access regime will be treated analogously to a site conditions report56, with the onus on the private party to satisfy itself that the proposed access arrangements are adequate for delivery of the project or to propose and negotiate (directly with the third parties) additional access rights sufficient for its requirements. Government will not warrant the adequacy or completeness of the regime. 56 See paragraph 4.2.3 of section 4 (Site conditions and suitability). April 2008 29 Partnerships Victoria Updated Standard Commercial Principles 8.3 Access for government and third parties 8.3.1 Government access The private party must provide government with access to the site during construction at all reasonable times to the extent necessary to enable government to exercise any of its rights or perform any of its obligations under the project agreement. 8.3.2 Obligations With respect to other parties on or adjacent to the site, the private party must: (a) provide all things and take all measures necessary to protect and ensure the safety of people and property; (b) avoid or minimise unnecessary interference with the passage of people and vehicles and the operations or activities carried out of, on or from areas adjacent to the site; (c) prevent nuisance and unreasonable noise, dust, vibration and disturbance (including preventing such matters that would affect the project facility or areas and activities adjacent to the facility, beyond what is inherent in the provision of the services); and (d) unless required for purposes of public health or safety, not interfere (insofar as compliance with the project agreement permits) with the free movement of traffic into and out of, adjacent to, around, on or about the site or block or impair access to any premises. 8.4 Utilities 8.4.1 Interface Utilities are a special instance of third party site occupants giving rise to site availability issues. Management of the interface between the project and utilities is generally a matter for the private party. 8.4.2 Government facilitation As the presence of third party trunk infrastructure (e.g. telecommunications, gas, electricity, water and public transport infrastructure traversing the site) is a significant element of site risk for linear projects, government may agree to facilitate the private party's interaction with utilities by legislative or other means. This approach does not apply to accommodation-based projects, unless the interface with utilities is integral to the services provided under the project agreement. April 2008 30 Partnerships Victoria Updated Standard Commercial Principles 9. Tenure Principle Government will generally own the project site and grant the private party licences for construction. Depending on the scope of the services to be provided by the private party, it may be granted a lease, sub-lease or non-exclusive licence for the operating period, which will be subject to a government right of access. Government has no preference between granting a lease, sub-lease or non-exclusive licence provided that the structure most appropriate for the individual project is adopted and it is one which delivers best value for money. The term of the lease, sub-lease or licence will generally align with the term of the project agreement.57 9.1 Ownership For most projects, land will be in government ownership. This facilitates the vesting of the project assets in government at the end of the contract term and underpins government's step-in rights under the project agreement.58 9.2 Reservation of project land 9.2.1 Revocation of existing reservations Government owned land will frequently be subject to a reservation for a public purpose under the Crown Land (Reserves) Act 1978 (Vic). To enable the diversity of project uses and/or give the private party appropriate tenure, government may need to revoke the reservation.59 9.2.2 Reservation of land for the project Occasionally, in linear infrastructure projects, project land is re-reserved for the purposes of the project during the pre-construction and construction periods. In such a case, the reservation is generally revoked prior to the grant of the project lease. 57 This principle relates to the tenure of the core project. To the extent there is a related commercial development, appropriate tenure arrangements will be considered on a project-specific basis. 58 See section 30 (Step-in). 59 Revocation takes place in accordance with procedures under the Crown Land (Reserves) Act 1978 (Vic), which differ for temporary and permanent reservations. (Note that reservations under the Crown Land (Reserves) Act 1978 (Vic) differ from planning scheme reservations necessary to the process of compulsory acquisition.) April 2008 31 Partnerships Victoria Updated Standard Commercial Principles 9.3 Construction licence 9.3.1 Grant of licence Government will procure the grant to the private party of a licence or licences to use, and permit any construction subcontractor to use, the site during the construction period on the following terms. 9.3.2 • • Terms of licence The licence will: (a) be for the sole purpose of undertaking the project works (construction and any associated demolition and earthworks); (b) terminate upon the grant of a long-term lease or other access rights for the operation of the facility or upon earlier termination of the project agreement. Where more than one licence is granted, each licence is interdependent so that a breach of one licence is deemed to be a breach of each other licence. 9.3.3 Access to licensed area The private party is responsible for gaining access to and from the licensed area and is not entitled to any claim against government in connection with access or failure to gain or delay in gaining access to the licensed area.60 9.4 Tenure during the operating period 9.4.1 Nature of tenure • • 60 Government has no preference as to which form of tenure is utilised (as between a lease, sub-lease or non-exclusive licence) provided that the structure most appropriate for the individual project is adopted and it is one which delivers best value for money. The nature of tenure to be offered to the private party will be determined by government after consideration of various factors, including: (a) the access government requires for core services; (b) the extent of the contracted services; and (c) any relevant taxation considerations. After the Commercial Acceptance Certificate has been issued and if a lease is to be granted to the private party,61 government must promptly procure the execution of the lease by the appropriate government party. The lease will be subject to reservations enabling government to access the facility to deliver the core services and for any See paragraph 8.2 of section 8 (Site access). 61 Facility leases to the private party are a feature of infrastructure projects where government has little or no service delivery role outside step-in. However, they have also been granted in a number of accommodation-style projects. April 2008 32 Partnerships Victoria Updated Standard Commercial Principles other purpose authorised by the project agreement. Unless otherwise specified, the lease will be limited to use of the land solely for the purpose of delivering contracted services in accordance with the project agreement.62 • Alternatively, a head lease may be granted to a government or statutory entity responsible for delivery of the core services, which will in turn grant a sub-lease or other access entitlement to the private party for the purpose of delivering the contracted services. 9.4.2 Deemed lease The parties will agree to be bound by the lease or sub-lease from the agreed date of commencement of operations, regardless of whether execution of the lease or sub-lease by the government party is formally complete. 9.4.3 Effect of early termination of the project agreement If either party terminates the project agreement prior to the issuing of the Commercial Acceptance Certificate, the private party ceases to have any entitlement to call for the lease or other instrument conferring access for operations and has no further interest in or entitlement (whether legal or equitable) to the land. 9.5 Government access rights 9.5.1 Government need for access If a facility lease is granted to the private party, government's right of access to the site (including the right of the public to receive services from the site) will be secured either through reservations to the lease or by means of a sub-lease or non-exclusive licence-back to government for access to the leased area and use of the plant, equipment, furnishing and fittings for the purpose of exercising and performing any of its rights (including step-in rights) and obligations under the project agreement. Any sub-lease or licence for these purposes will be irrevocable and will not be able to be terminated or suspended for any breach by government. 9.5.2 Delivery of core services Government's concern to secure adequate tenure for the delivery of the core services may in some circumstances favour the grant of a head lease to the government entity responsible for delivery of the core services, with a sub-lease to the private party to enable the exercise and performance of its rights and obligations under the project agreement during the operating period. 9.6 Other licences or sub-leases The private party may be granted power during the operating period to grant sub-leases and licences over areas leased or sub-leased to it, subject to: 62 In certain circumstances the private party may, for tax and other reasons, seek a licence instead of a lease. However, the greater security of tenure associated with a lease favours a lease in most circumstances. April 2008 33 Partnerships Victoria Updated Standard Commercial Principles (a) the grant being for a use or purpose for which a sub-lease, licence or other instrument may be granted under the project agreement; (b) the term of the grant (including options) not exceeding the balance of the project term then remaining; (c) the grant being subject to a condition to the effect that the rights automatically terminate on termination, surrender or expiry of the private party's lease or sublease, without any right, action or claim by the grantee against government; and (d) the grant not reducing the ability of government to exercise its rights or of either party to comply with its obligations under the project agreement. 9.7 Improvements 9.7.1 Improvements to vest in government on expiry Any improvement which has not already vested in government will be transferred to government at the end of the contract term. 9.7.2 Payment for value of the improvements Generally, the value of the facility will have been paid for through the service fees and the private party can make no claim for payment for the assets upon their transfer to government. However, depending on the nature of the asset, its projected residual value and which party has assumed the end-of-term asset risk, a pre-determined amount may be payable to the private party by government for the facility. April 2008 34 Partnerships Victoria Updated Standard Commercial Principles 10. Design Principle The private party is responsible at its own cost, for designing the facility so as to achieve the output specifications for the contracted services. 10.1 Design obligations 63 The private party must design the facility so that the facility (when complete) will be fit for its intended purposes and uses as specified in, or reasonably inferred from, the functional brief as at the date of the project agreement and so that the private party can deliver the contracted services to specification (including, meeting the output specifications for government core services). 10.2 Fitness for purpose warranty The private party will provide a warranty that the facility, as designed and constructed, is (and will be during the contract term) fit for the intended purposes and uses specified in, or reasonably inferred from, the functional brief and the project agreement as at the Date for Commercial Acceptance.64 10.3 Mandatory design guidelines The private party must comply with any mandatory design guidelines as set out in the functional brief. The fitness for purpose warranty will be given in respect of the design and works as developed to meet the mandatory guidelines. 63 The private party is not relieved of any of its design obligations by subcontracting any of the design works to a design consultant. Issues associated with subcontracting are dealt with in section 20 (Subcontractors). 64 The functional brief (including any private party departures agreed to by government) will form part of the project agreement. Government recognises the need (given the requirement for a fitness for purpose warranty) for the functional brief to adequately describe the output specifications and disclose relevant operating protocols. However, government does not represent or warrant that adherence to the functional brief will ensure fitness for purpose. April 2008 35 Partnerships Victoria Updated Standard Commercial Principles 10.4 Design development process 10.4.1 Basic design development The private party must develop the basic design proposed in its bid (and set out in the project agreement) in accordance with an agreed consultative process and submit all final design documentation (and any amendments) to government for comment.65 10.4.2 • • Government comment Government (through the Project Director)66 will have the right, within specified periods, to comment on the detailed design documentation (and the accompanying drawings and specifications) submitted by the private party to the extent that: (a) they are not consistent with the design requirements set out in the project agreement or the private party's bid proposal or the last approved drawings and specifications; and (b) in government's reasonable opinion, they will adversely affect the private party's ability to deliver the contracted services to specification or government's ability to deliver the core services. Construction on the basis of the design documentation cannot occur until the specified period for comment by government has expired. 10.4.3 Parties to agree amendments Government and the private party must confer (at their own cost) to address government's comments and agree necessary amendments. 10.4.4 Resolution of disputes If the parties cannot agree on the necessary amendments to the detailed design documentation or the private party disagrees with government's comments, the matter may be referred to an independent expert for resolution. 10.4.5 Government-initiated modifications If the design complies with the output specifications and the private party's design as at contractual close, but government for its own reasons seeks a variation, this will constitute a government-initiated modification.67 65 For complex social infrastructure projects, Government will generally specify each stage of the design development process and the activities and level of documentation required at each stage (allowing for appropriate review periods). 66 See discussion in paragraph 11.5.7 in section 11 (Construction and commissioning) as to whether an independent completion certifier will be appointed to monitor and assess design preparation. In an accommodation project, where the private party is providing functional space from which government will deliver its core services, government needs to be confident of the suitability of the design. Accordingly, the Project Director will monitor the design development on government's behalf. In linear infrastructure projects, where demand risk is transferred to the private party and there is a less significant interface risk, there is more flexibility to allow for the appointment of an independent completion certifier. April 2008 36 Partnerships Victoria 10.4.6 Updated Standard Commercial Principles Effect of government participation Government has no obligation to comment or identify errors, omissions or inaccuracies in the design documentation. Neither its participation nor that of the independent expert in the design development phase relieves the private party of its design obligations (including warranties) or constitutes a representation by government as to the compliance of the design with project specifications. 67 See section 22 (Modifications). April 2008 37 Partnerships Victoria Updated Standard Commercial Principles 11. Construction and commissioning Principle The private party is responsible at its own cost, for constructing and commissioning the facility within the required time period, to deliver the output specifications for the contracted services. 11.1 Construction and commissioning obligations The obligations set out in paragraph 10.1 in section 10 (Design) as to fitness for purpose also apply to construction and commissioning.68 11.2 Construction updates and reports 11.2.1 Provision of construction progress reports During the construction phase, the private party must provide government with written reports outlining the progress of the works by reference to the construction program.69 The form of the construction program will be agreed with government, based on an indicative program prepared by the private party prior to contract execution. 11.2.2 Effect of government involvement The provision of progress reports or updated construction programs and their acceptance (or otherwise) by government does not relieve the private party of its construction and commissioning obligations. 11.3 Project committee A project consultative and advisory committee comprising government and private party representatives will be established for the design and construction phase. 68 The private party is not relieved of its obligations and liabilities under the project agreement by the private party subcontracting the performance of any works. Issues associated with subcontracting are dealt with in section 20 (Subcontractors). 69 Refer to Template H of the Partnerships Victoria Contract Management Guide for a detailed treatment of the 'Construction Stage reporting guidelines'. In addition to meeting the reporting requirements set out in Template H, the private party must also provide regular quality assurance audit reports. April 2008 38 Partnerships Victoria Updated Standard Commercial Principles 11.4 Inspections 11.4.1 Government's right to inspect and test • Government (and any person it authorises) has the right to enter, inspect and test any part of the works during the construction and commissioning phase. Except in the case of an emergency, government must give reasonable prior notice. The private party must provide all reasonable assistance required by government. • When exercising its right to enter and inspect, government must not cause any unnecessary inconvenience to the private party, any subcontractor or other authorised user of the site and will comply with the reasonable health and safety and other security requirements of the private party or any of its subcontractors that are notified to government by the private party. • The cost of any government inspection and testing will be borne by government unless the inspection or test shows that the design and/or construction is not consistent with the specifications, functional brief or other requirements set out in the project agreement. 11.4.2 Compensation for interference with works Government will compensate the private party for any loss or damage arising from a failure by government or any of its authorised persons to comply with government's obligations while on site, as set out under paragraph 11.4.1. 11.5 Commissioning, operational and commercial acceptance 11.5.1 Critical milestones Service commences upon satisfaction of clear and objective commissioning tests identified in the functional brief. The critical milestones in a project are 'Technical Completion' (also known as Operational Completion) and 'Commercial Acceptance' (also known as Final Completion). 11.5.2 • 70 Technical Completion For Technical Completion to be achieved: (a) works must be completed except for minor defects70 and be fit for their intended purpose; (b) all commissioning tests must have been carried out and a commissioning certificate issued by the completion certifier;71 See discussion in paragraph 11.6. 71 See discussion in paragraph 11.5.7. This role may be carried out by the Project Director. The completion and commissioning tests and generally the criteria for determining whether Technical Completion and Commercial Acceptance have been achieved will be agreed as part of the project agreement. April 2008 39 Partnerships Victoria • Updated Standard Commercial Principles (c) all consents, approvals, authorisations and certificates required for the works to be occupied and used for their intended purposes (including a certificate of occupancy) must have been obtained and complied with; and (d) all construction machinery, equipment and materials must have been removed from the site. Within a specified period after the completion certifier considers that Technical Completion has been reached, the completion certifier72 must issue a 'Certificate of Technical Completion' and advise of any defects and other obligations that remain outstanding.73 11.5.3 Commercial Acceptance • The final commissioning period commences once Technical Completion has been achieved. • For Commercial Acceptance to be achieved: • (a) a Certificate of Technical Completion must have been issued; (b) the private party must have provided government with all material documents and information (including all operating manuals); (c) the private party must have provided copies of relevant insurance policies; (d) if applicable, any liquidated damages payable must have been paid; (e) all notified defects must have been rectified except for minor defects identified in paragraph 11.6.1, in respect of which the parties must have agreed a regime and timeframe for rectifying such defects; and (f) all other tests and requirements required to satisfy the completion certifier that operations (in accordance with output specifications) can commence must have been satisfied.74 If the completion certifier is satisfied Commercial Acceptance has been reached, the completion certifier must within a specified period issue a 'Commercial Acceptance Certificate'. 72 See discussion in paragraph 11.5.7. The discussion in paragraph 11.5.7 also applies to the completion certifier's role during Commercial Acceptance commissioning. 73 If the completion certifier does not consider that Technical Completion has been achieved, he/she must promptly notify the private party. 74 Projects involving phased completion may require additional tests to be satisfied for Technical Completion and Commercial Acceptance to be reached, such as equipment or people from an existing site having been relocated. In addition, the completion procedure for projects involving government furnished equipment will need to allow for the installation and testing of such equipment. Risk allocation issues in respect of such equipment will be considered on a project-by-project basis. April 2008 40 Partnerships Victoria 11.5.4 Updated Standard Commercial Principles Commencement of payment Payment of the service fee will commence (assuming full service delivery) from the later of the Date the Commercial Acceptance Certificate is issued and the target Date for Commercial Acceptance.75 11.5.5 Phased commencement Commercial Acceptance and commencement of payment for services may begin at different times for different aspects of staged projects. Examples include bundled projects where different facilities will commence operations at different times, projects where there is to be a progressive relocation of equipment from an existing facility to the new facility and linear infrastructure projects where there is to be phased completion of different linear sectioning. Structuring service payments for phased service commencement is discussed in section 18 (Payment provisions). 11.5.6 • • • Failure to achieve Technical Completion or Commercial Acceptance Government may engage an independent expert (on or after a specified period after the site is made available to the private party)76 to assess: (a) whether the private party is likely to achieve Technical Completion or Commercial Acceptance by the date for Technical Completion and the Date for Commercial Acceptance (respectively); and (b) whether the private party is likely to achieve Commercial Acceptance before the Sunset Date. An Event of Default (allowing the private party a cure period) will occur if: (a) the independent expert considers that there is no reasonable prospect that the private party will achieve Technical Completion or Commercial Acceptance by the Date for Technical Completion and the Date for Commercial Acceptance (respectively;,77 or (b) the private party fails to reach Technical Completion or Commercial Acceptance by the Date for Technical Completion and the Date for Commercial Acceptance (respectively). Although government will generally treat a failure to reach Technical Completion by the Date for Technical Completion as a separate event of default, it may consider waiving this requirement78 in circumstances where achievement of Commercial Acceptance is conditional on the private party having provided government with sufficient time to 75 Government may, in limited circumstances, consider early payment (i.e. where Commercial Acceptance occurs prior to the target Date for Commercial Acceptance). 76 This period will be determined on a project-specific basis having regard to the expected construction period. It will expire after the date on which the private party may be defaulted if it has not commenced works (see paragraph 27.1(c) in section 27 (Default)) but will generally be before the date for Technical Completion. 77 See paragraph 27.1 in section 27 (Default). 78 Thereby limiting the events of default to a failure to meet Commercial Acceptance by the Date for Commercial Acceptance. April 2008 41 Partnerships Victoria Updated Standard Commercial Principles transition into and test the functionality of the facility. This period will be specified by government on a project-specific basis. • A Default Termination Event (giving government an immediate right to terminate the project agreement) will occur if: (a) the services do not become available by the Sunset Date (i.e, the 'drop dead' date);79;or (b) the independent expert considers that there is no reasonable prospect that the private party will achieve Commercial Acceptance before the Sunset Date.80 11.5.7 • Completion certifier The nature of the project will affect the costs and benefits of utilising an independent completion certifier rather than relying on design and construction monitoring and assessment by the Project Director. Factors to be considered include the following: (a) the completion certifier's independence and technical expertise which could minimise the risk of a party disputing a decision; (b) requirements of the private party's financiers (noting that government will not agree to financiers alone appointing the completion certifier); (c) the cost and time consequences of involving an additional party in the process; (d) from government's perspective, minimising the risk of take back of design and construction risk; and (e) government insistence on assessment by the Project Director where there would be significant residual risk to government if the private party fails to adequately design and construct the facility. • A completion certifier is appointed jointly by government and the private party. • Determinations and decisions by the completion certifier are generally final and binding on both parties.81 11.6 Defects 11.6.1 Identified defects Commercial Acceptance is not achieved (and payment of the service fee does not commence) until all identified defects have been rectified. The only exceptions are minor defects which: 79 See paragraph 28.1.1 in section 28 (Termination). Further, if the contracted services are not available by the Date for Commercial Acceptance, government may be entitled to liquidated damages. See section 13 (Protection against late or insufficient service delivery). 80 The independent expert will be prevented from making such a determination if the private party is complying with an agreed cure plan arising from such a default. See paragraph 27.2.1 of section 27 (Default). 81 Government will consider, on a project-specific basis, categories of decisions which are subject to appeal (e.g. on questions of law or above a cap). April 2008 42 Partnerships Victoria Updated Standard Commercial Principles (a) individually or in aggregate do not prevent the facility from being used for its intended purpose; and (b) although they cannot be immediately rectified, can be rectified within a reasonable period (to be agreed on a project-specific basis) following commencement of operations without unreasonable noise, disturbance or interference with or adverse effect on the intended use of the facility and any adjoining premises. Any deferred minor defects need not be immediately rectified, but must be rectified as directed by government in accordance with a rectification plan (which will include appropriate timeframes for completion of the rectification works to be determined on a project-specific basis) to be agreed by the parties as a condition of Commercial Acceptance. Failure to perform the rectification works in accordance with the agreed rectification plan will have financial consequence. For example, reduced service payments until the rectification works are completed. 11.6.2 Defects liability period During the specified defects liability period, the private party must rectify all defects which: • exist at Commercial Acceptance (defects other than minor defects referred to in paragraph 11.5.3(e) will have been rectified as a condition precedent to Commercial Acceptance); or • are discovered during the specified defects liability period (usually 12 months from Commercial Acceptance). Where the private party fails to so rectify, government may either direct rectification by the private party (in which case a further defects liability period will apply to such defect) or may itself rectify (or have a third party rectify) such defects at the private party's cost.82 82 Such amount shall be a debt due and payable by the private party to government. Government may set-off such amount against amounts owing to it or make a demand for such amount under any construction bond and defects bond provided in respect of the project. Nothing in paragraph 11.6.2 will affect the private party's obligations to deliver the contracted services to specification (including, all technical specifications, maintenance and aesthetic requirements) or government's right to abate payments. It is intended that rectification of any defect identified during the contract term following the expiry of the defects liability period (and any failure to rectify such defects) will be dealt with primarily through the specifications and abatement regime and, to the extent appropriate, other government rights of recourse under the project agreement (e.g. indemnities, performance bonds). April 2008 43 Partnerships Victoria Updated Standard Commercial Principles 12. Relief for construction delays Principle No relief will be given to the private party for delays, the occurrence or effects of which are within the private party's control. A delay which is not in the private party's control, but is best managed by the private party, will also be allocated to the private party, subject to limited relief. Government will generally only compensate the private party for losses incurred by the private party as a result of events which are within government's control and should therefore be at government's risk. 12.1 Form of relief Relief can take the form of 'time' only or 'time and money' depending on the cause of the delay. 12.2 Time relief 12.2.1 Threshold requirements • Relief may be given if the event affects a critical activity on the critical path and directly causes a delay to achievement of completion of the facility. This will be assessed by considering the updated master works program and relevant sub-programs referred to below.83 • The private party must give written notice of the delay, the effect of such delay and full details of the relief claimed, to government within a reasonably specified time after it has become aware of the delay. • The master works program and all relevant sub-programs must be updated on a monthly basis84 to ensure that at all times it accurately and transparently reflects the progress of the works program. The Project Director or Independent Reviewer shall be entitled to review and comment on any such updated programs and the private party will respond promptly to any requests for further information regarding the accuracy of the master works program and relevant sub-programs.85 83 The critical path for the purposes of allowing extensions of time will be determined by considering the ‘as bid’ master works program and sub-programs, as updated and adjusted to allow for extensions of time which have been allowed under the project agreement. 84 Or such other period as is considered appropriate on a project-specific basis. 85 However, as noted above, only the 'as bid' master works program and sub-programs (as adjusted from time to time to reflect time relief given to the private party) will be used to determine the critical path or allow extensions of time. The mechanism for calculating whether time relief is available must operate in a transparent manner and government must be able to clearly identify how any original contingency from the ‘as bid’ version is being used in any updated versions of the original master works program and sub-programs. April 2008 44 Partnerships Victoria 12.2.2 • Updated Standard Commercial Principles Extension of time events Subject to the threshold requirements in paragraph 12.2.1 being met, delays caused by any of the following will constitute an extension of time event (EOT Event)86 for which time relief will be given: (a) breach of any project document by the government party;87 (b) any act or omission of the State or relevant government-related party88 (but only in their capacity as a contracting party), other than any such act or omission which is authorised, permitted or otherwise in accordance with a project document89; (c) fire, flood or explosion (which is not also a Force Majeure Event); (d) failure by a statutory authority to carry out works or provide services unless the statutory authority, in failing to carry out the works or services, is acting in accordance with or pursuant to its statutory powers, duties and discretions or obligations; (e) site specific blockade or an embargo; (f) industrial action, but only to the extent that it directly affects the project (whether it also affects the relevant project related industries, or a significant segment of them,90 and the private party can demonstrate that the action results directly from an act or omission of the contracting government party or any of its employees at the facility/site;91 (g) any event or occurrence (outside the control of either party) which causes lack of possession at or access to the project site other than any event or occurrence arising from third party rights to use or access the site; 86 These EOT Events may be defined by various names in different projects (e.g. 'Extension Events' or 'Government Extension Events') as applicable. 87 This only applies to project documents to which the State is a party. Accordingly, government's obligations must be limited and clearly specified. 88 What constitutes a government-related party will depend on the nature of the project. Although it is intended to capture government employees, consultants and other parties at the site which are appointed by government or whom government effectively controls (for example, as a result of delivering core services). In particular, consideration will be given to the nature of each of the contracted services and core services and the level of interface between them. 89 The State’s role as contracting party is separate from its role as being responsible for the general administration of government affairs. Accordingly, the relief events in paragraphs (a) and (b) only capture acts or omissions (including breaches) of the State in its capacity as a contracting party, not acts and omissions carried out in its role as general administrator of government affairs. Please also refer to paragraph 1.6.4 (Right to compensation). 90 The project related industries will depend on the nature of the project. However, they will generally include the construction or building maintenance industries. 91 Industrial action caused or motivated by opposition to PPPs will be deemed not to be the direct result of a government act or omission. April 2008 45 Partnerships Victoria Updated Standard Commercial Principles (h) a government or court direction to suspend or cease all or any part of the works because of a native title claim or application or as a result of the discovery of an artefact (provided the cessation order does not result from a private party breach of its obligations in dealing with discovered artefacts); (i) delay in any works to be carried out by government which are required to allow for the relocation or decanting of equipment, staff or users of the facility (e.g. students, patients etc);92 (j) government-initiated modifications;93 (k) compensable changes in law as set out in section 23 (Change in Law);94 and (l) force majeure.95 • Time relief will not be given when any of the above events are caused or to the extent they are contributed to (directly or indirectly) by the private party or any subcontractor (and in each case, whether as a result of their action or inaction including, as a result of a breach of their obligations under the project documents). • The exact nature of the time relief events will depend on the project specifics. The above is not intended to be an exhaustive list of time relief events for all projects. Based on the risks of a specific project, government may introduce additional relief events or remove some of the above relief events. However, government will not provide relief for either the occurrence or effects of delays which are within the private party's control. This includes where the private party should have put in place appropriate contingency plans so as to reduce or avoid any effects on its ability to perform its obligations under the project agreement. • Some EOT Events will also qualify as Compensation Events under paragraph 12.3.2. 12.2.3 • Period of extension and other relief Government96 will (acting reasonably) determine: (a) the period by which the Date for Technical Completion and/or the Date for Commercial Acceptance are to be extended as a result of the delay;97 and 92 The exact nature of this relief event will depend on the nature of the project and government's particular phasing or transitional requirements. 93 See paragraph 22.1 in section 22 (Modifications) for process for giving relief to be provided to the private party in these circumstances. See also footnote 81. 94 See paragraph 23.3 in section 23 (Change in Law) for relief to be provided to the private party in these circumstances. See also footnote 81. 95 See paragraph 24.2 in section 24 (Force Majeure) for relief to be provided to the private party and process for providing such relief in these circumstances. See also footnote 81. 96 The Independent Reviewer is the independent party appointed by the private party and the State under the project documents to deal with areas such as completion testing and extension of time issues. Generally government will refer to the Independent Reviewer when making determinations on extensions of time and relief from other obligations. On a project-specific basis, government may consider appointing the Independent Reviewer to directly carry out this role. 97 This will be subject to the private party's right to refer any such government determination to either the Independent Reviewer or other independent expert for dispute resolution. April 2008 46 Partnerships Victoria Updated Standard Commercial Principles (b) the nature of relief from any other obligations as is reasonable given the nature of the EOT Event.98 • Where an extension of the Date for Commercial Acceptance occurs as a result of an EOT Event described in paragraphs 12.2.2(a), 12.2.2(b) 12.2.2(f), or 12.2.2(h), the Sunset Date will be extended by the same period, although the Date for Commercial Acceptance will not at any time be extended beyond the Sunset Date (as extended) for any EOT Event.99 12.2.4 Concurrent delays If delays result from multiple causes including a material event which is not an EOT Event, the private party will not be given time relief for the concurrent period of delay unless the EOT Event is also a Compensation Event.100 12.2.5 Acceleration If the progress of the works is delayed by an EOT Event, government will have the option (at its cost) of requiring the private party to accelerate the works, instead of extending time. In this instance, government will pay for the private party's incremental costs (but with no allowance for a profit margin by the private party). 12.2.6 Mitigation The private party will only be given an extension of time if, and to the extent that, it can demonstrate (to the reasonable satisfaction of government) that all proper and reasonable steps to prevent or minimise the risk of the occurrence, duration and consequences of the delay were taken having regard to the nature of the site and the works. The private party will notify government as soon as it becomes aware of any further information relating to the EOT Event. 98 However, the private party will not be granted relief from those obligations which government would ordinarily expect the private party to comply with during an EOT Event (i.e., any obligation to reinstate or to provide certain critical facility management services which government would ordinarily expect to be provided during such events). 99 The Sunset Date will only be extended in the limited circumstances identified. Where failure to meet the Sunset Date is caused by a force majeure event, the private party's obligation to meet the Sunset Date will be suspended in accordance with the regime in section 24 (Force Majeure) and government will not be able to claim an Event of Default or Default Termination Event on the basis of such failure. To the extent the force majeure event continues for a specified period, either party will be able to terminate on the basis of a Force Majeure Termination Event in accordance with the regime set out in section 24 (Force Majeure). Government also recognises (in respect of those events where the Sunset Date will not be extended) the importance of ensuring an adequate time period between the Date for Commercial Acceptance and the Sunset Date. Where the failure to meet the Sunset Date is caused by a government initiated modification or compensable change in law, the private party's obligation to meet the Sunset Date will be suspended in accordance with the regime in section 22 (Modifications) and 23 (Change in Law), respectively. 100 This drafting assumes that the scope of 'Compensation Events' is limited to events caused by government. Relief will only be given for concurrent delays where the Compensation Event has been caused by government. April 2008 47 Partnerships Victoria 12.2.7 Updated Standard Commercial Principles Termination event A termination event will be deemed to have occurred if, at any time, an independent expert determines that there is no reasonable prospect that the private party will achieve Commercial Acceptance by the Sunset Date.101 12.3 Compensation relief 12.3.1 Threshold requirements • The delay or disruption must qualify as a 'Compensation Event'.102 • The private party must notify government and submit a claim to government for its delay costs strictly in accordance with specified procedures. 12.3.2 Compensation Events The following sub-set of EOT Events (being government-initiated events), may constitute Compensation Events:103 (a) breach of any project document by the government party;104 (b) any act or omission of the State or relevant government-related party105 (but only in their capacity as a contracting party), other than any such act or omission which is authorised, permitted or otherwise in accordance with a project document106; (c) government-initiated modifications;107 (d) compensable changes in law as set out in section 23 (Change in Law);108 101 See paragraph 11.5.6 of section 11 (Construction and commissioning). 102 See paragraph 12.3.2. 103 As with time relief events, the exact nature of these events may need to be amended to reflect the project specifics. However, the definition must underpin and not undermine the agreed risk allocation for the project. 104 This only applies to project documents to which the State is a party. Accordingly, government's obligations must be limited and clearly specified. 105 106 See footnote 81 for a definition of government-related party. The State’s role as contracting party is separate from its role as being responsible for the general administration of government affairs. Accordingly, the relief events in paragraphs (a) and (b) only capture acts or omissions (including breaches) of the State in its capacity as a contracting party, not acts and omissions carried out in its role as general administrator of government affairs. Please also refer to paragraph 1.6.4 (Right to compensation). 107 See section 22 (Modifications) for relief to be provided to the private party in these circumstances. 108 See paragraph 23.3 in section 23 (Change in Law) for relief to be provided to the private party in these circumstances. April 2008 48 Partnerships Victoria Updated Standard Commercial Principles (e) delay in any works to be carried out by government which are required to allow for the relocation or decanting of equipment, staff or users of the facility (e.g. students, patients etc);109 (e) a government or court direction to suspend or cease all or any part of the works because of a native title claim or application or as a result of the discovery of an artefact (provided the cessation order does not result from a private party breach of its obligations in dealing with discovered artefacts); and (f) industrial action, but only to the extent it directly affects the project (whether it also affects the relevant project related industries (or a significant segment of them)110) and the private party can demonstrate that the action results directly from an act or omission of the contracting government party or any of its employees at the facility/site.111 Compensation will not be allowed when the relevant event was caused or to the extent it is contributed to (directly or indirectly) by the private party or any subcontractor (and in each case, whether as a result of their action or inaction including, as a result of a breach by the private party of its obligations under the project documents). The exact nature of the Compensation Events will depend on the project specifics. The above is not intended to be an exhaustive list of Compensation Events for all projects. However, any extension will be limited to events caused by government. Compensation Events will also qualify as EOT Events under paragraph 12.2.2. 12.3.3 Compensation amount • The private party will be entitled to its reasonable costs and expenses (including incremental funding costs) arising from the delay caused by a Compensation Event (Delay Costs), based on its written claim for costs as reasonably assessed by government112 less any insurance proceeds paid or payable to the private party for the loss or damage113. • Government has the option of compensating the private party for Delay Costs by way of: (a) an adjustment to the service fee; (b) a lump sum payment; or 109 The exact nature of this relief event will depend on the nature of the project and government's particular phasing or transitional requirements. 110 The project related industries will depend on the nature of the project. However, they will generally include the construction or building maintenance industries. 111 Industrial action caused or motivated by opposition to PPPs will be deemed not to be the direct result of a government act or omission. 112 Any government determination in respect of Delay Costs will be subject to the private party's right to refer such determination to an independent expert for dispute resolution. Furthermore, in certain projects, the daily dollar value of delay costs (at various project stages) will be a bid item. 113 Project Co will be required to make a claim under its insurance policy for any damage or liability arising as a result of the compensable event occurring. Project Co will not be permitted to remedy the damage prior to lodging a claim with the insurer unless expressly permitted by the State. April 2008 49 Partnerships Victoria (c) Updated Standard Commercial Principles subject to the private party's agreement, extending the operating term. • Where option (a) is adopted and the amount the private party must fund up-front is above a specified threshold, the private party must use its best endeavours to obtain competitive funding for such costs. If, having used its best endeavours, the private party is unable to obtain funding acceptable to government, government will pay for those costs by way of a lump sum payment. • The service fee will be adjusted or a lump sum payment will be determined in accordance with the service fee adjustment principles for the project.114 • The financial model will be adjusted in accordance with the service fee adjustment principles to reflect the Delay Costs. 12.3.4 Mitigation Delay Costs are only payable to the extent that the private party has taken all reasonable measures to avoid or minimise the occurrence of the Delay Costs having regard to the nature of the site and the works. The private party must provide evidence that it has used reasonable endeavours (including, where practicable, use of competitive quotes) to ensure its subcontractors minimise increases in costs and maximise any reduction in costs. 114 See paragraph 18.4 in section 18 (Payment provisions). April 2008 50 Partnerships Victoria Updated Standard Commercial Principles 13. Protection against late or insufficient service delivery Principle Where non-payment or abatement of the service fee is insufficient to compensate government for costs and losses incurred as a result of late or insufficient service delivery, government may require additional protections from the private party such as liquidated damages, performance bonds or parent guarantees. 13.1 Liquidated damages 13.1.1 Value for money Government recognises that an entitlement to liquidated damages115 may result in higher bid costs. Accordingly, whether liquidated damages are payable and, if so, the amount payable will depend on whether they offer government value for money.116 For most projects, the incentive for timely achievement of Commercial Acceptance will be the impact on the operating term.117 However, where the private party is granted an extension of the operating term as a result of a Relief Event or a Compensation Event, government may require liquidated damages for a delay in achieving Commercial Acceptance. Such damages are to defray government's costs arising from the delay (e.g. the cost of bridging venues or services). 13.1.2 Genuine pre-estimate The rate of liquidated damages payable in any project must be a genuine pre-estimate of the costs and losses government is likely to incur from the delay in service delivery. Otherwise the amount may be judged to constitute a penalty and will not be enforceable. Liquidated damages may be reduced where the private party provides adequate temporary accommodation. 13.1.3 Sole and exclusive remedy Where payable, liquidated damages will be government's sole and exclusive remedy for delay. However, they do not affect or limit government's legal rights in relation to aspects or consequences of an event other than delay costs. 115 As distinct from the liquidated damages payable by the construction subcontractor to the private party for any period of delay. 116 In making such a determination consideration will be given to other remedies available to government under the project agreement to recover costs arising from a private party default (e.g. indemnities). 117 See section 3 (Contract term). April 2008 51 Partnerships Victoria 13.1.4 Updated Standard Commercial Principles Security for liquidated damages Government generally requires the private party to provide security for liquidated damages through bonds or guarantees issued either by the private party or its subcontractors. 13.2 Performance bonds 13.2.1 Performance bond during the construction phase and defects liability period 118 • For value for money reasons, government will generally not seek a direct performance bond from the private party for the construction phase.119 Instead it will require the private party to procure a performance bond (issued in the private party's favour) from the construction subcontractor, guaranteeing the subcontractor's construction obligations. This would generally, in any event, be a requirement of the private party's financiers who will have security over the private party's right to claim.120 • Government must be satisfied that its interests are adequately addressed and protected by any bond procured from the construction subcontractor. As part of the project brief, government will identify its minimum bonding requirements including, in respect of: (a) the quantum, rating and duration of the bond; and (b) the bases upon which the bond can be drawn (including requirements that government be notified when a call is made on the bond). Government's minimum requirements will seek to ensure that the interests of the private party, financiers and government are appropriately aligned. • The amount of any performance bond procured by the private party and the length of period for which any such bond is required will need to be considered carefully for possible value for money implications. The quantum of the bond will reflect the project features but will generally be a percentage of the design and construction contract price. The amount of the bond may be reduced following Commercial Acceptance (by an amount which appropriately reflects the fact that the project has moved beyond the period with the greatest level of construction risk). However, the bond will remain on foot during the defects liability period (at a reduced amount). 118 Government's strong preference is for bank bonds. However, in limited circumstances, it may consider accepting insurance bonds subject to the creditworthiness of the insurance company and government being satisfied with the enforceability of its rights under the bond and with the process for recovering funds in the event that it makes a demand. 119 However, where government is concerned with the creditworthiness of the subcontractor (and its parent, where a parent guarantee is given) it may require performance bonds directly from the private party in addition to those provided by the subcontractor. 120 Where government relies on the subcontractor's performance bond, the financiers' direct agreement will enable government to claim under the bond to rectify any default by the construction subcontractor to the extent that the private party or the security trustee (on behalf of the financiers) fails to rectify the default. Government's ability to claim will be subject to the financiers' right to access the bond. April 2008 52 Partnerships Victoria Updated Standard Commercial Principles • Any performance bond must be unconditional and irrevocable and provided (or backed) by a financial institution regulated by the Australian Prudential Regulation Authority and with a credit rating to be specified. • The required form of the bond will be set out in the project agreement and must not be amended without government's approval (such approval not to be unreasonably withheld). 13.2.2 Performance bond during the operating phase • Although government may consider obtaining operating bonds directly from the private party in certain circumstances, this is not normally appropriate in a Partnerships Victoria project agreement and will as a general rule not be requested by government. • The comfort government requires that the private party will deliver its operational obligations will generally be provided by the abatement regime, government's termination and step-in rights on default, the fact that any compensation on termination amount will be reduced by the cost to government of remedying defects/appointing a new contractor and collateral warranties. However, where government has concerns as to the creditworthiness of the operational subcontractors or their ability to perform their obligations, government may require the private party to procure a performance bond or parent company guarantee in respect of the operating subcontractor's obligations (see discussion on the provision of construction performance bonds). • Alternatively, although government may not require performance bonds or parent company guarantees at project commencement, it may require that such bonds or guarantees be provided at any time during the operating term when a repeated or severe service delivery failure occurs. 13.3 Parent guarantees • For value for money reasons, government generally does not seek performance guarantees from the parent companies of the private party or of the key subcontractors. However, this will depend on whether the commitment of a parent company is an important element in the selection of the private party or a key subcontractor. • Generally, government prefers that performance bonds (whether bank guarantees or insurance bonds) be given by subcontractors (in favour of the private party) as they can be called upon on clearly defined terms and their pricing is more transparent. April 2008 53 Partnerships Victoria Updated Standard Commercial Principles 14. Service requirements and specifications Principle Payment is based on private party delivery of the contracted service to service standards and specifications (i.e. key performance indicators) rather than the level of actual government use of the service. Payment will be abated to the extent the contracted service is not delivered to specification. 14.1 Provision of contracted services 14.1.1 The contracted services The contracted services will differ depending on the nature of the project. However, in an accommodation-based, core services model they will include the accommodation services (including maintenance), together with any or all of utilities management, cleaning and catering services, security, car parking, grounds maintenance and pest control. 14.1.2 • Delivering services to specification Throughout the operational term the private party must (at its own cost) provide the contracted services: (a) in accordance with the service standards and specifications (as varied in accordance with the modification provisions); (b) in a manner consistent with the functional brief, the asset management plan and any other operating and quality assurance manuals the private party is required to prepare for the project;121 (c) in accordance with industry best practice, all relevant policies and procedures122 and applicable laws, approvals and specified quality and safety standards; (d) so that the facility remains at all times during the contract term fit for its intended purposes and uses as specified in, or reasonably inferred from, the functional brief as at the date of the project agreement; and 121 See discussion on maintenance obligations during the operating phase in section 15 (Maintenance and refurbishment). 122 Policies applicable to the particular project will be identified in the project agreement. However, the private party will be responsible for ensuring it complies with all policies to which the project is subject. This is subject to the Change in Law and Modification regimes (see sections 22 (Modifications) and 23 (Change in Law)). April 2008 54 Partnerships Victoria (e) • Updated Standard Commercial Principles in coordination with the delivery of the core services and the contemplated possession and use of the facility by government (and so as to minimise disruption to government in the provision of the core services). The private party must warrant that it will at all times provide the resources, expertise and experience to maintain the facility and provide the contracted services in accordance with the above requirements. 14.2 Service standards and specifications • The service standards and specifications (specifications) will depend on the nature of the project and will be tailored and structured to reflect the particular needs of government. They will be output based, objective, measurable and reasonable, and not immaterial in the context of the contracted services as a whole. • The specifications will refer not only to the existence and accessibility of the asset (such as whether a prison cell or a classroom has been built and is available for use), but will include the delivery of 'soft services' which are integral to the contracted services. For example, a classroom or a prison cell must have a minimum level of lighting and temperature control and be clean. Adequate levels of catering, security and technology services may be required for the service to be 'available'. • The specifications will generally consist of: (a) generic specifications that will apply to the delivery of all services (general specifications); and (b) more specific specifications that apply to the delivery of particular services (specific service specifications). 14.2.2 General specifications General Specifications may be set for the following key performance areas: (a) management - that adequate management, reporting, communication and safeguarding systems are in place, that there is appropriate working committee attendance and that there is adequate reporting of performance against Key Performance Indicators (KPIs); (b) staff and development - that there are no staff shortages and there is adequate staff training and development; (c) policy and strategy - that there is compliance with all laws, industry best practice (as appropriate), prescribed health policies, prescribed work policies, procedures and practices and all other applicable quality standards (including, appropriate environment and emergency management systems); (d) liaising and resources - that there is adequate liaising between parties and information management and that the private party is providing adequate resources (equipment and consumables); and (e) performance monitoring - that the private party responds to and rectifies Service Failures within specified periods. April 2008 55 Partnerships Victoria 14.2.3 Updated Standard Commercial Principles Specific service specifications Specific Service Specifications are additional requirements that need to be met when delivering particular services. The specifications relating to accommodation services may require that: (a) accommodation is provided during prescribed periods; (b) adequate planned preventative maintenance service is provided; (c) all repair requests are addressed within set times; (d) fire safety systems and equipment are appropriately maintained; (e) lifts operate as intended; and (f) appropriate equipment testing is undertaken. 14.3 Service Failures 14.3.1 Performance parameters for assessing delivery of services to specification Each specification will have a corresponding performance parameter for determining whether the specification is achieved. There will be set periods over which each performance parameter will be assessed. 14.3.2 Service Failure Where a service is not provided in accordance with a specification, a Service Failure will have occurred except where such failure is the result of: (a) carrying out planned maintenance or refurbishment;123 or (b) an approved modification. 14.3.3 Failure Events and Quality Failures Each Service Failure will be categorised depending on whether the failure: (a) renders one or more functional areas or units of the facility unavailable for use for its intended function (Availability Failure); (b) affects one or more functional areas or units of the facility but does not result in such functional area or unit being unavailable for use in accordance with its intended function (Incident Failure);124 or 123 Generally, the private party is expected to carry out necessary maintenance and refurbishment without disruption to the service delivery. Relief from abatement may be given in certain circumstances, but only to the extent the planned maintenance or refurbishment is carried out in accordance with the agreed maintenance plan (based on the maintenance plan in the private party's bid proposal). April 2008 56 Partnerships Victoria (c) Updated Standard Commercial Principles is not referrable to a specific area in or unit of the facility (Quality Failure). Availability Failures and Incident Failures are also referred to as Failure Events. 14.3.4 Failure points for Quality Failure Each Quality Failure will automatically incur Failure Points. The number of failure points will depend on the severity of the failure. 14.3.5 Failure Event Levels - response and rectification times An Availability Failure or an Incident Failure will be categorised according to the severity of its impact on core service provision. Depending on its severity, it will be allocated a Failure Event Level which will have a corresponding response and rectification time. 14.3.6 Categorisation of Service Failures and effect of temporary measures and continued use • The helpdesk (which is to be notified of each Service Failure) will determine the initial categorisation of an Availability Failure or an Incident Failure, although government may alter that categorisation. Where parties do not agree on the categorisation, it will be determined by the independent expert. Where government's categorisation is subsequently determined to be incorrect, the private party will be compensated for any reduction in the service fee (together with interest). • The service fee will not be abated (or abated to a lesser extent) to the extent that the private party has adopted appropriate temporary measures to ameliorate or mitigate the consequences of an Availability Failure or Incident Failure that has not been rectified within the specified period. • The level of abatement will also be adjusted to reflect the extent to which government continues to use the facility although it is technically not 'available'. 14.4 Performance monitoring The private party's delivery of the contracted services (in accordance with the specifications) will be monitored and any failures (resulting in abatement of the service fee) will be reported in accordance with the procedures set out in section 16 (Performance monitoring and review).125 124 An Incident Failure is intended to capture failures which if they occur would not necessarily prevent government from continuing to use a service (e.g. a prison cell or class room) despite the defect/failure. In other words, it doesn't make it unavailable. For example, a light globe may have blown but other lighting is available. 125 Where the private party is self-monitoring, failure to correctly report or monitor such failure will result in a Quality Failure. April 2008 57 Partnerships Victoria Updated Standard Commercial Principles 14.5 Abatement and default 14.5.1 Abatement • The service fee will be abated where an Availability Failure, Incident Failure or Quality Failure126 occurs. The service fee will not be abated (except by way of adjustment for costs not incurred by the private party during any relevant period of suspension) when the Service Failure has been caused by an Intervening Event127 (other than a Force Majeure Event128), to the extent that the private party has been given relief from the relevant obligation that caused the Service Failure.129 • The amount abated for a Failure Event will depend on: (a) the area of accommodation affected; (b) the Failure Event Level classification; and (c) the time taken to rectify the failure following expiry of the rectification period. • The more critical the affected area to the provision of the contracted services, the higher the weighting given to that area and the greater the deduction from the service fee for a failure. For example, the higher the Failure Event Level classification the shorter the corresponding response and rectification times one would expect to see and therefore, the more frequent the deductions. This is intended to encourage the private party to rectify the failure as soon as possible. • The level of abatement for a Quality Failure (and therefore the number of performance points allocated for that failure) will depend on the severity of the failure, how often it is repeated130 and how long it is sustained (as appropriate). The more severe the failure (and the higher the number of points allocated to that failure) the higher the weighting given and the greater the deduction.131 14.5.2 • Overlap of Service Failures If an event simultaneously constitutes an Availability Failure and an Incident Failure, the service fee will be abated for an Availability Failure. 126 In respect of Quality Failures, there will generally be a minimum level of Quality Failure points, the accumulation of which will not incur any abatement. For example, accumulating up to 10 Quality Failure points in a month may not result in an abatement. 127 Subject to the threshold requirements being met (see paragraph 17.2 in section 17 (Intervening Events during the operation)) and except by way of adjustment for costs not incurred by the private party or to the extent the Intervening Event was required to be insured against under the project agreement (see paragraph 17.3.1 in section 17 (Intervening Events during the operation)). 128 Government will, in certain circumstances, keep senior debt whole during the period of suspension arising from a force majeure in accordance with the principles in section 24 (Force majeure). 129 See section 17 (Intervening Events during the operational phase). 130 See paragraph 14.5.3 in section 14 (Service requirements and specifications). 131 In respect of certain regimes, government may consider, if appropriate, the ability to set-off failures against superior performance in other areas or in previous time periods. This will depend on the importance and severity of the failure and the benefit to government of any superior performance. April 2008 58 Partnerships Victoria Updated Standard Commercial Principles • If an event simultaneously constitutes either an Availability Failure or an Incident Failure and a Quality Failure, the service fee will be abated for either of the Availability Failure or the Incident Failure (as applicable but without double counting) and also the Quality Failure. • Where there are two or more events that would deem an area unavailable, the level of abatement will be based on the event with the highest failure event classification. • Where a Service Failure may result in more than one Quality Failure, it will be deemed to be the Quality Failure with the highest number of points. 14.5.3 Repeated failures Repeated occurrences of the same failure within specified consecutive periods, whether an Availability Failure, Incident Failure or Quality Failure, may lead to an escalation of the relevant failure points or weighting (as appropriate) given to that particular failure.132 14.5.4 Default and termination Refer to paragraph 27.1 of section 27 (Default) and paragraph 28.1.1 of section 28 (Termination) for a discussion on what level of Service Failure and abatement will result in a default leading to termination. Service Failures caused by an Intervening Event (including, a Force Majeure Event) for which the private party has been given relief, will be excluded for the purposes of determining whether an Event of Default or Default Termination Event has occurred. 14.6 Delivery of core services does not relieve the private party of its contractual obligations The private party is not relieved of its obligations by the use and occupation of the facility by government (as contemplated by the project agreement) except to the extent that relief is given for 'Intervening Events'.133 14.7 Utility services • The private party is responsible (at its own cost) for the continuous supply of utility services134 to the facility in accordance with the specified standards. • Government will generally take the risk on the unit price of utilities. • However, depending on the nature of the project, government may look to either: 132 By way of example, if the same Quality Failure occurs in more than [X] consecutive operating periods, then each consecutive Quality Failure of the same type after the first Quality Failure will incur double the number of Quality Failure points as the previous Quality Failure. This process of doubling will continue until no Quality Failures of that type have occurred for [X] consecutive operating periods. [X] amounts or periods should be determined on a project-specific basis. 133 See section 17 (Intervening Events during the operational phase). 134 These include any utility service, such as water, electricity, gas, telephone, drainage, waste, sewerage and electronic communications. April 2008 59 Partnerships Victoria • Updated Standard Commercial Principles ¾ transfer the full volume risk to the private party for some or all utilities (for example, where the private party takes demand risk, such as in a toll road or in respect of social infrastructure projects, where the core service environment is reasonably predictable, such as in a school or prison or a carpark in a hospital project); or ¾ share volume risk above a specified threshold.135 This will be determined on a project-specific basis taking into account: (a) life cycle costs for the term of the project agreement; (b) incentives to use environmental and energy saving materials and systems; (c) which party is best placed to manage long-term consumption risk; (d) difficulty of estimating long-term consumption risk; and (e) most importantly, value for money. • Government will also look to share volume savings on the same basis (i.e. below a specified threshold) if the private party uses less utilities than a baseline expected volume. • To incentivise the private party to design an energy efficient facility, there will be no cap on the private party's exposure.136 • The Specifications may also include energy efficiency standards that the facility will need to meet in order to be commissioned. Ongoing energy efficiency tests may be required throughout the operational phase. 14.8 Government relief for private party failure to comply with service obligations The State is entitled to abate service payments made to the private party if the private party fails to comply with its service obligations under paragraph 14.1.2. Abatement is the sole remedy for which the private party is liable in respect of Service Failures except those which give rise to a claim or liability for: (a) third party injury (including death) or property damage; (b) loss or damage to, or destruction of, the facility or the site; 135 To be bid by the private party on a project-specific basis. Government will generally look to the private party to take responsibility for utility volume risk in relation to utility end uses over which the private party has a degree of control because, for example, of the way it designs the facility or approaches the delivery of the contracted services (through plant and material selection and operational and maintenance policies). The State will generally retain 100 per cent utility volume risk in relation to utility end uses that are not reasonably within the private party's responsibility. 136 During the evaluation of bids, the State will consider any environmentally sustainable design benefits and energy efficiency benefits which flow from the private party's bid. April 2008 60 Partnerships Victoria Updated Standard Commercial Principles (c) costs incurred by government in remedying the breach or default or exercising step-in rights; or (d) reasonably foreseeable economic loss suffered by government or governmentrelated parties (including the facility operator) which is caused by the unlawful or negligent act or omission of the private party,137 and in each case, only to the extent the amount of any such claim or liability exceeds any service payment abatements resulting from such act or omission. 137 Depending on the nature of the project and any direct relationships which the State has with third parties in relation to the facility, government may carve out all reasonably foreseeable economic loss and not only that which is "caused by the unlawful or negligent act or omission of the private party". April 2008 61 Partnerships Victoria Updated Standard Commercial Principles 15. Maintenance and refurbishment Principle The private party must maintain and refurbish the facility (at its own cost) as necessary to ensure it delivers the contracted services to specification. 15.1 Maintenance and refurbishment during the operating phase Throughout the operating phase, the private party must (at its cost) maintain and refurbish the facility in accordance with an asset management plan or as otherwise required in order to meet the service specifications (including ensuring that the assets achieve their full working life). 15.2 Asset management plan 15.2.1 Content • The asset management plan must provide for all preventative maintenance, lifecycle repair and asset management, replacement and refurbishment necessary during the operating phase to ensure delivery of the contracted services to specification (including, where relevant, handing the asset back to government in the necessary handover condition). • Although the private party may be given some flexibility to vary its asset management plan, it will be limited to the extent necessary to ensure the private party can continue to meet its contractual obligations throughout the contract term. For example, the private party may be permitted to defer scheduled refurbishment works for a limited period. 15.2.2 Provision of endorsed asset management plan as a condition of Commercial Acceptance • A draft asset management plan must be submitted as part of the private party's bid and will be incorporated into the project agreement. • A final updated asset management plan (which has been reviewed and commented on by government and which is consistent with the draft plan submitted as part of the private party's bid) must be provided as a condition to achieving Commercial Acceptance. • Government's right to comment is limited to differences between the draft and final bid plan or to the extent that there are adverse impacts on the private party's ability to provide the contracted services to specification. April 2008 62 Partnerships Victoria • Updated Standard Commercial Principles Failure to agree on amendments to the plan as a result of government comments will lead to the matter being referred to an independent expert for resolution.138 15.2.3 Regular updating • The private party must update the asset management plan regularly to take account of all approved modifications, together with improvements in best practice and technology and any other matters relevant to the maintenance of the project assets. • Any change to the final asset management plan must be provided to government for review and comment. • The private party must provide government annually with a fully consolidated updated asset management plan and a report on the private party's performance against the current plan. 15.2.4 No obligation on government Neither government's involvement nor that of the independent expert in the development or approval of the asset management plan relieves the private party of any of its obligations (including warranties) or constitutes a representation by government as to the private party's compliance. 15.3 Funding maintenance and refurbishment obligations The service fee will include amounts to fund the private party's maintenance and refurbishment obligations. This will generally be reflected in a smooth service payment profile, although depending on the project’s funding arrangements, government may consider a lumpy payment profile. The service fee will generally be abated to the extent the private party’s obligations are not satisfied.139 However, government may consider exempting the lifecycle/maintenance component of the service fee depending on the project’s funding proposal (in particular, the associated reserve costs). 15.4 Monitoring performance of maintenance and refurbishment obligations The private party's performance of its maintenance and refurbishment obligations will be monitored in accordance with the performance monitoring system and be subject to government's audit rights.140 138 See section 32 (Dispute resolution). 139 In projects where it is expected that a high degree of technological obsolescence will occur or where major refreshes of facilities will be required, it may be value for money for government to carve out refurbishment obligations from the service fee and benchmark them separately. 140 See section 16 (Performance monitoring and review). April 2008 63 Partnerships Victoria 15.5 Updated Standard Commercial Principles End-of-term arrangements See section 31 (End-of-term arrangements) for a discussion on end-of-term arrangements such as handover obligations upon expiry of the contract term, end-of-term surveys/inspections and additional end-of-term maintenance and refurbishment obligations. April 2008 64 Partnerships Victoria Updated Standard Commercial Principles 16. Performance monitoring and review Principle The private party will be required to monitor its performance against the project specifications, using a comprehensive performance management methodology. 16.1 Monitoring obligations 16.1.1 Performance monitoring system The parties will agree upon a comprehensive performance monitoring system (PMS) to monitor on a timely and effective basis whether the private party is delivering the contracted services to specifications.141 The robustness of this system is an important source of comfort to government that the private party is meeting its obligations.142 16.1.2 Who does the monitoring The private party must monitor its own performance by means of the PMS (subject to government's rights of review and audit). The performance monitoring must commence on the date of commencement of service provision. 16.1.3 Performance data warranted The performance data which results from the application of the PMS (including source information, periodic performance reports, documentation and data created for or by the PMS) must be contractually warranted by the private party as being at all times accurate, complete and correct. 16.1.4 Periodic performance report The private party must prepare a regular periodic performance report143 which is delivered to government (generally, through the contract administrator). This report will provide sufficient information to allow the calculation of the service fee by the contract administrator (or where the service fee is calculated by the private party, to allow confirmation of the 141 The methodology for the performance management system will be fully set out in the project agreement. 142 Note that this comprises only one component of the broader project and contract monitoring that government should carry out. Government party reporting and monitoring is discussed in Chapter 8 of the Partnerships Victoria Contract Management Guide. 143 The relevant monitoring periods will depend on the nature of the project. However, it is usual for performance reporting to occur on a monthly basis and within a set number of days from the end of each month. Chapter 8 and Templates H-K of the Partnerships Victoria Contract Management Guide provide further guidance on what the private party should be required to include in its periodic performance reports. April 2008 65 Partnerships Victoria Updated Standard Commercial Principles calculations by the contract administrator) and will include, amongst other things, the number of Service Failures144 in the preceding period, details of each Service Failure and how often it was repeated during that period. 16.2 Additional performance monitoring rights 16.2.1 Monitoring rights of government145 Government (through the contract administrator) may also monitor and review the private party's performance and the PMS in any way it thinks fit. Except where costs are payable by the private party as described in paragraph 16.3.3, this will be at government's cost.146 These additional monitoring rights include the use of: (a) customer satisfaction surveys; (b) audit processes; (c) scheduled and unscheduled reviews and inspections; and (d) feedback from users (including, where appropriate, the core services) as to the adequacy and quality of the facility or the services being provided by the private party. 16.2.2 Access to information • The private party must grant access to the PMS and any performance data for, or resulting from, the PMS on the provision of reasonable notice by government. Copies of all information, documents and data relevant to the PMS or the provision of the service by the private party must be kept for seven years after their creation or production. • The private party must provide such assistance and access as government requires in the exercise of its performance monitoring rights. 16.3 Auditing 16.3.1 Requirement for audit Government can (through the contract administrator) require an audit of the PMS or any performance data for, or resulting from, the PMS at any time up to six months after the end of the term of the project. 144 See paragraph 14.3.2 in section 14 (Service requirements and specifications) for definition of 'Service Failure'. 145 By way of clarification, the intention of this paragraph 16.2 is to provide a mechanism for government to review and monitor the private party's performance under the project agreement, not to introduce additional service requirements. 146 Broader government party reporting and monitoring is discussed in Chapter 8 of the Partnerships Victoria Contract Management Guide. April 2008 66 Partnerships Victoria 16.3.2 Updated Standard Commercial Principles Who will conduct the audit? The audit will be conducted by an independent person appointed by government on terms and conditions determined by government. 16.3.3 Who will pay for the audit? Government will pay for the cost of the audit. However, if an audit identifies incorrect information provided by the private party that affects the service fee, the private party must pay for the costs of the audit. 16.3.4 Inaccurate PMS or performance data If the auditor's written report shows an inaccuracy, incorrectness or incompleteness in the PMS or any performance data for, or resulting from, the PMS then the private party must: (a) correct and re-issue the affected report or data and take steps to remedy the fault in its monitoring, measuring and reporting system; and (b) if the error has affected the amount of a service fee, make the appropriate adjustment from the next scheduled service fee, or if there is no further service fee scheduled and the adjustment amount is a deduction, the amount will be a debt due and payable from the private party to government. 16.3.5 Fraudulent or false, misleading or negligent reporting If any fraud or false, misleading or negligent reporting is disclosed in the auditor's report, this will constitute a serious breach potentially leading to termination of the project agreement.147 16.4 Operating committee 16.4.1 Composition of the operating committee During the operating phase an operating committee must be established typically comprising two representatives of the private party, two representatives of government and the contract administrator (who will be the chairperson).148 16.4.2 Role of the operating committee The operating committee will meet regularly149 to discuss any matters relating to the project including issues of public concern, facilities management and maintenance issues, community and media relations issues and issues arising from the reports provided by the PMS. 147 See sections 27 (Default) and 28 (Termination). 148 This is a usual structure of the operating committee although it may vary on a project-specific basis. 149 Usually not less than once a month. April 2008 67 Partnerships Victoria 16.4.3 Updated Standard Commercial Principles Authority of the operating committee The operating committee will not have any legal responsibility to either the private party or government and will not have power to require either party to act or refrain from acting in any way. Its decisions do not affect the rights or obligations of either the private party or government under the project documents. April 2008 68 Partnerships Victoria Updated Standard Commercial Principles 17. Intervening events during the operational phase Principle The private party will be relieved from termination for failure to deliver the contracted services during the operational phase where the event causing such failure is clearly within government's control. Relief from termination may also be given for certain events outside the control of both parties provided the private party could not have avoided or mitigated the effects of such event on its performance. Compensation for private party losses will generally be limited to those attributable to events within government's control. 17.1 • Intervening Events The following will be Intervening Events150: (a) any breach of a project document by government151; (b) an act or omission by the State or relevant government-related parties152 at the facility/site (but only in their capacity as a contracting party) other than: (i) the performance of the core services or any act or omission authorised or permitted under the project documents; or (ii) an act or omission which is a reasonably foreseeable consequence of the performance of the core services153 or other authorised/permitted acts or omissions154; 150 This is not intended to be an exhaustive list of Intervening Events for all projects. Government recognises that there are some sector specific projects which will require additional events or the removal of certain events. However, the concept of intervening events will be extended in limited circumstances and only after very careful consideration of the project specifics. These events may be defined in various ways in different projects (e.g. 'Acts of Prevention'). 151 This is only intended to capture project documents to which the State is a party and the relevant government entity that has entered into the relevant document. . 152 What constitutes a government-related party will depend on the nature of the project. Although it is intended to capture government employees, consultants and other parties at the site which are appointed by government or whom government effectively controls (for example, as a result of delivering the core services). The focus of that risk will depend on the nature of each of the contracted services and core services and the level of interface between them. 153 154 This is intended to also capture ancillary services incidental to or otherwise in support of the core services. The State’s role as contracting party is separate from its role as being responsible for the general administration of government affairs. Accordingly, the relief events in paragraphs (a) and (b) only capture acts or omissions (including breaches) of the State in its capacity as a contracting party, not acts and omissions carried April 2008 69 Partnerships Victoria Updated Standard Commercial Principles (c) any disruption or delay caused by a third party (other than the private party) engaged by government to undertake additional capital works or services on the site;155 (d) fire, flood or explosion (which is not a Force Majeure Event); (e) failure by a statutory authority to carry out works or provide services unless the statutory authority, in failing to carry out the works or services, is acting in accordance with or pursuant to its statutory powers, duties and discretions or obligations; (f) site specific blockade or embargo affecting specialised project equipment (to be determined on a project-by-project basis); (g) industrial action but only to the extent that it directly affects the project (whether it also affects the relevant project related industries156 or a significant segment of them) and the private party can demonstrate that it results directly from an act or omission of the contracting government party or any of its employees at the facility/site;157 (h) any event or occurrence (outside the control of either party) which causes lack of possession of or access to the project site, other than any event or occurrence arising from third party rights to use or access the site; and (i) a government or court direction to suspend or cease all or any part of the works because of a native title claim or application or as a result of the discovery of an artefact (provided the cessation order does not result from a private party breach of its obligations in dealing with discovered artefacts). • Relief to be provided as a result of force majeure events, government-initiated modifications and compensable changes in law is dealt with in sections 24 (Force majeure), 22 (Modifications) and 23 (Change in Law). • Where the act or omission for which relief is given involves additional works government has decided to undertake, any such relief may be conditional on the private party entering into reasonable and appropriate interface agreements with the relevant government contractors. out in its role as general administrator of government affairs. Please also refer to paragraph 1.6.4 (Right to compensation). 155 The intention is, to the extent government engages a third party to undertake capital works, it will provide the private party relief against any adverse effects of those works on the private party's obligations under the project documents. However, relief will not be given where the need for those works arises because of a breach or failure by the private party to meet it's obligations under the project documents. 156 The project related industries will depend on the nature of the project. However, they will generally include the construction or building maintenance industries. 157 Industrial action caused or motivated by opposition to PPPs will be deemed not to be the direct result of a government act or omission. April 2008 70 Partnerships Victoria 17.2 Updated Standard Commercial Principles Threshold requirements Relief for an Intervening Event or a Compensable Intervening Event158 will only be given to the extent that: (a) the private party can demonstrate to government's reasonable satisfaction that it is prevented from or delayed in providing the contracted services and is otherwise complying with its contractual obligations as a direct result of an Intervening or Compensable Intervening Event; (b) neither the private party, nor any of the private party's related parties, agents or employees, nor any subcontractor has directly or indirectly caused or contributed to the Intervening Event or Compensable Intervening Event (in each case, whether as a result of an action or inaction including, as a result of breach by the private party of its obligations under the project documents); (c) the private party has taken all proper and reasonable steps to minimise the duration of the Intervening Event or Compensable Intervening Event and to prevent and minimise the effect of the Intervening Event/Compensable Intervening Event and continues to use reasonable endeavours to provide temporary measures during any suspension period; and (d) the private party has, within a specified period of the occurrence of the Intervening Event or Compensable Intervening Event, given notice to government of the Intervening Event or Compensable Intervening Event and its effects on the private party and of the private party's intention to claim relief. Government will not provide relief for either the occurrence or effects of events which are within the private party's control. This includes where the private party should have put in place appropriate contingency plans so as to reduce or avoid any effects on its ability to perform its obligations under the project agreement. 17.3 Relief for Intervening Events 17.3.1 Form of relief If the threshold requirements are met, then: (a) the private party's obligation to deliver the affected service or comply with its affected contractual obligations will be suspended;159 (b) the relevant service fee will not be abated for the Service Failures160 except: (i) by way of adjustment for costs not incurred by the private party during suspension; and 158 See paragraph 17.4.1. 159 This includes obligations to provide temporary measures. Where the Intervening Event prevents the cure of a default within the specified cure period, the cure period will be extended by a reasonable time period given the effect of the Intervening Event. 160 This principle is currently under review for events which are controlled or better managed by the private party and for which, therefore, only time relief (not money relief) should be given. Government will issue separate guidance material in the event any change is made to the current principle. April 2008 71 Partnerships Victoria Updated Standard Commercial Principles (ii) to the extent the Intervening Event or any risk occurrence that caused the Intervening Event was required to be insured against by the private party under the project agreement;161 and (c) no default notice may be given in respect of such Service Failure. 17.3.2 Period of suspension of obligations The private party's obligations affected by the Intervening Event will be suspended from the date it gives notice to government of the Intervening Event until it ceases to be prevented from performing its obligations. 17.4 Compensation 17.4.1 Compensable Intervening Events • The following will be Compensable Intervening Events:162 (a) any breach of a project document by government;163 (b) loss directly caused by the malicious, unlawful or reckless act of government employees or other government-related parties164 (but only in their capacity as a contracting party)165; 161 The private party will be expected to take out adequate levels of insurance, including business interruption insurance to cover servicing of senior debt. 162 This is not intended to be an exhaustive list of Compensable Intervening Events for all projects. Government recognises that there are some sector specific projects which will require additional events or the removal of certain events included below. However, the concept of Compensable Intervening Events will be extended in limited circumstances and only after very careful consideration of the project specifics. These events may be defined in various ways in different projects (e.g.. 'Compensation Events' or 'Compensable Acts of Prevention) as applicable. 163 Being the government party under the project agreement and only to the extent government is a party to the project document. 164 What constitutes a government-related party will depend on the nature of the project. Although it is intended to capture government employees, consultants and other parties at the site which are appointed by government or whom government effectively controls (for example, as a result of delivering the core services), the focus of the risk will depend on each of the contracted services and core services and the level of interface between them. Although government may in theory have a relatively greater level of control than the private party over actions of government-related parties, the private party is expected to be able to manage wilful damage (by any party) through appropriate facility design and security services. In other words, government expects the private party to deliver a solution which accommodates risks associated with the delivery of core services and the governmentrelated parties delivering or using those core services. 165 The State’s role as contracting party is separate from its role as being responsible for the general administration of government affairs. Accordingly, the relief events in paragraphs (a) and (b) only capture acts or omissions (including breaches) of the State in its capacity as a contracting party, not acts and omissions carried out in its role as general administrator of government affairs. Please also refer to paragraph 1.6.4 (Right to compensation). April 2008 72 Partnerships Victoria Updated Standard Commercial Principles (c) industrial action but only to the extent that it directly affects the project (whether it also affects the relevant project-related industries166 or a significant segment of them) and the private party can demonstrate that it results directly from an act or omission of the contracting government party or any of its employees at the facility/site;167 (d) a government or court direction to suspend or cease all or any part of the works because of a native title claim or application or as a result of the discovery of an artefact (providing the cessation order does not result from a private party breach of its obligations in dealing with discovered artefacts). 17.4.2 Relief • If the threshold requirements are met, then government will pay the private party the reasonable additional costs incurred by the private party as a direct result of the Intervening Event less any insurance proceeds paid or payable to the private party for the loss or damage168. The amount of compensation will be determined, and the financial model adjusted, in accordance with the service fee adjustment principles set out in section 18 (Payment provisions). • Government has the option of compensating the private party by: • (a) an adjustment to the service fee; (b) a lump sum payment; or (c) subject to the private party's agreement, extending the operating term. Where option (a) is adopted and the amount the private party must fund up-front is above a specified threshold, the private party must use its best endeavours to obtain competitive funding for such costs. If, having used its best endeavours, the private party is unable to obtain funding acceptable to government, government will pay for those costs by way of a lump sum payment. 17.5 Alternative arrangements During the suspension of the private party's obligations government may make alternative arrangements for the delivery of the suspended services. The allocation of risks associated with the delivery of any alternative arrangements will be determined on a project-by-project basis depending on the nature of the additional services and their interface with the existing contracted services and the nature of the event leading to the suspension. 166 The project related industries will depend on the nature of the project. However, they will generally include the construction or building maintenance industries. 167 Industrial action that is caused or motivated by opposition to PPPs will be deemed not to be the direct result of a government act or omission. 168 Project Co will be required to make a claim under its insurance policy for any damage or liability arising as a result of the compensable event occurring. Project Co will not be permitted to remedy the damage prior to lodging a claim with the insurer unless expressly permitted by the State. April 2008 73 Partnerships Victoria 17.6 Updated Standard Commercial Principles Cessation of the Intervening Event The private party must notify government immediately after it ceases to be prevented from performing its obligations as a result of an Intervening Event. The private party must continually update information previously provided to government in respect of the Intervening Event as and when circumstances change or as reasonably directed by government. 17.7 No effect on government's step-in rights The private party's right to relief arising from an Intervening Event does not affect government's step-in rights for an emergency situation. 18. Payment provisions Principle The payment mechanism will provide for deductions from the service fee to be made for sub-standard performance. The level of deduction will reflect the severity of the performance failure. 18.1 Service payment 18.1.1 Service fee The service fee may be made up of sub-elements reflecting particular categories of expenses faced by the private party (both fixed and variable), but collectively these will comprise a single service fee payable for each unit of service. All payments of the service fee by government shall be made in arrears.169 18.1.2 Whole of service fee to be abatable No sub-element of the unitary service fee should be such that it is always received by the private party regardless of its performance or that it is immune from abatement for 169 In some very limited circumstances, there may be specific components of a project’s construction costs that may be highly uncertain, leading to those components being highly priced in bids. In these circumstances, government may hope to obtain a better value-for-money outcome by including a “provisional sum” for that construction component in the service fee, which represents the expected cost of that component but is subject to adjustment once the actual cost becomes known during construction. If it is proposed that provisional sums be included, care is needed to ensure that the component of the works to which the provisional sum relates is clearly and comprehensively defined, the costs incurred in delivering the component of the works to which the provisional sum relates will be identifiable as a discreet component of the total construction costs (this may not be possible unless the construction contractor enters a separate subcontract for those works), and the project agreement contains a clear and robust process for determining the actual amount payable by government in respect of the relevant component of the works - for example, a tender process to engage a subcontractor to perform the works, with both government and the private party having a role in evaluating the tenders. April 2008 74 Partnerships Victoria Updated Standard Commercial Principles particular service failures. However, government may consider exempting the lifecycle/maintenance component of the service fee depending on the project’s funding proposal (in particular, the associated reserve costs). 18.1.3 Calculating actual service fee For any given period the service fee should be calculated in accordance with a formula commencing with the pre-agreed amount payable for the full performance of services in the period less amounts for: (a) Quality Failure abatement; (b) the sum of abatement amounts for each Availability Failure and Incident Failure; (c) the repeated failure abatement amount (if any);170 and (d) any utility volume adjustments. 18.1.4 Maximum amount deductible for service failure The maximum amount that can be deducted in any given payment period should be no more than the entire service fee for a payment period. If the operation of the payment mechanism results in a negative amount for that payment period it will be deemed to be zero. 18.2 Payments 18.2.1 Invoicing • If government disputes the private party's claim for payment it may notify the private party of the amount that government considers it should pay and why it differs from the private party's claim. Government will pay any undisputed part of the payment on the date that payment is due. • If government's payment notice is issued after the private party's claim is paid, government may deduct the amount by which the payment made to the private party exceeded the amount in the government's payment notice from the amount due for the next payment period. • Payment of moneys by government to the private party will not of itself be evidence that any works or services have been carried out in accordance with the project agreement. • Any late payment of amounts that are properly due and payable (including a previously disputed amount where the dispute is resolved in favour of the private party), will incur interest at a pre-agreed default rate. • All payments will be made in arrears. 170 To the extent that abatement amounts ratchet up for repeated failures. These failure types are defined and discussed further in section 14 (Service requirements and specifications). April 2008 75 Partnerships Victoria 18.2.2 Updated Standard Commercial Principles Set off • Government may set off amounts payable to the private party under the project documents against any amounts owing by the private party to government or paid by government on the private party's behalf.171 • The private party must make all payments under the project documents without setting off, counter-claiming or deducting any amounts. 18.3 Indexation The payment mechanism will include provisions for indexing the service fee. This will be determined on a project-by-project basis. 18.4 Service payments for phased completion • As discussed in section 11 (Construction and commissioning) certain projects (especially linear infrastructure projects) may require phased service commencement. • In these circumstances, either: • (a) Commercial Acceptance, and therefore commencement of payments, will only occur when all the facilities in the scheme reach the required output specification; or (b) Commercial Acceptance of each facility in the scheme (or each part of the facility) will take place as it reaches the required output specification, such that government pays for elements of the service as they come on stream. Although the first option is intended to incentivise the private party to complete all of the facilities as soon as possible, government would effectively be receiving a service (in the form of the completed facilities) for which it is not paying. This will generally come at a cost and unless the time period between delivery of the first facility and the last facility is relatively short, this approach may not delivery value for money. The second approach can be adapted to more fully incentivise the private party with government withholding a percentage of the payment to be made for services delivered in relation to the completed facilities until all facilities (or all parts of a facility) reach Commercial Acceptance. 18.5 Service fee adjustment principles The following service fee adjustment principles apply to adjustments to the service fee which result from specific agreed events that are explicitly set out in the project agreement.172 171 By way of clarification, this does not include amounts owing by the private party that are in dispute (for the duration of the dispute). 172 Examples of such events which may require adjustment of the service fee include agreed modifications, force majeure events, compensation events, relief events or re-financing gains. April 2008 76 Partnerships Victoria 18.5.1 Updated Standard Commercial Principles Overriding principles • The overriding factor in determining the adjustment principles upon which the private party is effectively compensated, is government receiving value for money. Government has the right to appoint an independent party to audit any information prepared by the private party in this regard. • Government reserves the right to pay a lump sum for any adjustment which would otherwise result in an increase in the service fee and to receive by way of payment from the private party the benefit of any adjustment that would otherwise result in a decrease in the service fee.173 • The private party will not be entitled to compensation for any indirect costs. 18.5.2 Recurrent expenditure The private party will provide government with a written reasonable quote for the cost or saving applicable to an event requiring an adjustment in recurrent expenditure (which quote will not include any private party profit margin).174. To the extent that the quote is not acceptable to government, government may appoint an Independent Reviewer to review the quote and if appropriate, provide an alternative cost estimate. Where this occurs, the cost or saving applicable to the event will be the lower of the private party's quote and the Independent Reviewer's estimate.175 18.5.3 Financing costs If any debt or equity is required to fund an event requiring an adjustment then the service payment will be adjusted according to the following principles: (a) if the funding is provided by a third party financier any necessary increase in the service fee will reflect the minimum amount required to amortise the new debt by the expiration of a specified repayment period taking into account interest and indexation; (b) if the funding is to be provided by subscription of shares in the private party or new loans by its shareholders, any necessary increase in the service fee will generally be the minimum amount required to give new equity a return not greater than the prevailing market rate of return for projects of a similar risk profile over the remaining period of the project term (to be determined on a project-by-project basis). 173 In determining the method of payment it will require from the private party, government will give due regard to the form in which the private party is receiving the benefit (including, the availability of financing at the time). However, in making such determination government must ensure value for money is delivered. 174 Government will only compensate the private party for subcontractors' reasonable profit margins. 175 This is subject to the private party's right to refer the issue to dispute resolution. April 2008 77 Partnerships Victoria Updated Standard Commercial Principles 18.6 Variations to financial model 18.6.1 When will the base case model be varied? The base case financial model (as at financial close) may only be varied on the occurrence of certain specified events and in accordance with the principles and procedures set out below and only to the extent that such variation events result in an adjustment to the service fee over the remaining contract term. 18.6.2 Variation events The variation events will generally include: (a) modifications, as discussed in section 22 (Modifications); (b) change of law, as discussed in section 23 (Change in Law); (c) force majeure event, as discussed in section 24 (Force majeure); (d) benchmarking/market testing, as discussed in paragraph 19.3.4 of section 19 (Review and market testing of services); (e) insurance, as discussed in section 26 (Insurance); (f) government requested acceleration of the construction works; (g) compensation events, as discussed in paragraph 12.3 of section 12 (Relief for construction delays) and paragraphs 17.3 and 17.4 of section 17 (Intervening Events during the operational phase); (h) refinancing, as discussed in section 33 (Re-financing gain); and (i) other events requiring an adjustment to the periodic service fee as specified under the project agreement. 18.6.3 Principles for variations to base case financial model Where a variation event occurs, the base case financial model will be varied taking into account only the following: (a) the changes to the private party's incremental costs directly resulting from the variation event, in light of certain specified parameters such as minimum debt coverage ratios and the internal rate of return (as agreed in the base case financial model); and (b) any changes to the periodic service fee made in accordance with the project agreement. 18.6.4 • Procedure for variations to base case financial model Promptly after it becomes aware of a variation event, the private party must submit a modified base case financial model for endorsement by government giving full details of the assumptions and calculations used. April 2008 78 Partnerships Victoria Updated Standard Commercial Principles • The private party must provide government with full and complete access to any electronic copies of the calculations required to amend the base case financial model. In addition, the private party must promptly provide any other additional information requested by government in relation to the variation event and any necessary amendments to the base case financial model. • Government may: • (a) agree with the variation event; (b) disagree with all or any aspect of the submission by the private party; or (c) require the modified base case financial model to be reviewed by an independent expert in accordance with the dispute resolution procedures. Once the modified base case financial model is agreed or is determined by the independent expert, the modified base case financial model will be endorsed and become the base case financial model under the project agreement. 18.7 Taxes 18.7.1 General tax liability The private party is responsible and indemnifies government for all taxes payable pursuant to the project documents and any transactions evidenced or contemplated by them. However, government will generally reimburse the private party for any land tax and stamp duty payable to the Victorian government. 18.7.2 Rates and taxes Where rates and taxes are assessed in respect of the site, the private party must pay those when due (if separately assessed) or, if not separately assessed, must pay a portion of the rate or tax based on the proportionate area of the site to the total area assessed. However, government will consider on a project-by-project basis, and based on a value for money outcome, reimbursing the private party for part or all of those costs.176 18.7.3 Goods and services tax If a goods and services tax (GST) is payable on a taxable supply made under the project documents then the party paying for that taxable supply must also pay the GST amount (having accounted for any input tax credit entitlement). 176 Particular attention will be given to whether the design submitted, or the uses proposed (e.g. ancillary commercial uses), by the private sector party is able to influence the quantum of rates charged in respect of the site. Rates are generally pass-through costs save that, to the extent that the private party's bid solution can influence the quantum of rates charged, government will consider reimbursing the private party for part or all of these costs if a value-for-money outcome is being achieved. April 2008 79 Partnerships Victoria Updated Standard Commercial Principles 19. Review and market testing of Services Principle Review and market testing of the cost of specified soft services is used to keep service costs competitive over the long life of the project and ensure government achieves value for money. 19.1 Reviewable services 19.1.1 Types of services that can be reviewed/market tested For the majority of projects, only ‘soft services’ (such as catering, cleaning, security and IT services which do not involve a large capital component) are appropriate for either review by government or market testing. This is because price comparison with a potential alternative subcontractor is generally only feasible where capital costs are excluded from the service being compared.177 19.2 Review of soft services 19.2.1 Review by agreement • At agreed intervals,178 the private party can submit (and must submit if so required by government) an offer for the provision of specified soft services for the next interval. The offer must provide a comparison to market prices and detail all relevant factors and inputs into the proposed price on an open-book basis. • If an offer is submitted within the required period prior to expiration of the previous interval, government will negotiate exclusively with the private party for [two] months179 and accept or reject the offer within [one further] month. • If the private party is required to submit an offer but fails to do so or the parties are unable to reach an agreement during the period of exclusive negotiation, either the private party or government may elect to refer the matter for dispute resolution. However, if government elects to utilise the competitive tendering provisions (see below), the parties will not have recourse to the dispute resolution process. 177 Where utility costs represent a relatively significant portion of the project operating costs, government may consider making certain utility services (e.g. electricity, gas and water) subject to review/market testing. 178 Usually between five to seven years, depending on the type of service being reviewed. In a falling or highly competitive market, a shorter time interval may provide better value for money. 179 Or such other period agreed by the parties at the time. April 2008 80 Partnerships Victoria • Updated Standard Commercial Principles The private party must continue to provide the services during the tender process on the same terms as during the previous interval. 19.2.2 Cost sharing arrangement Any decrease in the cost of providing the benchmarked services will, depending on a value for money considerations, either be shared on a percentage basis to be agreed in light of the project specifics, or fully retained by government.180 Although government may on individual projects fully bear any cost increases where it is value for money it will seek to substantially but not fully bear the increase.181 The respective percentages may be items upon which the private party is required to bid. 19.3 Market testing 19.3.1 Competitive tender • The private party will be required to market-test the reviewed services by calling for tenders from at least three independent tenderers where: (a) in the event it has been required to, the private party fails to make an offer within the agreed time; (b) government rejects the private party's offer or the parties fail to reach agreement within the exclusive negotiation period (and the matter is not referred to dispute resolution); (c) the difference between the existing price and new offer is greater than an agreed percentage;182 (d) government elects to market-test the offer; or (e) the outcome of any dispute resolution process related to any exclusive negotiation recommends or requires market testing. • The private party must continue to provide the services during the tender process on the same terms as during the previous interval. • Government and the private party will agree the procedures for market testing. However, at a minimum, the tender process must: 180 (a) include tenders from at least three independent tenderers; (b) be open, transparent and inclusive with agreed evaluation criteria; (c) subject to these requirements, be managed by and conducted at the cost and risk of the private party; Generally, government will look to share in any decrease on a 50:50 basis. 181 Where government seeks to share it, less than 100 per cent of the increase in the cost of providing the reviewed soft services will be passed through to government. This cost sharing approach reflects the fact that the review by government process is likely not to result in costings which are as precise as performing a full market testing process and also incentivises the private party to control its costs. 182 Percentage to be agreed on a project-specific basis. April 2008 81 Partnerships Victoria Updated Standard Commercial Principles (d) be conducted so that government has an observational role; (e) avoid actual or perceived conflicts of interest arising (e.g. if a company associated with the private party or its shareholders or its principal operating subcontractor intends to bid, then an independent tender process manager should be appointed); (f) be overseen by a project team made up of representatives of both the private party and government;183 and (g) if government requires, be certified as compliant with these requirements by an independent probity auditor. 19.3.2 Prospective tenderers Government must be satisfied that all prospective tenderers are of good character and have appropriate financial standing and technical capacity.184 19.3.3 Call for tenders The call for tender must be accompanied by a draft services provider subcontract from the private party (approved by government) which the successful tenderer will be required to enter into, so that the service obligations are the same in all material respects as the current service subcontract (except for the fee, term or any other provision agreed by government). 19.3.4 Outcome • Government may either approve any tender made under the competitive tender process or accept the offer from the private party arising from the benchmarking process. • The service payment will then be adjusted in accordance with agreed cost sharing arrangements185 and with such modifications as required to reflect the terms and conditions of the approved tender or accepted offer.186 • If the private party enters into a subcontract with the approved tenderer on the terms of the approved tender, the services provider subcontract will be deemed to be approved by government under any replacement of subcontractor approval provisions. • If government and the private party are negotiating in good faith or a dispute is being resolved through the dispute resolution procedures regarding government approval of a tender or the acceptance of the private party's offer, then the private party will 183 Although government may have a role in overseeing/observing the tender process, it is simply to ensure it is compliant with agreed process requirements. The risk and cost of carrying out the tender process and appointing appropriate subcontractors, rests with the private party. 184 Appropriate interface arrangements between operators will need to be considered on a project-by-project basis. 185 See paragraph 19.3.5. 186 The market testing process will result in a 100 per cent pass through of the increase or decrease in the cost of providing the market tested services whether this is determined through the approved tender or the accepted offer. April 2008 82 Partnerships Victoria Updated Standard Commercial Principles continue to provide the market tested soft services at the existing price until that negotiation or dispute is resolved. 19.3.5 • Cost sharing arrangements Any decrease in the cost of providing or subcontracting the relevant services under the approved tender or the accepted offer (as the case may be) will, depending on value for money considerations, either be shared on a percentage basis to be agreed in light of the project specifics, or fully retained by government.187 Although government may on individual projects fully bear any cost increases where it is value for money it will seek to substantially but not fully bear the increase.188 The respective percentages may be items upon which the private party is required to bid. 187 Generally, government will look to share in any decrease on a 50:50 basis. However, this may vary on a project-by-project basis. 188 Where government seeks to share it, less than 100 per cent of the increase in the cost of providing the benchmarked soft services will be passed through to government. Although government understands the need to share such costs increases, it must also ensure that the private party is fully incentivised to continually control its costs and to mitigate against any cost increases. April 2008 83 Partnerships Victoria Updated Standard Commercial Principles 20. Subcontractors Principle All subcontracts and material sub-subcontracts must be in an agreed form. The main construction and operations subcontracts may not be amended without government consent. Amendments to other material subcontracts (including, sub-subcontracts) which may impact on government's rights or lessen the ability of the private party to perform its obligations, may not be made without government consent. The private party is not relieved of any of its obligations and liabilities under the project agreement by subcontracting the performance of the contracted services. 20.1 Subcontracts - generally 20.1.1 Timing of appointment of major subcontracts 189 Government will, as a standard position, require the private party to appoint the main construction and operational services subcontractors at contractual close. However, in exceptional circumstances, this may be a condition precedent to financial close. 20.1.2 Construction and operations subcontracts to be in agreed form • The construction and operations subcontracts entered into by the private party (in respect of all or any part of the contracted services) must be in a form agreed by government.190 • Provided there is compliance with all other requirements set out in this section 20, government's prior written approval to every subcontract will not be required. 20.1.3 Effects of unapproved amendments Government will not be bound by, and none of its rights (under the project agreement or otherwise) will be affected by, any amendment to, termination, assignment or replacement of, any subcontract entered into by the private party, which has not been approved by government.191 189 A breach of any of the subcontractor provisions (including unauthorised amendments to subcontracts) will constitute an Event of Default, see Default regime in section 27 (Default). 190 Details of the type of provisions required in material subcontracts (which includes the main construction and operations subcontracts) are more fully set out in paragraph 20.2.3. 191 See 20.3 in respect of amendments to material subcontracts. April 2008 84 Partnerships Victoria Updated Standard Commercial Principles 20.2 Additional material subcontract requirements 20.2.1 Material subcontracts • The project agreement will specify what type of subcontracts (including subsubcontracts) are to be regarded as 'material'. They will usually include subcontracts above a specified threshold value, but may also include subcontracts of a specified duration and subcontracts for the provision of particularly important or sensitive services (such as security services in a prisons contract). • The threshold value will depend on the nature and value of the project and whether the subcontract is for construction or operation. However, it is effectively intended to represent a material part of the works or operational services (as appropriate). • Material subcontracts will be deemed to include the main construction and operations subcontracts. 20.2.2 Provision of material subcontracts The private party must promptly provide to government a copy of each material subcontract entered into. 20.2.3 Terms and conditions of material subcontracts Each material subcontract must include192: (a) a covenant requiring entry into a side deed (if requested by government) and collateral warranty with government and for the assignment, at government's option, of the benefit of the material subcontract to government if the project agreement is terminated; (b) an undertaking from the subcontractor to provide such consents and information as may be required under the project agreement in respect of its employees;193; and (c) provisions recognising and permitting government to exercise its step-in rights and any of its rights arising as a result of a default or probity event.194 In addition, the main construction and operating contracts must include: (a) an undertaking from the subcontractor to rectify any defects; 192 These reflect government's minimum requirements and are not intended to be an exhaustive list of material subcontract requirements. Additional requirements or amendments to the requirements may apply on a projectby-project basis. 193 Employee-related requirements will be more fully detailed in the project agreement on a project-specific basis. 194 A probity event will be defined to include an event, matter or thing that relates to a subcontractor and has a material adverse effect on the public interest and public confidence in the facility or which involves a material failure by the subcontractor to achieve or maintain standards of ethical behaviour reasonably expected of an entity involved in a government project. See section 37 (Probity). April 2008 85 Partnerships Victoria Updated Standard Commercial Principles (b) an undertaking from the subcontractor to provide such guarantees, warranties and manuals as are required by the private party; and (c) provisions which give full effect to the provisions of the project agreement relating to intellectual property and moral rights. 20.2.4 Collateral warranty No material subcontractor195 is to be engaged in connection with the works or contracted services without having delivered to government a collateral warranty196 in substantially the form set out in the project agreement. 20.3 Amendments to material subcontracts • The main construction and operation subcontracts (to be determined on a project-byproject basis) are not to be amended, terminated, assigned or replaced without government's prior written consent. • The other material subcontracts are also not to be amended, terminated, assigned or replaced without government's prior written consent where such amendment may impact on government's rights or lessen the ability of the private party to satisfy its obligations under the project agreement. • Where prior government consent is not required, the private party must give government prompt notice of the termination or material amendment of a material subcontract. • The private party must not, without government's prior written consent, compromise or waive any claim it may have against a material subcontractor. 20.4 Side deed A side deed (substantially in a form agreed by the parties and set out in the project agreement) must be provided in respect of the construction and operations subcontracts. 20.5 • 195 Subcontractor requirements The private party must ensure that each subcontractor is reputable and has access to sufficient experience, expertise and ability to perform its obligations in accordance with the project documents. A material subcontractor is a subcontractor which enters into a material subcontract. 196 The collateral warranty constitutes a direct covenant from the subcontractor in favour of government with respect to its performance of relevant obligations including, without limitation, maintenance and non-vitiation of insurances, provision of information regarding defaults and claims, and the continuing performance by the subcontractor of its obligations in certain circumstances for the benefit of government. This is a necessary element of government's 'security' package, given that it is dealing with a special purpose vehicle which itself does not have the necessary resources and competencies to perform the project. In addition, since government consent to all subcontracts is not required, it needs direct rights against the subcontractors (such as making claims in respect of defects) which are not dependent on the subcontract or upon government exercising its stepin rights. April 2008 86 Partnerships Victoria Updated Standard Commercial Principles • Key material subcontractors must not be replaced without government's prior written consent.197 • In respect of Change in Control in material subcontractors, refer to section 21.198 20.6 Private party's obligations in respect of subcontracts The private party must: (a) comply with its obligations and enforce the terms of any subcontract as necessary to comply with the project obligations; and (b) advise government of any claims made by a material subcontractor (in respect of outstanding payments or otherwise). 20.7 Subcontractors appointed by financiers The subcontractor requirements set out in this section 20 also apply to any substitute subcontractor appointed by financiers under their funder's direct agreement. 20.8 No relief to private party by subcontracting obligations The private party is not relieved of any of its obligations and liabilities under the project agreement as a result of subcontracting any of the contracted services or government's approval of any subcontractor. The private party will, in each instance, be responsible for the subcontractors' performance. 20.9 Probity The private party must use reasonable endeavours to ensure that all of its employees, subcontractors and authorised officers (and those of all material subcontractors) are competent, experienced, reputable, hold relevant licences and are of good character. 197 It is intended that this generally only capture the main construction and operating subcontractors. However, depending on the importance of the other material subcontracts, this requirement may be extended to other material subcontracts. 198 Key material subcontractors must not undergo an unauthorised Change in Control. Failure to rectify the situation by the private party may constitute an Event of Default. See section 21 (Change in Control) for further details. April 2008 87 Partnerships Victoria Updated Standard Commercial Principles 21. Change in Control199 Principle With the exception of transfers to related bodies corporate and of listed shares and interests, the private party must obtain prior government consent to any Change in Control of the private party or any member of the private party's group and to any change in the private party group's structure (in each case, from the situation as at contract signing). 21.1 Warranty as to Control The private party will warrant the legal and beneficial ownership of each member of the private party group200 and the private party group structure as at contract signing. 21.2 Change in Control of private party 21.2.1 Prior consent • Except as set out in paragraph 21.2.2, the private party must not permit any Change in Control of any member of the private party group or material subcontractors201 without government's prior consent (not to be unreasonably withheld). It will be reasonable for government to withhold its consent if any of the conditions in paragraph 21.3 (Consent may be withheld) apply. • Failure to obtain this consent will give rise to a government right of immediate termination as a Default Termination Event (where it relates to the private party) or a default subject to cure as an Event of Default (where it relates to key subcontractors or other relevant related bodies corporate such as a parent guarantor). Where it is an Event of Default, the private party may be required to cure the event by replacing the subcontractor or parent guarantor within a 199 'Control' means the ability or capacity to determine the outcome of decisions about the relevant entity's financial and operating policies. 'Change in Control' means a change; (a) in the board of directors or decision making control or influence; (b) in the parties who are able to cast (or control the casting) of 20 per cent or more of the votes at a general meeting; or (c) in the shareholding which affects 20 per cent of the shares. 200 The constitution of the private party group will be defined on a project-specific basis. However, it will generally include all relevant related bodies corporate of the private party as at contract signing or as otherwise approved by government during the contract term in accordance with Change in Control provisions. 201 In certain projects, government may require some control over key material subcontractors ( e.g. for security or other public interest reasons or where government has placed particular importance on the identity, ability or financial strength of the original subcontractor when selecting the winning bidder). In these circumstances, Change in Control provisions relating to key material subcontractors will be introduced. April 2008 88 Partnerships Victoria Updated Standard Commercial Principles reasonable period. The private party must notify the State of any change in the legal and beneficial ownership of the private party, its relevant related bodies corporate and key subcontractors (i.e. even where the State’s consent is not required because it is not a Change in Control or because it falls in the exception in paragraph 21.2.2). 21.2.2 Exception to consent requirement Government's prior consent is not required for a Change in Control of any listed equity interests202 or any transfer of equity interests by a party to its related body corporate. 21.2.3 • Publicly listed holding companies If a Change in Control occurs due to the transfer of listed shares or interests in an entity with ultimate control of any member of the private party group or, where relevant, a key subcontractor: (a) the private party must promptly notify government of such event (providing full details); and (b) government must notify the private party within a specified period whether it accepts or rejects the Change in Control. • If government rejects the Change in Control, the private party must procure that the relevant person ceases to have the voting power or control or to hold the share capital or other equity interests (giving rise to the Change in Control), within a specified time. Failure to so procure will give rise to a government right of immediate termination as a Default Termination Event (where it relates to the private party) or a default subject to cure as an Event of Default (where it relates to key subcontractors or other relevant related bodies corporate such as a parent guarantor). Where it is an Event of Default, the private party may be required to cure the event by replacing the subcontractor or parent guarantor within a reasonable period. • Government may, but is under no obligation to, provide pre-approval to a Change in Control if the private party so requests and provides sufficient information to government. 21.3 Consent may be withheld Government may withhold its consent to a Change in Control if it is of the reasonable opinion that one or more of the following conditions apply: (a) the private party has not provided it with full details of the proposed Change in Control and any further information requested by government; (b) the Change in Control is to take effect prior to the second anniversary of Commercial Acceptance (where it relates to the private party only); (c) the proposed entity:203 202 Equity interests includes shares or units. 203 Proposed entity to be considered and defined on a project-specific basis. April 2008 89 Partnerships Victoria Updated Standard Commercial Principles (i) is not solvent and reputable; (ii) has an interest which conflicts in a material way with the interests of government and is involved in a business or activity which is incompatible or inappropriate in relation to the construction or operation of the facility; and (iii) does not have a sufficient level of financial and technical capacity; (d) the proposed Change in Control is against the public interest; (e) the proposed Change in Control would increase the level of risk or liabilities to government; or (f) the proposed Change in Control would impact adversely on the ability or capacity of the private party to perform its obligations under the project agreement or any other project documents and, if applicable, of the material subcontractor to perform its obligations under the material subcontract. April 2008 90 Partnerships Victoria Updated Standard Commercial Principles 22. Modifications Principle Government may initiate modifications to the facility and the service specifications at any time during the contract term. The cost of government-initiated modifications will be borne by government. The private party may initiate modifications to the facility at any time during the contract term. Government will have complete discretion as to whether and on what basis it accepts a proposed modification. If accepted, the modification will be funded by the private party. 22.1 Government-initiated modification to the facility 204 22.1.1 Right to request Government may at any time request a modification to the facility by serving a notice on the private party.205 22.1.2 Private party's proposal • Within a defined period after government's request, the private party must advise government of the cost of preparation of a proposal for carrying out the requested modifications. Government will either accept or reject this quote. • If government rejects the quote, it may: • 204 (a) require the private party to submit a further price; (b) refer the issue to an independent expert for dispute resolution; or (c) advise the private party that it will not proceed with the modification. If government accepts the quote for the proposal, the private party must provide government with its proposal for carrying out the requested modification, including details of any effect on the facility and delivery of the contracted services, necessary Government-initiated modifications to services and service specifications are dealt with in paragraph 22.3. 205 Government will provide the private party with sufficient detail of the required modification to enable the private party to quantify the effects and costs in its proposal (see paragraph 22.1.2). If the private party considers a government request constitutes a modification, the private party will be required to notify government of this. A determination will then be made as to whether the request constitutes a government-initiated modification and whether government wishes to proceed with that request. April 2008 91 Partnerships Victoria Updated Standard Commercial Principles capital expenditure, any impact on recurrent costs (on a fully transparent basis) and, where necessary, how the private party will fund the costs.206 22.1.3 • Cost of modification works The cost of carrying out government-initiated modification works will be borne by government. Government will determine (and advise the private party when notifying it of its modification request) whether it: (a) requires the private party to initially fund the modification works (with government paying for that cost through an adjusted service fee over the contract term). This requirement will be subject to the last bullet point in this paragraph 22.1.3; (b) will pay the initial costs directly through a one-off capital expenditure payment; or (c) will, subject to the private party's agreement, extend the operating term. • The private party will only be compensated for its reasonable costs arising as a direct result of carrying out the modification works. The private party must provide government with all quotations it receives in relation to carrying out the proposed modification on an open-book basis. • During the bid phase of the project, the private party will be required to bid fixed or maximum margins and other on-costs that the private party or its subcontractors may apply to the cost of modifications during both the design and construction phase and the operating phase. These will be taken into account in evaluation of the bids and, once agreed by government, will be included in the project agreement. • The private party will not be entitled to apply any margin or other on-costs to the price charged to the private party (by its subcontractor) for modifications up to a specified threshold. This threshold will be determined on a project-specific basis and will depend on the value of the project, but is intended to capture those modifications for which the private party does not require additional resources or which do not materially affect the private party's project risk profile. • Allowance will be made for the builder's margin for profit up to the relevant bid margin (in respect of the modification works only) and any incremental changes in overhead, management and administration costs (which are to be provided at no more than the bid rates). • An allowance may also be made for delay costs or prolongation costs arising directly from the variation (subject to there being no double counting). • Any compensation amount will be reduced by an amount equivalent to: (a) expenditure that was anticipated to be incurred to replace or maintain assets that have been affected by the government modification and which will be avoided as a result of the modification; and (b) any previously planned capital costs that will no longer be incurred due to the modification. 206 This is not an exhaustive list of everything the private party must provide for any one project but a general description of the key items. April 2008 92 Partnerships Victoria Updated Standard Commercial Principles • The private party must provide evidence that it has used reasonable endeavours (including, where practicable, the use of competitive quotes) to ensure that its subcontractors minimise increases in costs and maximise any reduction in costs. • Where government requires the private party to fund the modification and the modification requires capital expenditure in excess of a specified limit,207 the private party must use its best endeavours to obtain competitive funding for the cost of the modification works. However if, having used its best endeavours, the private party is unable to obtain funding acceptable to government, the private party does not have to carry out the modification unless government pays up front for the cost. 22.1.4 Acceptance or rejection of a proposal Government may, at its discretion, accept (with or without conditions) or reject the private party's proposal or withdraw its modification request. 22.1.5 • Failure to agree Where the parties fail to agree upon the cost of the modification works and government still wishes to proceed with the modification, the cost will be determined either by: (a) the independent expert during the construction phase;208 or (b) competitive tender209 during the operating phase. • Where the cost is to be determined by competitive tender, the private party must appoint the tenderer whom the parties agree (or an independent expert determines) offers best value for money.210 In the event that government agrees to proceed, it will compensate the private party for the cost in accordance with the tender which it is agreed or determined offers best value for money. • Where the parties fail to agree on any aspect of the private party's proposal (other than the cost of the modification works during the operating phase), the matter may be referred to an independent expert for resolution. 22.1.6 Government's options following expert determination Where the expert determination or tender cost is not to government's satisfaction, government may elect not to proceed with the modification works or to carry out the modification itself.211 207 To be agreed on a project-specific basis but is intended to be set at a fairly low level in light of the value of the project. 208 See section 32 (Dispute resolution). 209 The private party will call for tenders (for a fixed price for carrying out the works) from a list of three contractors agreed with government or determined by an independent expert. 210 The value-for-money assessment will have regard to, amongst other things, the experience, skills, reputation and financial capacity of each tenderer. 211 Where government carries out or appoints a third party to undertake the modification works, it will compensate the private party for costs directly incurred by the private party as a result of such works. April 2008 93 Partnerships Victoria 22.1.7 Updated Standard Commercial Principles Obligation to carry out modification works • Where a proposal for carrying out the modification is agreed by the parties or government wishes to proceed with a modification in accordance with the independent expert determination or tender proposal, the private party must implement the modification. • The private party must continue to provide the contracted services except to the extent that it is prevented from doing so as a consequence of implementing the modification. 22.1.8 Adjustment to service fee • Any adjustment to the service fee (to reflect the modification cost) must be agreed by the parties or determined by an independent expert in accordance with the service fee adjustment principles.212 • Any payment made to the private party by government (as a result of a modification) will be on a whole-of-life basis (i.e. it will take into account the positive and negative effect of the modification on the private party's recurrent expenditure, as well as the capital cost of any works). 22.1.9 Third party costs Where government does not proceed with a government-initiated modification, it will pay the reasonable, fully audited third party costs incurred by the private party in preparing its proposal up to the amount of the quote given by the private party under section 22.1.2 (Private party's proposal). 22.1.10 Works that do not constitute modifications Government-initiated modifications will not include: (a) during the operational phase, any minor works;213 (b) the development and refinement of the design documentation in accordance with the project agreement; (c) during the design and construction phase, minor design changes to the facility works of a non-structural nature which are requested by government which do not, in aggregate, increase the capital cost of the works214 or cause a delay to the achievement of completion of the facility by the Date for Commercial Acceptance; (d) any refurbishment and maintenance works required during the operational phase; or (e) any other modifications required to ensure the facility is fit for its intended purpose. 212 See paragraph 18.5 in section 18 (Payment provisions). 213 See paragraph 22.4 (Minor works). 214 Government may, in certain projects, identify a monetary threshold for these purposes. April 2008 94 Partnerships Victoria Updated Standard Commercial Principles 22.2 Private party initiated modification works 22.2.1 Private party's right to request modification • The private party may at any time request modifications to the facility works provided they are consistent with the project agreement and the functional brief and do not have an adverse effect on the facility or the delivery of the contracted services (including the core services). • The private party must demonstrate that it has the appropriate financial and technical resources to undertake the proposed modification. 22.2.2 Government's response Government may not unreasonably withhold its approval to a private party proposed modification. However, it may accept the proposal subject to conditions and amendments. Where government does so, the private party may either accept them or withdraw its proposal. 22.2.3 Private party's right to proceed The private party may carry out the modifications only if its proposal is approved by government. Where it is so approved, the private party must implement the modification at its own cost, in accordance with its proposal and otherwise in accordance with all the design, construction and commissioning provisions of the project agreement as if it were part of the original works. 22.2.4 No extension of time No extension of time (to the Date for Technical Completion, the Date for Commercial Acceptance, the Sunset Date or any other milestone date) will be given to the private party as a consequence of any private party-initiated modification unless government considers (at its sole discretion) that to do so would deliver value for money. 22.2.5 Government to share in any efficiency or saving Government will share in any revenue upside and/or saving arising from the modification (whether as a result of a decrease in the private party's capital expenditure or recurrent costs or the subcontractors' costs and having deducted the private party's costs in implementing the change). Sharing will occur in accordance with a mechanism to be agreed as part of the project agreement. Any service fee reduction (reflecting the saving being shared) will be set in accordance with the service fee adjustment principles.215 215 See paragraph 18.4 in section 18 (Payment provisions). April 2008 95 Partnerships Victoria 22.2.6 Updated Standard Commercial Principles Modifications required due to a Change in Law Government cannot reject a modification required by the private party to comply with a Change in Law. The costs of such modifications will be dealt with in accordance with the Change in Law provisions.216 22.3 Government-initiated modifications to service standards 22.3.1 Government's right to request modification Government may at any time request an addition or modification to the specified service standards (i.e. key performance indicators (KPIs)) provided it has first consulted with the private party. 22.3.2 Private party's proposal Within a defined period from government's request, the private party must provide government with its proposal as to how it will implement the modification, the effects of the proposed modification on the contracted services and the private party's ability to deliver them, the estimated effect of the modification on the private party's recurrent expenditure and any necessary adjustment to the service fee. 22.3.3 Obligation to implement KPI modifications If government agrees with the private party's proposal, the private party must provide the contracted services to the amended KPI. It must do so in a way which avoids or minimises any disruption to the delivery of the contracted services to specification. 22.3.4 Failure to agree on private party's proposal If the parties, after making reasonable endeavours, cannot agree upon the private party's proposal, the matter will be referred to an independent expert for resolution. 22.3.5 Adjustment to the service fee The cost of implementing a government-initiated KPI modification will be borne by government through an adjustment to the service fee. Any adjustment to the service fee must be made in accordance with the service fee adjustment principles.217 22.3.6 Government sharing of any benefit arising from a modification Government will share in any cost savings to the private party arising from a KPI modification (having deducted from the saving the private party's costs in implementing the change) by way of a reduced service fee in accordance with a mechanism to be agreed as 216 See section 23 (Change in Law). 217 See paragraph 18.4 in section 18 (Payment provisions). April 2008 96 Partnerships Victoria part of the project agreement. principles.218 22.4 Updated Standard Commercial Principles Any sharing will reflect the service fee adjustment Minor works • In addition to and notwithstanding the modifications regime, government may elect to create a minor works regime.219 • The minor works regime will be utilised by the private party to complete works (Minor Works), the cost of which fall under specified per event monetary thresholds and which are considered to be a routine element of administering the relevant social infrastructure (whether it be a hospital, school etc). Any thresholds will be determined on a project-specific basis. • A minor works regime will only be relevant to works completed during the operational phase of the project. Minor works requested by government or the operator of the facility will be deemed to be part of the Services. No additional margin or other costs will be payable to the private party for the minor works. • If minor works are requested, the private party must cost them on an open-book basis. • Minor works will not impact on the risk transfer between the private party and government. Although it is envisaged that the minor works will generally be agreed directly between the facility operator and the facilities management subcontractor. • Generally, any overspend of the provisional sum allowed for minor works over the operating term will be recovered directly by the facilities management subcontractor from the facility operator on an annual basis. Any annual underspend will be rolled forward to the next year. Any accumulated underspend will be payable to the State. 218 See paragraph 18.4 in section 18 (Payment provisions). 219 In making this decision, government will consider (inter alia) the level of minor modifications expected during the operation phase as well as budgetary constraints of the operator. April 2008 97 Partnerships Victoria Updated Standard Commercial Principles 23. Change in Law Principle Government will compensate for changes in law which exclusively affect the project or category of project. Government will also share the cost of changes in law which necessitate significant capital expenditure or operating cost effects not captured through indexation or benchmarking. Government expects thresholds to be realistic so the private party is incentivised to minimise the costs of implementing changes in law. Generally, changes in tax arrangements are to be borne by the private party. 23.1 Scope of Change in Law 23.1.1 Definition 'Change in Law' encompasses the following occurrences after the execution of the project agreement: (a) the enactment of new laws; (b) the amendment, repeal or change of any law; and (c) any judgment of a relevant court of law which changes a binding precedent. For these purposes, 'law' means legislation, subordinate legislation, rules and regulations and policies or guidelines with which the private party is legally required to comply. 23.1.2 Exclusions Change in Law does not include: (a) changes in the way the law is interpreted (except as provided in paragraph 23.1.1(c)); (b) changes to the Income Tax Assessment Act 1936 (Cth), the Income Tax Assessment Act 1997 (Cth) and the A New Tax System (Goods and Services Tax) Act 1999 (Cth); (c) changes in law or policy which, as at the date of the project agreement: (i) were published or of which public notice had been given (even as a possible change); or (ii) a party experienced and competent in the delivery of services similar to the contracted services (including the works) would have reasonably foreseen or anticipated, in substantially the same form as the change eventuating after the date of the project agreement; April 2008 98 Partnerships Victoria Updated Standard Commercial Principles (d) changes in law or policy effected in response to an illegal act or omission by the private party (other than an act or omission which becomes illegal by virtue of the change); and (e) a change in relation to Part IVAA - Proportionate Liability of the Wrongs Act 1958 (Vic) or its application. 23.2 General Change in Law 23.2.1 Relief for Change in Law • Relief for Change in Law220 is limited to changes which: (a) require significant capital expenditure (as set out in paragraph 23.2.2); or (b) have significant operating cost effects221 not captured through benchmarking or indexation (hard operating costs) (as set out in paragraph 23.2.3). 23.2.2 General Change in Law as a shared risk and agreeing suitable thresholds • Although change of law is not a risk which the private party cannot control, in practice the private party is usually in the best position to manage the effects of changes of law and minimise their impact on the business. For this reason a sharing approach is often the most equitable way to ensure that the costs of implementing changes in law are minimised. The advantage of sharing risk in the way described in paragraphs 23.2.2 and 23.2.3. is that this should incentivise the private party to minimise the cost of implementing the change (as opposed to simply invoicing the government for whatever it costs), reduce any concern the private party may have that government may take advantage of the situation and also enable the private party and its financiers to quantify the private party's maximum exposure. • Both the government and the private party should seek to ensure that cost and adequate risk transfer are balanced as far as possible to achieve the best value for money on a particular project. The threshold figures agreed and the number of graduated steps will take into account the size of the project and the impact of other factors such as the likelihood of environmental and health and safety legislation.222 220 As distinct from project specific Change in Law - see paragraph 23.3 below. 221 Government will only bear the operating cost effects above a threshold (not captured through indexation or benchmarking) in a core services model project. This principle does not necessarily apply to economic infrastructure projects. 222 Government hopes that the competitive bidding process will incentivise bidders to accept realistic maximum thresholds and competitively price general Change in Law risk. April 2008 99 Partnerships Victoria 23.2.3 • • Updated Standard Commercial Principles Capital expenditure relief Government will share the relevant capital expenditure cost effects arising from a change in law (per event) in accordance with a three tiered cost sharing mechanism as follows:223 (a) the private party will bear 100 per cent of the capital expenditure cost effect up to a specified threshold (first threshold); (b) the private party and government will share the capital expenditure cost effect above the first threshold on a percentage share basis (to be agreed on a projectspecific basis) until a higher threshold (second threshold) is reached;224 and (c) government will bear 100 per cent of the capital expenditure cost effect above the second threshold. Where a change in law results in both increased capital expenditure and hard operating costs, government will not consider the private party's claim for capital expenditure relief until the next specified review date225 (following the private party's claim) as part of its assessment of the private party's claim for hard operating costs. However, where the increased capital expenditure is above a specified threshold226 and the private party, having used its reasonable endeavours, is unable to obtain competitive funding for the cost of additional works which is acceptable to government, government will consider the private party's claim for capital expenditure in isolation from the operational effect at the time the private party submits its claim. 23.2.4 Hard operating cost relief227 • For hard operating cost increases, no relief will be given for costs arising in the interval before the next specified review date. Subject to the requirements in the following bullet point, government will share the increased hard operating costs arising after the relevant review date above a specified threshold.228 • Government will only share hard operating cost increases as set out above, provided: (a) 223 the private party provides a written claim to government for such cost increases as soon as reasonably practicable following the relevant change in law; and The form of payment relief given shall be at government's discretion, see paragraph 23.4. 224 This three tiered cost sharing mechanism is illustrative only. More stages in the graduation could be considered on a project-specific basis if the private party and government believe this achieves a better balance between cost and achieving adequate risk transfer (see footnote 205). 225 The relevant review dates for these purposes will be determined on a project-specific basis. However, it is expected that they will coincide with the benchmark dates. 226 To be agreed on a project-specific basis. 227 Examples include cost increases arising from a general change in law affecting the provision of hard facilities management services such as maintaining large items of plant and equipment and changes to the ‘as-built’ form. Government will share the risk of increased hard facilities management costs on a percentage basis subject to thresholds on a project-specific basis, in the same way that the risk of increased capital expenditure costs are shared. 228 It is intended that this threshold will be lower than the threshold for capital expenditure. paragraph 23.2.2. April 2008 However, see 100 Partnerships Victoria (b) Updated Standard Commercial Principles that sufficient detail of the relevant operating cost increases (including steps taken to mitigate its effect) is provided by the private party to government. • Government will not assess or respond to the private party's claim for hard operating cost increases until the next review date following the private party's claim. • To the extent that government bears hard operating costs in accordance with the above regime, the service fee will be increased accordingly over the balance of the term from the next review date following the relevant change in law with no retrospective adjustment for increased costs incurred during the period prior to that review date. 23.2.5 Sharing of Change in Law benefits Government will share in any cost benefits or savings arising from a change in law above a specified threshold229 on a percentage share basis to be agreed between the parties. Government will share in any cost savings or benefits whether arising from reduced hard operating costs or because capital expenditure that was otherwise anticipated to be incurred by the private party is avoided as a result of the change in law. Government will only share hard operating cost savings or benefits arising in a period during which it would otherwise share in cost increases. To the extent government shares in a cost benefit or saving, the service fee will be reduced accordingly over the balance of the term. 23.2.6 No relief for soft operating costs230 Costs arising from general changes in law affecting soft facilities management services should generally be for the account of the private party, as these services are reviewable and the private party is protected on pricing the risk through the combined effects of government review, market testing and indexation. 23.3 Project-specific Change in Law 23.3.1 Project-specific changes compensable • Where a change in law is a project-specific Change in Law (as set out in paragraph 23.3.2), government will, subject to nominal threshold levels to be agreed on a projectspecific basis,231 take full risk of a project specific change in law (per event) and compensate the private party for any increases in the private party's operating costs, as well as bearing any capital expenditure consequences.232 However, government will also share in the benefit of any decreases in operating costs. • Where the private party's claim for relief is only in respect of capital expenditure arising from a project-specific Change in Law, government will assess and respond to the 229 To be agreed on a project-specific basis. 230 Examples of soft operating cost increases would include services such as cleaning, security, grounds maintenance, porterage and catering. 231 See paragraph 23.3.4. 232 See paragraph 23.4. April 2008 101 Partnerships Victoria Updated Standard Commercial Principles private party's submission as soon as practicable following the submission of the private party's claim.233 • Subject to the bullet point that follows, where the private party's claim is only in respect of hard operating cost increases or a mixture of capital expenditure and hard operating cost increases, government will assess and respond to the private party's claim at the next review date following the submission of the claim. To the extent the private party's claim is accepted by government, government will compensate the private party (by way of a one-off payment) for any approved capital expenditure and hard operating costs incurred by the private during the period between the relevant project-specific Change in Law occurring and the relevant review date. • Where: (a) the private party's claim is for a mixture of capital expenditure and hard operating cost increases; (b) the capital expenditure is above a specified threshold;234 and (c) the private party, having used its reasonable endeavours, is unable to obtain competitive funding for the cost of additional works which is acceptable to government, government will consider the private party's claim for capital expenditure in isolation from the operational effect at the time the private party submits its claim. 23.3.2 Meaning of project-specific Change in Law A project-specific Change in Law is a change in law of the relevant State, the terms of which apply expressly to the: (a) project and not to similar projects procured by government; (b) project facility or site and not to other similarly situated land or facilities; (c) private party in relation to the project and not to other persons; or (d) companies undertaking projects procured under public private partnerships arrangements and not to other persons. 23.3.3 Exceptions A change in law will not be a project-specific Change in Law: (a) solely on the basis that its effect on the private party is greater than its effect on other companies; or (b) if it is a change in taxes (including GST). 233 The project agreement will specify appropriate time periods for government to assess and respond to the private party's claim. 234 To be agreed on a project-specific basis. April 2008 102 Partnerships Victoria 23.3.4 Updated Standard Commercial Principles Threshold levels The private party will be entitled to compensation for any direct cost increases (including financing costs)235 either in the works or the provision of services arising from a projectspecific Change in Law above a nominal threshold.236 23.4 Form of relief 23.4.1 Form of relief at government's discretion • • Government may, at its discretion, choose to provide the private party with compensation relief in any of the following forms: (a) an increase in the service fee over the balance of the term; (b) a lump sum to be paid at the time of the next services fee; or (c) subject to the private party's agreement, an extension to the operating period. Where option (a) is adopted and the cost of such capital expenditure is in excess of a specified limit,237 the private party must use its best endeavours to obtain competitive funding for the cost of the works. If, after using its best endeavours, the private party is unable to obtain funding acceptable to government, government will pay for those costs up-front by way of a lump sum payment. 23.4.2 Adjustment of service fee The service fee will be adjusted or a lump sum payment will be determined in accordance with the service fee adjustment principles for the project,238 The financial model will be adjusted in accordance with the service fee adjustment principles to reflect the compensation amount. 235 The private party will not be compensated for any profit margin on any additional costs incurred (only profit margins at the subcontractor level will be compensated (to the extent incurred)). 236 These nominal threshold levels will be determined on a project-specific basis but are intended to avoid the administrative burden to government of frequent claims for relatively small amounts of monetary relief. Examples of the type of thresholds government may consider appropriate are $200,000 (indexed) for capital costs and $20,000 (indexed) per annum for operating costs. 237 To be agreed on a project-specific basis but is intended to be set at a fairly low level in light of the value of the project. 238 See paragraph 18.4 in section 18 (Payment provisions). April 2008 103 Partnerships Victoria 23.5 Updated Standard Commercial Principles Threshold requirements 239 Relief for Changes in Law and project-specific Changes in Law will only be given to the private party in accordance with the principles of this section 23 provided the private party: (a) uses all reasonable endeavours to mitigate any costs incurred as a result of the relevant change in law; and (b) notifies government of the relevant change in law and its effects as soon as possible after the private party becomes aware (or should have reasonably been aware) of the change or its effects. 23.6 Inconsistency with performance standards The private party must continue to provide the services except to the extent that they cannot be provided as a necessary and intended consequence of implementing and adopting the project-specific Change in Law. 239 This is not intended to be an exhaustive list of the threshold requirements for the giving of Change in Law relief by government. Whenever government bears some of the risk of a change in law, the private party should be obliged to keep any cost increases to a minimum and this should be clearly stated in the project agreement. This duty to mitigate can be measured, in part, by reference to the extent to which price increases in comparable sectors are experienced. It will also require the private sector to foresee and anticipate the effect of changes in law, particularly in relation to expenditure which it has planned to incur anyway in the ordinary course of the project agreement. April 2008 104 Partnerships Victoria Updated Standard Commercial Principles 24. Force majeure Principle For a limited category of events of exceptional severity which are outside the control of either party and prevent the private party from performing all or a material part of its non-financial obligations under the project agreement, the private party will be given relief from termination and any other liability for breach.240 24.1 Qualifying events The 'Force Majeure Events' for which relief will be given are: (a) lightning, cyclones, earthquakes, natural disasters, landslides, tsunamis and mudslides; (b) civil riots, rebellions, revolutions, terrorism, insurrections and military and usurped power, sabotage, ex public enemy and war (declared or undeclared); (c) ionising radiation, contamination by radioactivity, nuclear, chemical or biological contamination unless caused by the private party or subcontractors;241 (d) fire, flood or explosion caused by events referred to in paragraphs (a) or (b) above; and (e) during the operating phase only, one or more utility services required for the operation of the facility not being available for use at the mains connection to the site, due to a major distribution or transmission system failure, except to the extent the non-availability is because of an act or omission of the private party or its subcontractors including failure to comply with any of its obligations such as having to provide back-up or other security requirements,242 or a dispute between the private party and the relevant utility supplier. where these directly delay or prevent the private party performing all or a material part of its non-financial obligations under the project agreement.243 240 Although the principles in this section 24 focus on giving relief to the private party for a breach resulting from a force majeure event, the same regime will apply in respect of government and a breach of its non-financial obligations (if any). 241 The reference to contamination in this definition excludes the risk of pollution and contamination allocated to the private party in accordance with section 5 (Environmental issues). 242 Regardless of whether or not provision of such back-up supply, connection or other security of supply would have prevented the event occurring. 243 Although what is considered to be a Force Majeure Event for a particular project may vary, the definition should only be expanded where the nature of the particular project necessitates it. The definition will not be extended where to do so would undermine the underlying risk allocation. The definition of Force Majeure Events should only include events which, unlike EOT Events or Intervening Events, are likely to have a catastrophic April 2008 105 Partnerships Victoria • Updated Standard Commercial Principles However relief will not be given when: (a) any of the above events are caused (directly or indirectly) by the private party, any of the private party's related parties, agents or employees or any subcontractor (and in each case, whether as a result of their action or inaction including, as a result of a breach by the private party of its obligations under the project documents); or (b) the occurrence or effects of an event are otherwise within the private party’s control. This includes where the private party should have put in place appropriate contingency plans so as to reduce or avoid any effects on its ability to perform its obligations under the project documents. 24.2 Form of relief 24.2.1 Suspension of obligations • The private party's obligation to provide any contracted service or perform any other obligation affected by a Force Majeure Event will be suspended from the date the private party notifies government of the occurrence of the Force Majeure Event until the Force Majeure Event ceases or the private party ceases (or should have ceased) to be prevented or delayed by the Force Majeure Event.244 • An Event of Default or Default Termination Event will be deemed not to have occurred to the extent that the failure or breach is the direct result of a Force Majeure Event. 24.2.2 Service fee reduced Government's right to abate the service fee while the Force Majeure Event subsists is not affected. Accordingly, the service fee payable by government during the period of suspension will be reduced to the extent that the services are not being delivered as a result of the Force Majeure Event. 24.2.3 Additional relief Where (and only where) a period of suspension arises as a result of a Force Majeure Event which is not: • required to be insured against by the private party under the project agreement245 (as distinct from uninsurable events arising during the term to which the uninsurability regime under the project agreement applies)246, and effect on either party's (although usually the private party's) ability to fulfil its obligations under the contract and which neither party can prevent or where neither party is in a better position to manage the consequences of the event occurring. In practice, such events are highly unlikely to occur and this should be reflected in the drafting of Force Majeure Events as the potential consequences to government under paragraph 24.5 are much more serious than the granting of relief for EOT Events and Intervening Events. 244 The private party is therefore relieved of the risk of contract termination (and other government action for default). 245 Government will consider, on a project-specific basis, the force majeure events which are not required to be insured against, for example, damage caused by earthquake. Once identified, it is only on the occurrence of such Force Majeure Events that government will service forecast senior debt. 246 See paragraph 26.4 of section 26 (Insurance). April 2008 106 Partnerships Victoria • Updated Standard Commercial Principles an insurable risk customarily insured by operators of facilities similar to the facility or providing a service similar to the contracted service, government will service the lower of the actual senior debt commitments and the senior debt commitments forecast by the base case financial model as being due and payable during the period of suspension. 24.3 Temporary measures and alternative arrangements 24.3.1 Best endeavours to mitigate effect During the period of suspension the private party must use its best endeavours to remove or mitigate the effect of the Force Majeure Event and restore the services. This may include incurring reasonable expenditure, rescheduling resources or implementing appropriate temporary measures. 24.3.2 Alternative arrangements During the period of suspension, government may make alternative arrangements for the performance of any suspended services. 24.4 Financial relief 24.4.1 No financial relief unless project agreement terminated Government will not provide any financial relief to the private party during the period of suspension (e.g. to meet the private party's fixed operating costs) other than in respect of senior debt commitments in accordance with paragraph 24.2.3. An appropriate compensation amount will be paid (taking into account payments made in respect of the senior debt during the period of suspension) if the project agreement is terminated for a Force Majeure Event.247 24.4.2 No compensation to government The private party will not be liable to compensate government for any costs or losses government incurs (such as the increased costs of obtaining services from an alternative source) during the period of suspension.248 247 See paragraph 24.5. 248 Paragraphs 24.4.1 and 24.4.2 are consistent with the principle that for risks (such as Force Majeure Risk) which neither party is better placed to control or manage, the loss should lie where it falls. April 2008 107 Partnerships Victoria Updated Standard Commercial Principles 24.5 Termination 24.5.1 Either party may terminate 249 If the Force Majeure Event or its consequences continues to prevent the private party from performing all or a material part of its non-financial obligations for a specified continuous period (usually six to 12 months) either party may terminate the project agreement by giving written notice.250 In addition, the private party’s right to terminate only arises: • during the design and construction phase, once the period for which the builder has advanced consequential insurance has expired; and • during the operational period, where the private party is unable to recover under business interruption insurance. 24.5.2 Compensation Upon termination of the project agreement, government will pay the private party compensation in accordance with the principles set out in paragraph 29.2 in section 29 (Termination payments). 249 For projects involving multiple sites or where the force majeure event otherwise affects a separable portion of the site, the project agreement will contemplate the option of partial termination. 250 In the event that the private party issues a termination notice, government may require the project agreement to continue subject to government paying the service fee in full (less costs not incurred by the private party) for any continuing period. April 2008 108 Partnerships Victoria Updated Standard Commercial Principles 25. Reinstatement and repair Principle Subject to the uninsurability provisions, the private party is responsible, at its cost, for repairing and reinstating any loss or damage to the site, the works or the facility. However, where such loss or damage is a direct consequence of any fraudulent, unlawful or negligent act or omission by government or its associates, government will bear the costs of the private party repairing or reinstating the loss or damage. 25.1 Obligation to repair or reinstate 25.1.1 Proposed reinstatement plan If any part of the site, the facility or the works is damaged or destroyed or cannot be used or occupied, the private party must as soon as practicable notify government of the damage and submit a proposed reinstatement plan for approval.251 25.1.2 Repair or reinstatement The private party must repair the damage or reinstate the facility at its cost in accordance with the approved reinstatement plan, except where it is prevented from doing so by a Force Majeure Event or other event for which relief is given252 or the event which caused the damage is an uninsurable risk in which case the uninsurability provisions referred to in paragraph 26.4 in section 26 (Insurance) will apply. 25.1.3 Insurance proceeds • Any insurance proceeds received in respect of such damage253 (including, any amounts representing insurance proceeds paid by government where the relevant event was uninsurable) must be applied towards the cost of reinstatement or repair. • All insurance proceeds will be paid into a separate insurance account in the joint names of government, the private party and, as appropriate, the private party's financiers, and may only be withdrawn for reinstatement purposes. 25.1.4 Limitation of liability The private party does not bear the risk of property damage or third party claims to the extent that they are the direct result of a fraudulent, unlawful or negligent act or omission of 251 This obligation is subject to government's right to direct the private party not to repair or reinstate (see paragraph 25.2). 252 In each event, the relevant relief regime will apply. 253 This refers to proceeds paid under all risks/physical damage policies, not third party liability, employer's liability, business interruption or advance loss of profits insurance. April 2008 109 Partnerships Victoria Updated Standard Commercial Principles government (or its associates) or a government breach of the project agreement, unless and to the extent that the private party is entitled to, or does, recover under required insurances. 25.2 Direction by government not to reinstate or repair 25.2.1 Direction Where the facility has been materially damaged or destroyed, government may direct the private party not to reinstate or repair the relevant damage and may then also terminate the project agreement.254 25.2.2 No termination If government directs the private party not to repair or reinstate the damage but does not terminate: (a) the private party waives in favour, and for the benefit, of government its right to give a notice of claim under its insurance policy; (b) the private party must pay government any insurance proceeds it receives (including monies paid by government as an insurer of last resort in respect of an uninsurable risk)255;256 (c) the private party will be relieved of its obligations to construct the works or provide the services to the services specification, to the extent reasonably determined by government in the context of the damage;257 and (d) government will issue a government modification request in relation to the private party's reduced obligations.258 25.2.3 Termination If government terminates the project agreement and the damage was caused by an event which was: (a) a Force Majeure Event259, government must pay compensation on the basis of a Force Majeure Termination Event;260 254 It is envisaged that a monetary threshold will be agreed on a project-specific basis, above which the facility will be deemed to be materially damaged or destroyed. In addition, government will consider limiting its ability to exercise this right to a limited period before contract expiry. 255 See paragraph 26.4 in section 26 (Insurance). 256 This is subject to the rights of the financiers under any funder's direct agreement. 257 The service fee will be adjusted in accordance with paragraph 22.1.8 in section 22 (Modifications). 258 See section 22 (Modifications). 259 See paragraph 24.1 in section 24 (Force majeure) for a definition of Force Majeure Event. 260 See paragraph 29.2 in section 29 (Termination payments). April 2008 110 Partnerships Victoria Updated Standard Commercial Principles (b) a private party default, government must pay compensation on the basis of a Default Termination Event;261 (c) an event other than a Force Majeure Event or private party default, government must pay compensation on the same basis as for a voluntary termination by government.262 25.3 Direction by government to reinstate to different specifications Government may require the private party to reinstate or repair the facility on the basis of different specifications. Any such request will be treated as a government-initiated modification (but only to the extent that the specifications differ from those which would otherwise have been required under the project agreement and to the extent that any insurance proceeds do not cover the full reinstatement cost).263 261 See paragraph 29.1 in section 29 (Termination payments). 262 See paragraph 29.3 in section 29 (Termination payments). 263 See section 22 (Modifications). April 2008 111 Partnerships Victoria Updated Standard Commercial Principles 26. Insurance Principle The private party must obtain and maintain such insurances as a prudent owner or services provider would obtain and maintain for the type of facility from which the project services are delivered. In the current insurance climate, government will share within agreed thresholds any insurance cost increases for certain categories of operational insurance. 26.1 Insurance generally 26.1.1 Required insurance The private party must, at its own cost, effect and maintain such insurances throughout the construction and operating phases as a prudent owner or services provider would obtain and maintain for the facility in light of all relevant circumstances including but not limited to the private party's obligations under the project agreement (being insurances of a kind and on no less favourable terms than the minimum insurance requirements specified in the project agreement).264 The private party must also ensure that it and its subcontractors effect and maintain appropriate insurances in accordance with good industry practice and at a prudent level of cover, having regard to the nature and scope of the services each subcontractor is to provide. Levels of cover should be linked to the rate of inflation, such that the amount of insurance increases over time. 26.1.2 Proof of insurance • By financial close, the private party must have provided government with evidence from its insurers that the construction phase insurances are in effect. • Throughout the contract term, the private party must provide government with copies of insurance policies, certificates of currency, renewal certificates and any endorsement slips in relation to all required insurances. If actual policy copies cannot be provided due to commercial confidentiality, appropriately worded certificates confirming expressly all of the insurance terms and conditions, as set out in the contract, must be provided from the insurer or insurance broker. 264 Insurance requirements will reflect the degree of risk transfer, the ability of the private party to pay premiums (relative to the size of the risk), value-for-money considerations and the specifics of the particular project in question. Examples of required insurances during both the construction and operating phase include workers compensation insurance, property/material damage insurance, public/products liability insurance and motor vehicle insurance. In certain instances, insurances may be affected by means of the private party's existing group insurance policies, with appropriate care taken that these are extended to adequately cover the required project risks on an individual and aggregate basis. April 2008 112 Partnerships Victoria 26.1.3 Updated Standard Commercial Principles Reputable insurer The insurances are to be effected and maintained at all times with reputable insurers approved by government and on conditions required by government. When determining whether to accept the insurances proposed by the private party and what conditions it may seek to impose, government may have regard to the rating (if any) of the proposed insurer, the contracting entity of the proposed insurer and their relationship to the ultimate underwriter, the proposed insurer's exposure to other projects of a similar nature in the State and such other matters as government considers relevant in the circumstances. 26.1.4 Amendments The approved insurances are not to be materially changed (including the scope of cover, limits/sub-limits to liability, deductible levels etc.) without government's prior consent (which is not to be unreasonably withheld).265 The private party must indemnify government for its reasonable legal and other costs (if any) associated with determining whether or not to consent to any requested change. 26.1.5 Government may effect insurance policies If the private party fails to effect or maintain the required insurances, government may effect and maintain the relevant insurance and pay the premiums for that insurance. Any amount paid by government will be a debt due and payable from the private party and may be deducted from amounts owing to the private party under the project agreement. 26.1.6 Terms of insurance All required insurance policies must, at a minimum, include: (a) a provision requiring the policy to operate as if each was a separate policy of insurance covering each insured party; (b) a waiver of subrogation against any of the insured parties; (c) a breach of condition or warranty/severability/non-vitiation provision acceptable to government; (d) a provision requiring at least 30 days notice to be given to government prior to cancellation or amendment; and (e) government as a person to whom the benefit of the insurance policy extends for its relevant rights and interests (as appropriate).266 265 In determining whether and on what basis to provide its consent, government will consider the proposed changes in light of market conditions at the time, the impact of the changes on the project risk profile and valuefor-money considerations generally. 266 The extent of government's rights and interests in respect of specific insurance policies (such as public and products liability insurance and workers' compensation insurance) will be detailed in the project agreement. This requirement will not extend to those policies which relate only to private party interests (such as professional indemnity insurance). Please note that the actual terms in which the government's interest is noted in the policies are very important, as the words used will define the extent to which cover is extended and thus the circumstances under which the government can claim on the insurance. It is only notation on the policy that enables this. No form of words in the contract document above will create such a right for the government. April 2008 113 Partnerships Victoria 26.1.7 Updated Standard Commercial Principles Settlement of claims Any insurance proceeds received in respect of repairing or reinstating damage to the site, works or facility must be dealt with in accordance with paragraph 25.1.3. Upon settlement of a claim for any other property loss or damage under any required insurance where government did not have an insurable interest, the private party must pass through to government the benefit of the insurance where government has suffered a loss for which government has been indemnified by the private party under the project agreement. 26.2 General insurance obligations The private party will ensure that it:267 (a) does not do or permit (insofar as it is reasonably within its power) anything to occur which prejudices any insurance; (b) reinstates any policy if it lapses; (c) does not cancel, vary or allow an insurance policy to lapse without the prior written consent of the other party; (d) gives full, true and particular information to the insurer of all matters which might otherwise prejudice any policy or the payment of benefits under the insurance; (e) immediately informs government when it receives or gives a notice under, or in connection with, any insurance policy, including any notice of cancellation of claim; and (f) does everything reasonably required by government or any other person in whose name the policy is effected to enable government or that other person to claim, collect or recover monies due under any insurance policy. 26.3 Changes in insurance costs 26.3.1 Sharing mechanism • Government will not share in cost increases to the design and construction insurances other than in exceptional circumstances such as where there is a very long construction period and insurances for the whole period cannot be obtained up front. • Although operational insurances will not be reviewed or market tested like other ‘soft’ services,268 government will share cost increases of certain categories of required operational insurances.269 The cost of such insurances will be reviewed annually270 on a forward-looking basis to determine whether and by how much the actual costs of insurance for the following year will vary from the projected costs of insurance 267 This is not intended as an exclusive list but highlights the key obligations. 268 Accordingly, the cost of required insurances is (subject to inflation) fixed for the term of the project at financial close. It is not 're-set' as a result of any review. 269 Government will not share the cost of insurances which cover risks the private party is required to bear (such as loss of profit, professional indemnity and non-vitiation insurances). 270 Or such other period considered appropriate on a project-specific basis. April 2008 114 Partnerships Victoria Updated Standard Commercial Principles applicable to the forthcoming operating year. increases solely due to general inflation. Government will not share in cost • The private party must obtain and submit to government at least three separate quotations from reputable insurance brokers with respect to the annual premium costs of obtaining the shared operating insurances for the first year of the operating phase, and must notify government of the private party's preferred quotation and insurer. If government and the private party fail to reach agreement on the preferred approach to and cost of obtaining the shared operating insurances, the matter may be referred to an independent expert for determination. • At least three months prior to each anniversary of the operations commencement date, the private party must repeat the above procedures in respect of shared operating insurances to be taken out for the ensuing year. If government and the private party fail to reach agreement on the most suitable insurer, premiums and other terms and conditions of the shared operating insurances, the matter may be referred to an independent expert for determination. • Eligible insurance cost increases will be shared (on a forward-looking basis) as follows: (a) the private party will bear the insurance cost increases for the relevant period up to a specified threshold (first threshold);271 (b) government will share272 the insurance cost increases for the relevant period above the first threshold until a specified higher threshold (second threshold) is reached; and (c) government will bear a substantial percentage of the insurance cost increases for the relevant period above the second threshold.273 • Where the insurance costs increase above the second threshold, government will have the option of either sharing the cost on the above basis or declaring that the relevant insurance falls within the uninsurability provisions.274 • The private party will, in all circumstances, be liable for the original fixed cost of insurance. 271 The thresholds and the percentage of cost increases to be borne by government at each threshold level will be determined on a project-specific basis bearing in mind the need to ensure that the private party remains incentivised to prudently manage the cost of its insurance premium. In particular, government will consider what percentage of the overall operating costs is represented by insurance costs and the risk and magnitude of likely insurance cost changes (in light of the market conditions at the time). Government may wish to invite variant bids based on the size of thresholds and frequency of review periods. 272 For example, on a 50;50 basis. However, the exact basis for sharing cost increases will be determined on a project-specific basis. For example, the project may contain a mechanism outlining a base premium (indexed to Consumer Price Index) and a new premium and setting out a basis for sharing insurance cost increases between government and the private party linked to these two criteria. 273 The relevant percentage will be greater than the percentage borne by government for cost increases falling between the first and second thresholds. Government will bear a substantial part of any cost increases above the second threshold, and may consider bearing 100 per cent of those increases if the private party can demonstrate this would deliver a value-for-money outcome. The private party is generally required to share some component of such cost increases. Of course such sharing arrangements will be subject to the uninsurability regime and the protections that regime offers to the private party. 274 See paragraph 26.3.3. April 2008 115 Partnerships Victoria Updated Standard Commercial Principles • Where government is to share an insurance cost increase in the above manner, the service fee payable in the payment period following the review will be increased to reflect government's share of the insurance cost. • Similar sharing arrangements will apply if the insurance costs fall over the relevant review period, with any decrease from the original fixed cost being a debt due and payable to government by the private party. 26.3.2 Eligible costs increases • The ‘cost’ of insurance refers to the premium only. It does not, for example, include increases in broker's fees and commissions or the costs of any modifications required by an insurer. • In order to obtain the benefit of this costs sharing mechanism, the private party must: (a) have conformed and continue to conform with specified minimum risk management requirements in respect of the risks covered by those operational insurances included in the costs sharing mechanism;275 and (b) deliver to the government at least two copies of an Insurance Cost Report containing an account of the reasons for the change in insurance costs. This Report should be prepared with the assistance of the private party's broker.276 26.3.3 Portfolio cost savings • A 'Portfolio Cost Saving' is any insurance cost saving attributable to either the private party placing any of the required insurance within a policy or policies covering risks in other projects or matters outside the scope of the project in questions, or to a change in how that insurance is placed as compared with that which had been anticipated at financial close. • Any portfolio cost saving is to be shared with the government, under the costs sharing mechanism set out above. 26.3.4 Dispute resolution If the parties, after reasonable endeavours in good faith, cannot reach agreement about the contents of the Insurance Cost Report within 30 days of its submission to the government by the private party, the matter is to be resolved through the dispute resolution process set out in paragraph 32.3. 275 These risk management requirements will be developed in consultation with risk management experts, including the VMIA. 276 This would include any variations arising from the claims history of the private party or a subcontractor; the effect of placing some or all of the required insurances within a policy or policies covering risks which are outside the scope of the project; the effect of a change in how some of all of the required insurance is placed as compared to that which had been anticipated at financial close; the opinion of the private party's broker as to the reasons why the premium has changed, including specification of the impact of each of the factors and quantifying the amount attributable to each factor; evidence satisfactory to the government (acting reasonably) that the relevant costs change is, with the exception of any portfolio cost saving, due to circumstances generally prevailing in the Australian insurance market. When notifying government of a change to the cost of any shared operating insurances for the forthcoming operating year, the private party must exclude and separately identify any increases attributable to the acts and omissions or insurance claims history as outlined above. April 2008 116 Partnerships Victoria 26.3.5 Updated Standard Commercial Principles Mitigation • The increase must be due to circumstances generally prevailing in the Australian and overseas insurance market for the relevant class of insurance. Government will not be liable for insurance cost increases caused by the private party, its subcontractors or any member of the consortium (including the claims history of each such party). • The private party must use reasonable endeavours to minimise any increase and maximise any reduction whilst maintaining the minimum level of insurance agreed between the parties. 26.3.6 Effect of an appropriate insurance index The cost sharing arrangements set out in this section will be reviewed by government when an independently compiled index of Australian market movements in the annual premium cost of obtaining certain categories of required operational insurance is developed. 26.4 Uninsurability 26.4.1 Meaning of uninsurable risk An 'uninsurable risk' occurs where: (a) insurance is not available in the recognised international insurance market with reputable insurers of good standing (including the minimum credit rating specified in the project agreement) in respect of that risk at the time that the insurance is sought to be obtained; or (b) the insurance premium payable for insuring that risk is at such a level that the risk is not generally being insured against in the international insurance market with reputable insurers of good standing by prudent, competent and experienced providers of services similar to the services at the time at which the insurance was sought to be obtained.277 26.4.2 • Treatment of uninsurable risk If either party considers that a risk which is covered by the required insurances278 is or will be uninsurable then that party must immediately notify the other in writing, giving particulars. If the parties agree, or it is determined through the dispute resolution procedure, that the relevant risk is uninsurable, and the fact that the risk is uninsurable is not attributable to the actions of the private party or a subcontractor, the private party is not required to procure insurance against that risk for so long as that risk is and remains uninsurable. 277 The effect of this provision should not be to give protection against changes in terms of insurance or levels of deductibles. It is intended to offer protection if the cost of insurance is such that the market is not generally insuring against that risk (on any terms). 278 Uninsurability protection does not extend to insurances which cover risks which the private party is required to bear (such as loss of profit, professional indemnity and non-vitiation insurances). However, for value-for-money reasons, the uninsurability provisions will extend to cover business interruption insurance. April 2008 117 Partnerships Victoria Updated Standard Commercial Principles • The parties will then meet and seek to agree any changes to the private party's rights and obligations arising out of the unavailability of the relevant required insurance including the amount of any change to the service fee.279 • If the uninsurable risk materialises, government may: (a) request a modification to the facility which removes the affected part of the site and the uninsurable risk from the project;280 (b) pay to the private party an amount equivalent to the insurance proceeds that would have been payable if the relevant insurance was available; or (c) terminate the project agreement if the facility is wholly or substantially damaged or destroyed, in which case compensation will be payable on a force majeure termination basis. 281 • Where a risk is uninsurable, the private party must approach the insurance market on a regular basis to establish whether that risk remains uninsurable and advise government accordingly. If the insurance becomes available again, the private party must effect that insurance. 279 The change in the service fee should reflect the fact that the private party is not paying an anticipated insurance premium. 280 Modifications may only be requested by government in this context on the condition that such modifications will not materially adversely affect the private party. 281 See paragraph 29.2 in section 29 (Termination payments). April 2008 118 Partnerships Victoria Updated Standard Commercial Principles 27. Default Principle Depending on its severity a default is categorised as: (a) an 'Event of Default'; or (b) a 'Default Termination Event'. The type of event will determine the remedies available to government and the opportunity given to the private party to cure the default before government can exercise its remedies. 27.1 Events of Default • An Event of Default gives rise to various government remedies (such as termination and step-in). However, it does not of itself give rise to an automatic right of termination. • The following events will each constitute an Event of Default:282 (a) a serious Service Failure;283 (b) failure to achieve either Technical Completion or Commercial Acceptance by the due dates; (c) the independent expert determines (following a reasonable period after financial close)284 there is no reasonable prospect the private party will achieve Technical Completion or Commercial Acceptance by the due dates respectively;285 282 The listed Events of Default are not intended to be exhaustive and depending on the nature of the project they may need to be varied (as may the dichotomy of the Event of Default and Termination Event). Additional Events of Default may need to be added such as breaches of law, vitiation of project documents, any applicable limits on the private party's liability under the project documents being reached or the private party failing to provide or make available any licence, sub-lease or other tenure required by government. Breaches caused by an Intervening Event, see section 17 (Intervening Events during the operational phase) or Force Majeure Event, including a compensable Change in Law, see section 24 (Force majeure) do not constitute an Event of Default to the extent that relief is given from the relevant obligations. 283 A serious Service Failure is evidenced by the service fee being abated by a specified percentage within a specified period or performance points accruing beyond a specified level within a specified period. See paragraph 14.3.2 in section 14 (Service requirements and specifications) for what constitutes a Service Failure. 284 What constitutes a reasonable period is to be agreed on a project-specific basis. There may also be more than one look-forward period. 285 See paragraph 11.5.6 in section 11 (Construction and commissioning). April 2008 119 Partnerships Victoria Updated Standard Commercial Principles (d) the works not being commenced within such period after financial close286 as is likely to have a material adverse effect on the ability of the private party to achieve Commercial Acceptance by the Date for Commercial Acceptance; (e) fraudulent,287 misleading or deceptive conduct by the private party or its subcontractor, in the performance of its obligations or otherwise in relation to the project documents (including, any reporting in the form of financial and payment statements and invoices or other books or records of the private party and any reporting obligations of the private party in respect of the master works program and sub-programs);288 (f) a false or misleading representation or warranty made by the private party in the project agreement or other specified contracts which has a material adverse effect on government or the private party's ability to perform its obligations; (g) the private party's right to obtain finance or continue to have available funds under the finance agreements being materially restricted or cancelled; (h) a breach of the subcontractor provisions;289; (i) a failure by the private party to cure an unauthorised Change in Control of a key material subcontractor within a reasonable time;290 (j) a breach by the private party of its assignment obligations;291 (k) the private party failing to take out and maintain required insurances (subject to the Unavailability provisions);292 (l) failure by the private party to comply with its obligations to reinstate damage or destruction;293 and (m) any other breach by the private party of the project agreement which has not been remedied within a reasonable period or a breach of other specified contracts with government or third parties which has a material adverse effect on government or users of the facility or the private party's ability to perform its obligations.294 286 This date may change depending on the project. For example, if access is not freely available it would be appropriate to require that the works be commenced from the date that access is granted under an access regime. 287 The State will retain all its common law rights in relation to any fraudulent activity. 288 This Event of Default will also capture where it is discovered that the private party acted fraudulently or breached the law in the awarding of the contract (e.g. collusive behaviour). 289 See section 20 (Subcontractors). It would also be an Event of Default if the employee provisions of the project agreement were breached. 290 See paragraph 20.5 in section 20 (Subcontractors). 291 See paragraph 35.3 in section 35 (Restrictions on private party). 292 See paragraph 26.3.3 in section 26 (Insurance). 293 See section 25 (Reinstatement and repair) and paragraph 24.3 in section 24 (Force majeure). 294 If parent guarantees are taken as security, similar provisions to that contained in sub-paragraphs (e) and (m) will need to be inserted in respect of the guarantee, (i.e. false or misleading statements under, or breaches of, the guarantee). April 2008 120 Partnerships Victoria • Updated Standard Commercial Principles Although government will generally treat a failure to reach Technical Completion by the Date for Technical Completion as a separate event of default, it may consider waiving this requirement295 in circumstances where achievement of Commercial Acceptance is conditional on the private party having provided government with sufficient time to transition into and test the functionality of the facility. This period will be specified by government on a project-specific basis. 27.2 Cure periods and remedies for Events of Default 27.2.1 Cure periods • Government may give a default notice to the private party specifying that an Event of Default has occurred. • Where the Event of Default is capable of cure: (a) the private party must, within a specified period, provide a draft cure plan proposing a program of rectification (including the proposed cure period);296 (b) the private party and government must consult with a view to agreeing on the cure plan, but if agreement cannot be reached within a specified period, the private party must amend the draft cure plan in accordance with the requirements of government (acting reasonably).297 This then becomes the approved cure plan; and (c) the private party must comply with the approved cure plan or otherwise diligently pursue a cure of the Event of Default.298 • Where the Event of Default is not capable of cure it will not automatically give government a right to terminate the project agreement. In this situation the steps outlined below must be followed within reasonable timeframes agreed on a projectspecific basis: (a) the private party must prepare a prevention plan for submission to government for endorsement which will overcome the consequences of, or compensate the State for, the relevant Event of Default within an appropriate timeframe; (b) government must consider the prevention plan in compliance with the review procedures; 295 Thereby limiting the events of default to a failure to meet Commercial Acceptance by the Date for Commercial Acceptance. 296 The cure period applicable to a serious Service Failure will be in addition to the original response and rectification times for that Service Failure. 297 If the private party is still not satisfied with the approved cure plan, it may refer the matter for resolution pursuant to the dispute resolution procedures set out in the project agreement - see section 32 (Dispute resolution). In the event that the matter is referred to dispute resolution, the private party will need to comply with the cure plan (as amended to reflect government's requirements) until the dispute is resolved. 298 Although the financiers will have separate step-in rights under the funder's direct agreement, they will not have separate cure periods before an Event of Default can be called. Appropriate cure periods will be agreed as part of the cure plan. In addition, the cure periods may be extended in accordance with paragraph 27.3. April 2008 121 Partnerships Victoria Updated Standard Commercial Principles (c) if the prevention plan is accepted by government (such acceptance not to be unreasonably withheld), the private party must comply with that prevention plan; and (d) if the prevention plan is not accepted by government, government may require the private party to comply with other requirements it considers (acting reasonably) will overcome the consequences of, or compensate the State for, the relevant Event of Default. If government does not exercise the right or, having exercised it, the private party fails to comply with those requirements, this will give rise to an immediate government termination right. • Failure by the private party to comply with these requirements will allow government to treat the Event of Default as a Default Termination Event as set out in paragraph 28.1.2. 27.2.2 Remedies for Event of Default • If a default notice has been given, government may exercise its Step-in Rights except where the private party is complying with an approved cure plan and diligently pursuing a remedy.299 • If a default notice has been given and the Event of Default is either not capable of cure or, if it is capable of cure, the private party: (a) fails to provide a draft cure plan; (b) fails to comply with the approved cure plan or to otherwise diligently pursue cure of the Event of Default in accordance with the approved cure plan; or (c) fails to cure the Event of Default within the relevant cure period, government may: • (d) require the private party, at its own cost, to replace any subcontractor performing the obligations to which the Event of Default relates; or (e) exercise any of its security rights. In addition to the above remedies, if the private party fails to: (a) provide a draft cure plan; (b) otherwise diligently pursue cure of the Event of Default in accordance with the approved cure plan; or (c) comply with the approved cure plan, government may give notice specifying such failure and requiring the failure to be rectified within a specified period. • 299 Failure to comply with the notice will give government the right to terminate.300 See section 30 (Step-in). April 2008 122 Partnerships Victoria 27.3 Updated Standard Commercial Principles Extension of cure period Prior to the expiry of a cure period, the private party may request an extension301 by providing government with a written request together with the private party's reasons (in appropriate detail) as to why an extension is required and a detailed plan of the actions to be taken by the private party to ensure the default is cured during any extended period. Provided the private party: (a) has provided government with sufficient reasons for the extension (and has provided any further information reasonably requested by government); (b) can satisfy government (acting reasonably) that it will cure the default within the extended period; and (c) can satisfy government that it has complied and is continuing to comply with the approved cure plan (as may be amended with government's agreement) and is diligently pursuing cure of the Event of Default, government must act reasonably in considering the request. The private party may only request one extension. 27.4 General remedies The exercise by government of any of its remedies set out in this section does not prevent government from: (a) exercising any other power under the project agreement; or (b) suing the private party, or exercising any other legal or equitable rights or remedies, in relation to a default or any other action or conduct of the private party. 300 See paragraph 28.1.2(c) in section 28 (Termination). The suspension of termination rights will only be available for so long as the approved cure plan is being diligently pursued by the private party. 301 The extension period may not exceed a specified percentage (for example 50 per cent) of the original cure period. April 2008 123 Partnerships Victoria Updated Standard Commercial Principles 28. Termination Principle Government may terminate the project agreement on the occurrence of a Default Termination Event or Force Majeure Termination Event or may voluntarily terminate the project agreement subject to payment of a termination payment. 28.1 Default Termination Event 28.1.1 Termination without cure If a Default Termination Event occurs, government has the right to terminate the project agreement without any cure period being given to the private party. 28.1.2 What constitutes a Default Termination Event? The following events will each constitute a Default Termination Event:302 (a) the private party wholly or substantially abandoning the works, the facility or the provision of the services; (b) failure by the private party to cure an Event of Default (which is capable of cure) within the relevant cure period; (c) failure by the private party to: (i) prepare a prevention plan which is subsequently approved by government; (ii) comply with the government approved prevention plan; or (ii) comply with government's reasonable requirements as notified to the private party in the absence of an approved prevention plan, in relation to an Event of Default not capable of cure; (d) failure by the private party to comply with a notice given by government where the private party has failed in a material or substantial way to comply with an approved cure plan, diligently pursue cure of the default or provide a draft cure plan;303 302 The listed Default Termination Events are not intended to be exhaustive and depending on the nature of the project they may need to be amended or further Default Termination Events included. 303 See paragraph 27.2.2 in section 27 (Default). Breaches caused by an Intervening Event (see section 17 (Intervening Events during the operational phase) or Force Majeure Event, see section 24 (Force majeure), including a compensable Change in Law, do not constitute an Event of Default to the extent that relief is given from the relevant obligations. April 2008 124 Partnerships Victoria (e) Updated Standard Commercial Principles the occurrence of an 'Insolvency Event'304 in relation to: (i) the private party; or (ii) any other member of the private party group,305any guarantor or relevant key subcontractor, if the private party fails to replace that other member of the private party group, guarantor or key subcontractor within 60 business days306 of the occurrence of that Insolvency Event; (f) a breach of the relevant Change in Control provisions307 of the project agreement; (g) an independent expert making a determination that there is no reasonable prospect that the private party will achieve Commercial Acceptance by the Sunset Date;308 (h) Commercial Acceptance not having occurred by the Sunset Date; (i) a specified cap or a specified percentage of the cap being reached in respect of any performance bonds or parent company guarantees provided to government as required under the project agreement or any such bond or guarantee ceasing to be valid without, in each case, rectification or replacement within a specified period; (j) government directing the private party not to reinstate or repair damage309 where the relevant damage was caused by a private party default; (k) performance points accumulated over a fixed period (i.e. due to a series of Service Failures) exceeding a specified level;310 (l) the private party suffering abatements over a specified number of consecutive months, which in value equate to an amount which is a specified percentage of the total services fee; and 304 An Insolvency Event would include voluntary and involuntary winding up (except for the purposes of a reconstruction, merger or consolidation), administration, insolvency (including inability to pay debts as and when they fall due and failure to comply with a statutory demand), the appointment of a receiver, receiver and manager, controller or provisional liquidator, or entering into arrangements with creditors or bankruptcy. 305 See footnote 184 in section 21(Change in Control) for what constitutes the private party group. 306 Or such other reasonable period to be agreed by the parties at the time. 307 See section 21 (Change in Control). 308 See paragraph 12.2.7 in section 12 (Relief for construction delays) and paragraph 11.5.6 in section 11 (Construction and commissioning). 309 See paragraph 25.2 in section 25 (Reinstatement and repair). 310 Note that this specified level will be significantly higher than the level which triggers an Event of Default. See paragraph 27.1(a) in section 27 (Default). April 2008 125 Partnerships Victoria (m) Updated Standard Commercial Principles the occurrence of more than a specified number of private party breaches311 (whether or not such breaches are remedied) in a specified period312 if: (i) in the opinion of government, there has been a persistent or repeated failure by the private party to comply with its obligations; and (ii) the breach continues or recurs more than a specified number of times within a specified period after a final warning notice is given by government.313 28.2 Force Majeure Termination Events 28.2.1 Force Majeure Event Either party may terminate the project agreement if a Force Majeure Event314 subsists for a specified continuous period315 or if government directs the private party not to reinstate or repair damage316 and the relevant damage was caused by a Force Majeure Event. 28.2.2 Uninsurability provisions Government may terminate the project agreement pursuant to the uninsurability provisions.317 28.3 Voluntary termination In addition to the above termination events, government may at any time, in its sole discretion and without giving any reasons (but subject to a termination payment as set out in section 29 (Termination payments), terminate the project agreement by giving a specified period of notice. Where government has directed the private party not to reinstate or repair damage,318 and the relevant damage was not caused by a Force Majeure Event or private party default, termination of the project agreement by government will be treated as a voluntary termination. 311 This is intended to capture both repeated breaches of the same type or class and persistent breaches not of the same type or class. 312 These breaches would exclude any breach for which government otherwise has the right to abate the service fee. 313 The project agreement will set out a procedure for warning notices to be given before a final warning notice (leading to termination) is given. 314 See paragraph 24.1 in section 24 (Force Majeure) for the definition of Force Majeure Event. 315 See paragraph 24.5.1 in section 24 (Force majeure). 316 See paragraph 25.2 in section 25 (Reinstatement and repair). 317 See paragraph 26.4.2 in section 26 (Insurance). 318 See paragraph 25.2 in section 25 (Reinstatement or repair). April 2008 126 Partnerships Victoria 28.4 Updated Standard Commercial Principles Procedure • Following a Default Termination Event, Force Majeure Termination Event or otherwise in accordance with paragraph 28.3, government may elect to terminate the project agreement by giving notice to the private party. • Termination will take effect within a specified time after the date of the notice, or such earlier time as specified in the notice. 28.5 Consequences • Upon termination, the private party will be entitled to compensation in accordance with the principles set out in section 29 (Termination payments). • The rights and obligations of the parties to the project agreement319 will cease except for: (a) any accrued rights and obligations; and (b) any rights or obligations which are expressed to continue after termination. 319 Other agreements may be relevant to include here, such as any lease between the private party and government. April 2008 127 Partnerships Victoria Updated Standard Commercial Principles 29. Termination payments Principle On early termination of the project agreement, government must pay a termination payment to the private party, calculated in accordance with the principles set out in this section.320 29.1 Default Termination Payment 29.1.1 Payment amount On termination of the project agreement resulting from a Default Termination Event,321 government will pay the private party an amount equal to: (a) the fair-market-value of the project as determined through a re-tendering process under paragraph 29.1.3; or (b) if there is no liquid market or if government otherwise elects to, the estimated fair-market-value of the project as between a willing buyer and a willing seller (as calculated by the independent valuer,322 less the deductions in paragraph 29.1.2 (Default Termination Compensation Amount). 29.1.2 Deductions The following deductions will be made from the amount determined in paragraph 29.1.1: (a) any costs incurred by government in determining the fair-market-value, including engaging the independent valuer (as applicable); (b) any amounts owing by the private party to government as at the termination date (including all amounts government can set off under the project agreement); (c) credit balances standing to any of the private party's bank accounts and insurance proceeds or other amounts owing to the private party, in each case only to the extent not taken into account in calculating the fair-market-value; (d) government's reasonable actual or forecast internal and external re-tendering costs (where applicable); and 320 This section assumes that the private party has not taken residual risk on the project assets, and that those assets are transferred to government upon termination. In other circumstances, different termination payments may be appropriate. 321 See paragraph 28.1.1 in section 28 (Termination). 322 See paragraph 29.1.4 (Determination of fair-market-value) April 2008 128 Partnerships Victoria (e) Updated Standard Commercial Principles to the extent not covered by paragraph (b) above, any additional costs [reasonably] incurred by government as a result of the default.323 If the amount is negative, it will be deemed to be zero. 29.1.3 Determination of fair-market-value by tendering324 • If there is a liquid market, government will be entitled to sell (i.e. re-tender) the unexpired term of the project agreement (on its terms as at the termination date) and pay the proceeds of the sale to the private party provided the senior lenders have not and are not continuing to exercise their step-in rights. If, despite a liquid market, the government receives no compliant bids, the proceeds received from the tender will be deemed to be zero. • A liquid market will exist if there are a sufficient number of contractors in the prevailing market (or markets for similar contracts to Partnerships Victoria contracts) to ensure that the price that is likely to be achieved through a tender to be a reliable indicator of fair value.325 Any dispute as to the existence of a liquid market for the project will be referred for resolution to the dispute resolution procedure. • Government will not be entitled to re-tender the unexpired terms of the project agreement if the senior lenders have exercised their right to step-in under their direct deed with government and have not procured the transfer of the private party's rights and liabilities under the project agreement to a suitable substitute private party (provided they have used all reasonable efforts to do so).326 29.1.4 (a) Determination of fair-market-value by an independent valuer In determining the estimated fair-market-value, the independent valuer must determine the net present value of the projected cash flows for the unexpired contract term (ignoring any abatements and assuming no breach had arisen) calculated on a nominal, pre-tax basis, taking into account agreed rates of indexation327 and assuming: 323 This would generally exclude indirect and consequential losses for which government would otherwise not be liable. 324 The re-tendering mechanism and associated tests for a liquid market will be developed and refined by government on a project-by-project basis. 325 The minimum number of required market participants (in addition to participants controlled by the senior lenders) will be determined on a project-specific basis but will be at least two (although if no, or only one compliant bid is received, there may still have been a liquid market when the test for re-tendering was run). 326 The senior lenders must take the risk of the private party's performance (this risk is mitigated by their right to step-in and cure or to transfer the project). Where government elects to terminate the project agreement for poor performance, senior lenders are incentivised to exercise their step-in rights and use their reasonable efforts to transfer the project (which may include accepting offers which do not fully pay out senior debt). If the senior lenders have used their reasonable efforts to transfer the project and have been unable to do so (for reasons other than not achieving full pay-out of senior debt), then government considers that a liquid market is unlikely to exist. 327 The inflation rate to be used in this calculation will be the forecast general inflation rates from the predictions in the State budget papers. See Partnerships Victoria Advisory Note – Determining the General Inflation Rate for Use in Partnerships Victoria projects (August 2005). If the parties cannot agree any other rates of indexation which are applicable, the relevant indexation rates must be referred to dispute resolution. April 2008 129 Partnerships Victoria (b) Updated Standard Commercial Principles (i) a reasonable time to achieve Commercial Acceptance;328 (ii) the subsisting grounds for termination of the project agreement have not arisen (but the costs of remedying any default by the private party giving rise to termination, including any rectification costs, must be taken into account); and (iii) any breach of the project agreement arising prior to the successful tender will not entitle government to terminate the project agreement.329 The projected cash flows must take into account the amount and timing of any rectification and reinstatement costs required to be incurred to enable the delivery of the contracted services to specification for the unexpired contract term, as well as all other forecast costs (including every day operating costs and life cycle maintenance costs), indexed at the agreed or determined rate. These will include any costs forecast to be incurred to achieve Commercial Acceptance and all costs incurred or to be incurred by government where: (i) it directly completes the works and/or delivers the relevant services; or (ii) procures the completion of the works or delivery of the services by a third party. (c) In addition, the costs identified above will be adjusted for a reasonable contingency over the base amount. The resultant projected cash flows are to be the valuer's estimate of the operating cash flow stream which, had a liquid market existed and the project been tendered, a hypothetical bidder would have valued to determine the amount to bid for the project and must be discounted to its net present value at the termination date.330 (d) The discount rate to be used by the independent valuer to establish the net present value of the projected cash flows will be derived using the following formula: R = ((1 + real base case pre-tax project IRR331 + CB B – CB A) * (1 + i)) - 1, where: 328 R = the discount rate; CB B = the real yield to maturity on a benchmark Commonwealth bond traded in the Australian bond markets with a modified duration closest to that of the weighted average life of any outstanding senior debt as shown in the base case financial model as at the date of termination; CB A = the real yield to maturity on a benchmark Commonwealth bond traded in the Australian bond markets with a modified duration closest to that of the weighted average life of any outstanding senior debt as shown in the base case financial model as at the date of financial close; and Where the project agreement is terminated prior to Commercial Acceptance 329 In making this determination some amendments to the project agreement's terms and conditions may need to be assumed to allow for the incoming service provider to deliver the project (e.g. all things being equal, any accrued warning notices and frequent and persistent breaches will need to be cancelled or where termination occurs during the construction phase, the date for completion and the sunset date may need to be extended). 330 Using the discount rate determined in paragraph 29.1.4(d) 331 As at project commencement. April 2008 130 Partnerships Victoria i Updated Standard Commercial Principles = the assumed inflation rate used in paragraph (a)332 to index the cash flows. For the purposes of the above formula, government recognises that there may not be a product with an appropriate tenor. If this occurs, an appropriate alternative will be determined at the time in consultation with the private party. 29.1.5 • Post termination service fee or interest Where government pays the private party an amount determined under paragraph 29.1.3 (Determination of fair-market-value by tendering), then from the termination date until the termination payment is made, government will pay the private party a post termination service fee calculated as the full service fees less: (a) the greater of all cost components related to the provision of the hard and soft services and the costs to government of alternative provision of the services; (b) all cost components related to the provisions of insurance; and (c) rectification costs incurred by government.333 29.1.6 Method of payment and interest • Government will be entitled to pay to the private party the Default Termination Compensation Amount by way of a lump sum payment or in a specified number of instalments,334 no later than a specified period after the date on which such amount is determined.335 • Interest will be payable on the Default Termination Compensation Amount where payment is delayed, on a project-specific basis336. 332 i.e. the forecast general inflation rate from the predictions in the State budget papers. 333 The term of the new project agreement will typically be the same as the unexpired term of the terminated project agreement (i.e. the expiry date in the new project agreement will be later than that in the old project agreement by the amount of time the re-tendering procedure has taken). In such circumstances, any post termination service amounts should be deducted from the ultimate termination payment made. It may be, however, that a service requirement can only be delivered for the period that expires on the original expiry date. In such circumstances, it would not be possible for the term of the re-tendered project agreement to be for a period equal to the unexpired term of the original project agreement and the parties will have to fix a date for the new project agreement to come into effect, so that tenderers can bid for a fixed term. In such circumstances the post termination service amounts should not be deducted from the ultimate termination payment made. 334 To the extent that government pays by instalments, the instalments will (to the extent possible) reflect debt commitments. Alternatively, government will compensate the financiers for their costs and expenses incurred as a consequence of government exercising such a right. 335 This is subject to any disputed element of the payment being referred to dispute resolution, in which case payment of the disputed component will be deferred until the matter has been determined. 336 Whether interest is payable and the applicable interest rate will depend on the type of financing and the reasons for the delay in payment. April 2008 131 Partnerships Victoria Updated Standard Commercial Principles 29.2 Force Majeure Termination Payment 29.2.1 Payment amount • 337 On termination of the project agreement for each type of Force Majeure Termination Event,338 government must, subject to paragraph 29.2.3 and paragraph 29.2.5, pay to the private party an amount equal to: (a) the lower of senior debt339 owing to financiers at the termination date and the amount forecast in the base case financial model (as varied from time to time in accordance with section 18.6) to be owing to financiers as at the termination date;340 and (b) any break costs payable by the private party to the financiers under the finance documents as a direct result of early termination341 (not included in paragraph (i) above), less the deductions in paragraph 29.2.2 below (Force Majeure Compensation Amount)342. • Accordingly, in a project financed by bonds, government will only pay the par value of the bonds outstanding (together with any accrued and unpaid interest) less any deductions. • The debt component of a Force Majeure Compensation Amount will include amounts payable and must be reduced by any gains receivable, as a direct result of early termination of hedging arrangements. • Where the Force Majeure Compensation Amount could potentially include amounts to be refinanced by an anticipated contribution from equity at the end of the construction phase, government may seek to cap the compensation amount to the level of what would have been the long term senior debt. 337 The termination payments for force majeure and voluntary termination are based on the assumption that the debt finance component of the project is bank debt or bond funded. To the extent that the project is fully or partly financed by a hybrid issue or another form of finance, appropriate amendments to the senior debt element of any payment will need to be made. 338 See paragraph 28.2 in section 28 (Termination). The term Force Majeure Termination Events captures termination resulting from a Force Majeure Event and termination pursuant to the uninsurability provision. 339 Mezzanine and other subordinated debt will be afforded the same protection as senior debt for purposes of the Force Majeure Termination Payment and the voluntary termination payment but only to the extent that such debt has the essential characteristics of senior debt (other than to the extent that it is subordinated to pure senior debt). This will be determined on a project-specific basis before the execution of the project agreement depending on the debt structure of the private party. However, government will not compensate subordinated debt which is effectively equity. 340 In either case, ensuring that any senior debt payments of principal made by government during any period of suspension (arising from a force majeure event) are appropriately taken into account. 341 This will be subject to the private party's obligation to mitigate any such break costs. The break costs are also intended to capture any break costs incurred as a result of early termination of hedging arrangements. Any break gains must be deducted. 342 The Force Majeure Compensation Amount must take into account any payments made to keep senior debt whole under paragraph 24.4.1 in section 24 (Force majeure). April 2008 132 Partnerships Victoria 29.2.2 Updated Standard Commercial Principles Deductions The following deductions will be made from the amount set out in paragraph 29.2.1: (a) all credit balances on any bank accounts held by or on behalf of the private party on the termination date; (b) any amounts owing by the private party to government as at the termination date (including any amounts government is entitled to set-off); (c) any insurance proceeds paid or payable to the private party (or which would have been payable to the private party if it had complied with its insurance obligations) at any time between the termination date and the date of payment other than payments that are to be applied to repairing or rebuilding the facility or to third party liabilities;343 and (d) all sums due and payable to the private party from the financiers as a result of any prepayment of senior debt344 and any third party amounts paid to the private party at any time during the period between the termination date and the date of payment.. 29.2.3 The higher of the Default Termination Compensation Amount and Force Majeure Compensation Amount Where the Force Majeure Compensation Amount is less than the Default Termination Compensation Amount which would have been payable had termination (and the relevant loss or damage to the project) occurred as a result of a contractor default rather than a force majeure event, then government will pay the Default Termination Compensation Amount. 29.2.4 Method of payment and interest Government will be entitled to pay the Force Majeure Compensation Payment amount in a specified number of instalments.345 Interest will be payable on the Force Majeure Compensation Amount where payment is delayed, on a project-specific basis346. 343 Government would also be seeking to deduct insurance proceeds which would have been received before the termination date and applied against a component of the Force Majeure Compensation Amount, if the private party had complied with the project documents. 345 To the extent that government pays by instalments, the instalments will (to the extent possible) reflect debt commitments. Alternatively, government will compensate the financiers for their costs and expenses incurred as a consequence of government exercising such a right. 346 Whether interest is payable and the applicable interest rate will depend on the type of financing and the reasons for the delay in payment. April 2008 133 Partnerships Victoria 29.2.7 Updated Standard Commercial Principles Subsisting private party default termination event Where a private party Default Termination Event is subsisting at the time that notice of termination is given for a Force Majeure Termination Event, the termination payment is to be calculated on the same basis as for termination following a Default Termination Event.347 29.3 Payment for voluntary termination by government 29.3.1 Voluntary Termination Payment Amount On termination of the project agreement resulting from a government voluntary termination,348 government must (subject to section 29.3.3) pay to the private party an amount equal to the aggregate of: (a) where the senior debt amount has been financed by bank debt, the lower of senior debt owing to financiers at the termination date and the amount forecast in the base case financial model (as varied from time-to-time in accordance with section 18.6) to be owing to financiers as at the termination date; (b) where the senior debt amount has been financed by capital market instruments (bonds), the lower of the present value of the: (i) future cash flows under the outstanding bonds; and (ii) the future cash flows under the bonds forecast to be outstanding at the date of termination in the base case financial model (adjusted for any refinancing pursuant to which government is paid a refinancing gain),349 calculated at the termination date having regard to the yield at which the underlying capital market instruments are priced in the market at the termination date, using standard market conventions for each relevant instrument,350 on the basis that the project agreement and the other project documents as existing immediately prior to the termination date continue to operate to the expiry date; (c) an amount which gives an equity return351 (from the date of termination to the original expiry date of the project agreement) of the greater of: 347 See paragraph 29.1.1. 348 See paragraph 28.3 of section 28 (Termination). 349 In both paragraph (i) and (ii), the future cash flows must exclude any 'bond payout amount' or the like payable under the bond terms on default or early repayment of the bonds. 350 The determined yields should each comprise a market reference (base) interest rate plus the lower of the issue margin as set out in the base case financial model and the trading margin derived from the average offer rate as quoted by a panel of leading dealers in the Australian bond market over five trading days preceding the date the government gives notice of the voluntary termination. The precise calculation of any bond payout will depend on the terms of the specific funding proposal. 351 Being on both any share capital subscribed at financial close and any shareholder subordinated debt not taken into account as 'debt' above. April 2008 134 Partnerships Victoria Updated Standard Commercial Principles (i) the blended equity internal rate of return in the base case financial model (as varied from time-to-time in accordance with section 18.6); and (ii) the market rate of equity return, having regard to market rates of return, for the project cash flows taking into account the independent valuer's reasonable assessment of forecast cash flows to equity from the date of termination to expiry of the project agreement, in each case: (A) assuming the services will be delivered in accordance with the performance standards set out in the project agreements; (B) assuming the service fee provisions will continue to apply as set out in the project agreement; (C) taking into account deductions for forecast costs (including everyday operating costs, finance costs and life cycle maintenance costs) required to enable the delivery of all the contractual services to specifications for the un expired term; and (D) taking into account the net present value of the projected distributions to equity for the unexpired contract term;] (d) the break costs352 and all other reasonable costs incurred by the private party as a direct result of terminating a finance agreement; and (e) redundancy payments for employees of the private party and amounts owing to the subcontractors, which are, in each case, reasonably and properly incurred and arise as a direct result of the termination,353 less the deductions in section 29.3.2 below (Voluntary Termination Payment Amount). 29.3.2 Deductions The following items will be deducted from the amount set out in paragraph 29.3.1: (a) all credit balances on any bank accounts held by or on behalf of the private party on the termination date; (b) any amounts owing by the private party to government as at the termination date (including any amounts government is entitled to set-off); (c) any insurance proceeds paid or payable to the private party (or which would have been payable to the private party if it had complied with its insurance obligations) at any time between the termination date and the date of payment other than 352 The break costs are also intended to capture any break costs incurred as a result of early termination of hedging arrangements. If there are any break gains they must be deducted. 353 Government will not compensate the private party for redundancy amounts and subcontractor costs arising from arrangements not entered into in connection with the project or in the ordinary course of business and on commercial arm's length terms. In addition, government will not compensate subcontractor loss of profit for work not performed or for indirect or consequential loss. April 2008 135 Partnerships Victoria Updated Standard Commercial Principles payments that are to be applied to repairing or rebuilding the facility or to third party liabilities;354 and (d) all sums due and payable to the private party from the financiers as a result of any prepayment of senior debt355 and any third party amounts paid to the private party at any time during the period between the termination date and the date of payment.356 29.3.3 The greater of outstanding debt and Voluntary Termination Payment Amount In the event the Voluntary Termination Payment is less than the senior debt amount identified in paragraph 29.3.1(a)357 or paragraph 29.3.1(b),358 as applicable, (together with break costs under paragraph 29.3.1(c)), government will pay the private party the relevant senior debt amount. 29.3.4 Interest Government will pay interest on the Voluntary Termination Compensation Amount, where payment is delayed, on a project-specific basis.359 29.4 Mitigation The private party must use all reasonable endeavours to mitigate losses or costs in respect of which government is making a termination payment. 29.5 Transfer of debt obligations Government will have the right to request (in its absolute discretion) that it have transferred to it all outstanding debt obligations instead of paying any outstanding debt amount as part of a termination payment. In the event this occurs, the termination payment will be reduced accordingly. 354 Government would also be seeking to deduct insurance proceeds which would have been received before the termination date and applied against a component of the Force Majeure Compensation Amount, if the private party had complied with the project documents. 355 This will include any amounts payable as a result of early termination of hedging arrangements. 356 Upon termination, the private party must assign to government its rights to any claims against third parties which have not been determined or paid by the payment date. 357 i.e. the lower of senior debt owing to financiers at the termination date and the amount forecast in the base case financial model (as varied from time to time in accordance with section 18.6) to be owing to financiers as at the termination date. 358 ie. the lower of the present market value of the future cash flows under the bonds forecast to be outstanding at the date of termination in the base case financial model and those forecast to be paid at the termination date. 359 Whether interest is payable and the applicable interest rate will depend on the type of financing and the reasons for the delay in payment. April 2008 136 Partnerships Victoria Updated Standard Commercial Principles 30. Step-in Principle Government may step-in and assume all or some or the service delivery obligations of the private party when: (a) there is an emergency, a serious risk to the environment, the public or users of the facility or a serious risk of material damage to the facility; (b) step-in is necessary to discharge a statutory duty; or (c) an Event of Default remains unremedied or a termination event occurs. 30.1 Circumstances of step-in 30.1.1 Circumstances Government may assume all or some of the service delivery obligations of the private party360 for a period of time where: (a) there has been an Event of Default361 except where the private party is complying with an approved cure plan and diligently pursuing a remedy; (b) a Default Termination Event362 occurs; (c) there is likely to be a serious risk to the environment, a risk to the health or safety of the users of the facility or other members of the public or a serious risk of material damage to public or private property (including the facility) or other emergency; or (d) it is necessary for government to take immediate action to discharge or exercise a statutory duty or power.363 360 In some circumstances (such as in emergencies and to discharge a statutory duty) government may require the private party to suspend the performance of the services or request that alternative services be provided until normal operation of the facility can resume. Such rights are in addition to government's 'traditional' step-in rights but will generally be treated in a similar manner to step-in rights under the project agreement. The focus of the right, particularly in respect of emergencies, is a serious short-term problem that can or must be solved quickly, where the government is in a better position to do this than the private party. Government should not in any situation be obliged to step-in. 361 See paragraph 27.1 in section 27 (Default). 362 See section 28 (Termination). Although reference to Force Majeure Termination Event has been omitted the intention is that government has the right to exercise its step-in rights under paragraphs (c) and (d) at any time during the contract term, including during any period of suspension following the occurrence of a force majeure event but before the contract is terminated for a Force Majeure Event. However, it is not intended that any government emergency step-in regime cut across the force majeure regime (e.g. operation of termination rights for force majeure). April 2008 137 Partnerships Victoria 30.1.2 Updated Standard Commercial Principles Funders' step-in rights Government's step-in rights in paragraphs 30.1.1(a) and (b) will be subject to funders' step-in rights under the funders' direct agreement. 30.2 Rights and obligations on step-in 30.2.1 Extent of rights Government may elect to: (a) temporarily assume total or partial possession, management and control of the facility and the provision of the services; and (b) take such other steps as are necessary or desirable to continue the provision of the services and to minimise the risk to the environment, the public or users of the facility or of material damage to the facility. 30.2.2 Assistance by private party The private party must assist government whenever and however possible to exercise its step-in rights as set out in paragraph 30.2.1. 30.2.3 Government obligations • When exercising its step-in rights, government must use all reasonable endeavours to operate the facility and otherwise deliver the contracted services consistent with the project agreement. What is reasonable under the circumstances will be determined in light of the reason for government stepping-in. • Government is not obliged to remedy or cure any Event of Default or Default Termination Event to overcome or mitigate any risk or risk consequences in respect of which it exercises step-in rights. 30.2.4 Private party's rights and obligations suspended The private party's rights and obligations under the project agreement are suspended to the extent necessary to permit government to exercise its step-in rights. 30.2.5 Power of attorney The private party irrevocably appoints government (and its nominees) as its attorney with full power to exercise its step-in rights. 30.3 Costs of step-in While government is stepped-in, it must continue to pay the full service fee reduced by the following amounts: 363 Where the service being provided is an essential service, government may be given step-in rights to guarantee the continuity of an essential service. April 2008 138 Partnerships Victoria (a) Updated Standard Commercial Principles Where government has stepped in as a result of an Event of Default or a Default Termination Event364 (without double counting): (i) government's reasonable estimate of the costs not incurred by the private party as a result of it not providing the contracted services; and (ii) the costs incurred by government in exercising that step-in right, including all reasonable and proper costs incurred by government in delivering the affected services (whether directly or through a replacement subcontractor). If the aggregate amount to be deducted under paragraphs 30.3(a)(i) and (ii) is greater than the service fee, the difference will be a debt due and payable from the private party to the government. Where government has stepped-in as a result of any other triggering event,365 the operating or other costs which will not be incurred by the private party as a result of the exercise of the step-in rights. (b) 30.4 No liability or limitation on government's rights 30.4.1 No liability Government will have no liability to the private party and the private party will not be entitled to make any claim arising out of or in connection with the exercise of step-in rights unless government has acted negligently (in relation to emergency step-in only), fraudulently or in bad faith in the exercise of those rights. 30.4.2 No limitation on existing rights The exercise of step-in rights does not limit any other right of government under the project agreement, including rights arising pursuant to an Event of Default and Default Termination Event (but subject to funders' step-in rights366). 30.5 Stepping-out 30.5.1 Circumstances • Government may cease to exercise step-in rights at any time. • Government must cease to exercise step-in rights in each of the following circumstances: (a) where government has exercised its step-in rights as a result of an Event of Default or Default Termination Event,367 as soon as the Event of Default or 364 See paragraphs 30.1.1(a) and (b). 365 See paragraphs 30.1.1(c) and (d). 366 See paragraph 30.1.2. 367 See paragraphs 30.1.1(a) and (b). April 2008 139 Partnerships Victoria Updated Standard Commercial Principles Default Termination Event is remedied or government ceases to pursue a remedy; or (b) • where government has exercised its step-in rights as a result of any other triggering event,368 the relevant material risk is averted, overcome, or mitigated to government's satisfaction or the statutory duty has been performed.369 Government will not be obliged to cease exercising its step-in rights in respect of a particular step-in event if, prior to the date upon which government would otherwise have been required to step-out (in respect of that event), there occurs another step-in event entitling government to step-in. Government will then be required to step-out in accordance with paragraphs (a) or (b) above as applicable to the later step-in event. 30.5.2 Private party recommencing performance Upon government ceasing to exercise any step-in rights (and subject to government not having terminated the project agreement): (a) the private party must immediately recommence performance of the suspended obligations; and (b) government will, at the cost and expense of the private party, give reasonable assistance to ensure a smooth transition. 368 See paragraphs 30.1.1(c) and (d). 369 See comments in footnote 339 in paragraph 30.1.1 in respect of the effect of emergency step-in rights on the force majeure regime. April 2008 140 Partnerships Victoria Updated Standard Commercial Principles 31. End-of-term arrangements Principle The private party must (at its own cost) ensure that the project assets meet government's return conditions at contract expiry. The project assets and site will vest in government at the end of the contract term. Where government is to re-tender the contracted services at the end of the contract term, the private party must take all reasonable steps to ensure that the contracted services continue with minimum disruption and risk to government employees and public users. 31.1 Return conditions at contract expiry 31.1.1 Inspection at contract expiry • An independent assessor appointed by government:370 (a) must during the 12 months prior to the last five years of the operating term; and (b) may (if requested by government) at any time within the last five years of the operating term,371 inspect the project assets to determine what condition they will be in at contract expiry.372 • Following the inspection and subject to expected normal breakage and fair wear and tear, the independent assessor must notify government and the private party of:373 (a) the rectification and maintenance works (if any) the independent assessor considers are required from the date of the review until contract expiry to bring the condition of the project assets to the standard they would have been in had the private party properly performed its maintenance and refurbishment 370 See paragraph 11.5.7 in section 11 (Construction and commissioning) for a discussion on the requirements for the appointment of an independent assessor (completion certifier). Depending on the nature of the project, it may be more appropriate for government (rather than an independent assessor) to survey the condition of the facility, in which case the Project Director/Contract Administrator will carry out such assessment on government's behalf. In such a case, the private party could refer any dispute (regarding the works required or their cost) to an independent expert for resolution. 371 This period may be changed depending on the relevant life cycle expectations of the assets. 372 The project agreement will also provide for a contract termination inspection. 373 The private party may refer the matter for dispute resolution by an independent expert if it disagrees with the assessment by the independent assessor. April 2008 141 Partnerships Victoria Updated Standard Commercial Principles obligations under the project agreement and to ensure that on contract expiry the project assets comply with the 'return conditions';374 (b) a reasonable program for the private party to carry out such works; and (c) the expected cost of carrying out the works in accordance with the program. 31.1.2 Cost of inspection The cost of the inspection will be borne equally by government and the private party.375 31.1.3 Obligation to cooperate The private party must cooperate with the independent assessor and provide all assistance necessary for the inspection to be carried out. 31.1.4 Deductions from service fee • Government will deduct from each remaining scheduled service fee due for payment during the period from the inspection until contract expiry, an amount equal to the cost of the final maintenance and refurbishment works (as determined by the independent assessor) divided by the number of remaining payments. • Government will deposit such deductions into the escrow account.376 • As an alternative, government may consider accepting a performance bond or appropriate security for the cost of the final maintenance and refurbishment works. 31.1.5 Obligation to carry out works • The private party will carry out the final maintenance and refurbishment works in accordance with the agreed program, all applicable laws and approvals, all specified quality, design and construction standards and otherwise to the independent assessor's satisfaction. • The private party must ensure that, on contract expiry (having carried out any final maintenance and refurbishment works), the project assets comply with the return conditions. The independent assessor must be satisfied this has been achieved. 31.1.6 • Private party successfully performs the final maintenance and refurbishment works If the independent assessor is satisfied that the private party has completed the final maintenance and refurbishment works (or any relevant part of them), then upon the independent assessor advising government to that effect, government will pay the private party the cost of the works by drawing on the escrow account. 374 The project agreement will specify the condition the project assets must be in at contract expiry, taking into account the design life requirement after contract expiry. 375 The project agreement will specify the condition the project assets must be in at contract expiry, taking into account the design life requirement after contract expiry. 376 See paragraph 31.1.9. April 2008 142 Partnerships Victoria • Updated Standard Commercial Principles Government's obligation to pay for the private party's costs is limited to the amounts held in the escrow account. 31.1.7 Refurbishment bond Where: (a) the cost of the final maintenance and refurbishment works is greater than the aggregate amount of any remaining scheduled payments (until expiry); or (b) at any time during the period from the inspection and contract expiry, the cost of any remaining works to be completed is greater than the balance standing to the credit of the escrow account at such time, the private party must provide government with a performance bond with a face value of not less than the amount of the shortfall and which expires one year after contract expiry. 31.1.8 Deductions from termination payments To the extent not already accounted for in any termination payment, the value of any maintenance and refurbishment works that have not been carried out by the private party but for which government has paid during the contract term will be deducted from any early termination payment.377 31.1.9 Escrow account • Government will be the sole signatory to the escrow account which is to be an interest bearing account with an authorised deposit-taking institution and on call with 24 hours notice. • Interest earned on money standing to the credit of the escrow account will be deposited in the escrow account. • The private party will be given full particulars of the escrow account. • Money in the escrow account is government's property. 31.2 Other private party rights and obligations 378 31.2.1 Surrender and return of the project assets The private party must surrender and return to government all its right, title and interest in the facility and site (licensed or leased to the private party) free from encumbrances and consistent with the return conditions.379 377 See section 29 (Termination payments). 378 These provisions will depend on the specific project and the extent to which government may already own relevant assets and the extent to which government requires the assets to be transferred to it. 379 The project assets and site become the absolute property of government at the end of the contract term. The private party may, if relevant for the particular project, also be required to make available any handover packages. April 2008 143 Partnerships Victoria 31.2.2 Updated Standard Commercial Principles Novation If government so requests, the private party must novate to government or its nominee any project lease, sub-lease or licence granted by the private party or any other agreement entered into by the private party in respect of the works or the services. 31.2.3 Re-tendering requirements • The private party must use reasonable endeavours to assist government where government is to tender the right to deliver the contracted services following the end of the contract term. This includes making available any information government or any successor party reasonably requires relating to the project (excluding confidential financial information). • The private party must take all reasonable steps to assist government and any successor so that any continuation of the contracted services is achieved with minimum disruption and risk to government employees and public users. However, the private party is not required to undertake activities which will unreasonably interfere with the operation of its business. 31.2.4 Power of attorney From the end of the contract term, the private party will appoint government (and any persons nominated by government) as its attorney to carry out any end-of-term rights and obligations as described in paragraph 31.2. 31.2.5 Continuing obligations • Expiry or early termination of the project agreement is without prejudice to any accrued rights and obligations as at the expiry or termination date (including any rights and obligations accrued as a result of a default). • The parties will agree the specific provisions which will survive termination or expiry of the project agreement. However, they usually include provisions relating to the satisfaction of conditions precedent, indemnities and warranties, the defects liability period, end-of-term maintenance and refurbishment obligations (including the escrow account), payment and termination provisions, government's step-in rights, general remedies, intellectual property, confidentiality obligations, dispute resolution, public relations and publicity, records and end-of-term rights and obligations. 31.2.6 • End-of-term payment In circumstances where government believes that the private party is unlikely to perform any of its specified ongoing obligations after expiry or early termination of the project agreement, government may either: (a) withhold part of the final scheduled payment380 (in the event of contract expiry) or the relevant termination payment (where there is an early termination); or (b) require a performance bond to be provided in respect of those obligations.381 380 Depending on the amount of the final scheduled payment, government may need to withhold part or all of several scheduled payments near the end of the term. April 2008 144 Partnerships Victoria Updated Standard Commercial Principles • Any monies withheld by government will be payable to the private party on the earlier of the outstanding obligations being satisfied and the end of a specified period (to the extent that the private party has met its obligations arising up to the end of that specified period). • Government may make a demand under the performance bond to the extent that the private party fails to perform its obligations. The performance bond will expire at the end of a specified period.382 • The amount of any withheld monies and the value of any bond (which may be a bid item) is intended to reflect the costs and losses which government is likely to incur as a result of the private party's failure to perform its ongoing obligations. • Whether government seeks to withhold any funds or requires a performance bond is a value for money consideration dependent on a number of issues. These include whether government will continue using the facility at the end of the contract term (and, in particular, whether it will be re-tendering the services), the risk and effect on government of the private party not complying with its end-of-term obligations and whether the private party is a special purpose vehicle or a company of substance financing the project on balance sheet. 381 The performance bond may also include an amount to cover any latent defects, where the defects liability period extends past the end of the contract term. 382 This period will be determined on a project-specific basis depending on the nature of the obligations, but would generally be expected to be a 12 month period. April 2008 145 Partnerships Victoria Updated Standard Commercial Principles 32. Dispute resolution Principle The dispute resolution processes are designed to provide resolution of matters in dispute in a speedy and non-litigious but fair and independent manner. 32.1 Panel A panel will be established under the project agreement as the initial forum for resolution of disputes (panel). 32.1.1 Notification and obligation to resolve disputes • All disputes notified by one party to another will be referred to the panel for resolution. • Within a specified period of receiving notice of the dispute, the panel must meet in good faith and use its reasonable endeavours to resolve the dispute. 32.1.2 Composition The panel will consist of one senior government representative and one senior private party representative with sufficient seniority and authority to resolve the dispute (subject to any requirements for formal approvals as discussed in paragraph 32.1.3). 32.1.3 Decision A decision of the panel may only be made by unanimous agreement and is binding on both parties, subject to any formal approval required as part of the parties' governance structures or by statute. 32.2 • • Independent determination Where the panel is unable to resolve the dispute, it will (depending on the nature of the disputed matter) refer the matter for independent determination either by: (a) an independent expert; or (b) an arbitrator. Matters of a technical or financial nature (including disputes over compensation amounts) will generally be referred to an independent expert for resolution. However, arbitration may be the appropriate course in other circumstances.383 383 The project agreement will specify what matters will be referrable to the independent expert and which to the arbitrator. April 2008 146 Partnerships Victoria Updated Standard Commercial Principles 32.3 Independent expert 32.3.1 Appointment An independent expert will be appointed by agreement of the panel or, failing agreement, by a third party such as the chairperson for the time being of the Institute of Arbitrators and Mediators Australia (Victorian Chapter). 32.3.2 Capacity and procedure The independent expert will act as an expert and not as an arbitrator and may adopt such procedures as he or she sees fit. 32.3.3 Time for decision A timeframe will be set for the independent expert to deliver his or her determination. 32.3.4 Decision final and binding To the extent permitted by law, the decision of the independent expert will be final and binding on the parties unless a party disputes it within a specified period or the value of the determination is greater than a specified monetary threshold.384 32.3.5 Costs • The costs of the independent expert will be borne equally by the parties. • Each party will bear its own costs relating to the independent expert's determination. 32.4 Arbitration 32.4.1 Appointment Where a dispute is to be resolved by arbitration, an arbitrator will be appointed by agreement of the parties or, failing agreement, by a third party such as the chairperson for the time being of the Institute of Arbitrators and Mediators Australia (Victorian Chapter) or the Australian Centre for International Commercial Arbitration. 32.4.2 Capacity and procedure The arbitrator will conduct the arbitration in accordance with and subject to the Commercial Arbitration Act 1984 (Vic) (but excluding section 27). 32.4.3 Time for decision A timeframe will be set for the arbitrator to deliver a determination.385 384 An appropriate monetary threshold for these purposes will depend on the value of the project. 385 Generally 10 business days from completion of legal submissions. April 2008 147 Partnerships Victoria 32.4.4 Updated Standard Commercial Principles Decision final and binding The decision of the arbitrator is final and binding on the parties. 32.4.5 Costs The decision of the arbitrator will include a decision relating to the costs of the reference and the award, including the fees and expenses of the arbitrator. 32.5 Fast-track process • Provision will be made for a fast-track option for resolution of disputes where the outcome is time-critical. • The timeframes of both the panel process and expert determination or arbitration will be truncated. 32.6 Legal rights A party may appeal to the Supreme Court of Victoria on a question of law arising from the determination of the arbitrator but will not otherwise be entitled to have recourse to the courts on disputes subject to dispute resolution under the project agreement. 32.7 Obligation to continue to perform Despite the existence of a dispute, each party must continue to perform its obligations under the project agreement (including obligations to pay monies). April 2008 148 Partnerships Victoria Updated Standard Commercial Principles 33. Re-financing gain Principle All re-financings other than those contemplated at financial close will require government consent.386 Any re-financing gain is to be shared between government and the private party on a 50:50 basis provided the projected equity return at the time of the re-financing (taking into account any refinancing) is above that reflected in the original base case financial model. 33.1 Government consent The private party must not re-finance the project without government's prior consent (which is not to be unreasonably withheld or delayed) or without a direct agreement being entered into with the new financier. 33.2 Notice and re-financing details The private party must give government adequate notice and full details of the proposed re-financing. Required details will include an amended financial model, the basis for the assumptions used in the amended financial model, a certificate from the auditors of the model, any material changes to the private party's obligations to its funders and the anticipated re-financing gain. 33.3 What is a re-financing? 33.3.1 Re-financing definition A re-financing is: (a) any amendment to or replacement of the current financing agreements387 and the exercise of any right under such documents, however they may occur; and (b) any new contractual or financing arrangement which has the effect of in any way restructuring the funding arrangements as at contract signing (including the gearing levels). 386 Government recognises the importance to financiers of being able to obtain government's approval quickly in circumstances involving a rescue re-financing. Accordingly, government will ensure it acts reasonably and expeditiously in those circumstances. 387 For these purposes, 'current financing agreements' refers to the agreements for financing the project as at contract signing (as amended with government's approval). April 2008 149 Partnerships Victoria 33.3.2 Updated Standard Commercial Principles Exemptions Re-financing will not include:388 (a) any re-financing which was specifically contemplated at financial close and reflected in the base case financial model;389 (b) disposals of investments or commitments of debt or equity in an arms length transaction at market value; (c) the syndication or subscription of any debt under the current funding agreements that is contemplated at financial close; (d) the change in control or sell down of any bonds390 in an arms length transaction at market value; and (e) waivers and consents and similar actions which relate to day to day administrative matters. 33.4 When may government withhold its consent Government may withhold its consent where: (a) the re-financing would adversely affect government's interests including increasing or adversely affecting government's contractual liabilities;391 (b) the terms and conditions of the proposed re-financing (taken as a whole) are materially more onerous or disadvantageous to the private party than the existing funding arrangements and government considers the private party will be unable to adequately service and repay the financial indebtedness assumed under the refinancing or that such financial indebtedness will adversely impact the private party's ability or capacity to perform its obligations under the project documents; (c) the terms and conditions are not in accordance with market practice at the time; and (d) the indebtedness will not be used solely for the project. 388 These exemptions assume that the project is not undertaken on a corporate finance basis. 389 Such re-financings will be exempted only up to the amounts included in the financial close base case financial model and taken into account in determining the service fee. Government must ensure adequate due diligence of the base case model is conducted prior to financial close to ensure that any re-financing assumptions are clarified and agreed. 390 Whether or not this is an exclusion will depend on the funding arrangements of the individual project. 391 For example, government's obligation to pay termination payment amounts. Government will take into account the level of compensation it will receive in determining the effect of any re-financing on it. April 2008 150 Partnerships Victoria 33.5 Updated Standard Commercial Principles Sharing a re-financing gain Government will be entitled to a 50 per cent share of any re-financing gain but only where the projected equity return at the time of the re-financing (taking into account any refinancing) is above that included in the original base case financial model. 33.6 Calculating the re-financing gain 33.6.1 What is a re-financing gain? Re-financing gain is the difference (greater than zero) between the net present value of: (a) the distributions projected at the proposed re-financing date (taking into account the proposed re-financing) using the updated financial model referred to in paragraph 33.2 (post-refinancing distributions); and (b) the distributions projected immediately prior to the proposed re-financing (without taking into account the proposed re-financing) using the base case financial model as varied from time to time in accordance with the project agreement (prerefinancing distributions).392 33.6.2 The discount rate The discount rate used to determine the net present value of the distributions (for both pre and post re-financing) will be the equity rate of return provided for in the base case financial model. 33.6.3 Distributions Distributions are any dividends, interest payments or other distributions by the private party to its shareholders, loanstock or related bodies corporate (including amounts available for such distributions)393 and receipt of any other benefit by those parties (including the release of any contingent liabilities) but excluding payments made to a related body corporate under a subcontract (where the related body corporate is a subcontractor) or otherwise on arm's length terms. 33.6.4 Professional costs The re-financing gain will be calculated after allowing for the recovery by both parties of their reasonable and proper professional costs directly incurred in connection with the refinancing. 33.7 Payment of the re-financing gain Government may elect to receive its share of the re-financing gain in one (or a combination) of the following ways: (a) a single payment from the private party; or 392 See paragraph 18.6 in section 18 (Payment provisions). 393 Whether such distributions are in respect of share capital or subordinated debt. April 2008 151 Partnerships Victoria (b) Updated Standard Commercial Principles a reduction in the service fee in accordance with the service fee adjustment principles.394 33.8 Government audit rights Government may at any time audit any financial model used in connection with the refinancing (including the underlying assumptions for the data and projections used in the proposed model). 33.9 Acting in good faith Both parties will at all times act in good faith with respect to any re-financing. In particular, they must negotiate in good faith to agree the basis and method of calculation of the refinancing gain and the manner and timing of payment of government's share of the gain. 33.10 Funder's direct agreement The private party must not enter into a re-financing until the new financiers have entered into a funder's direct agreement. 33.11 Termination payments Unless otherwise agreed, government is obliged to make termination payments only to the extent set out in the base case financial model (as varied, including for any re-financing, in accordance with the principles and procedures in paragraph 18.6 in section 18 (Payment provisions)). 394 See paragraph 18.4 in section 18 (Payment provisions). In determining the appropriate method for payment, government will consider the form in which the private party receives the re-financing gain (i.e. whether a reserve that has been released is paid out). April 2008 152 Partnerships Victoria Updated Standard Commercial Principles 34. Indemnities, warranties and contractual claims Principle The private party indemnifies government for death or personal injury, property and third party claims arising from the project. The private party acknowledges that it has entered into the project on the basis of its own investigations and not on the basis of any government representations and it indemnifies government accordingly. 34.1 Private party indemnity 34.1.1 Indemnity • • 395 Subject to paragraph 34.1.2, the private party will release and indemnify395 government and its associates in respect of any action, claim, demand, cost, charge, liability, loss, damage and expense (including legal expenses) incurred by government (including any third party claims or liabilities) resulting from: (a) the design, construction, operation or maintenance of the facility; (b) any acts or omissions of the private party, the subcontractors and their associates in relation to, or in consequence of, the project (including, from the performance or non-performance by the private party of its obligations under the project agreement and their presence on, or access to, the facility and the site); and (c) any contamination or pollution occurring on or from the site other than that created by a government core service at the site and for which the private party does not have management responsibility.396 On many projects, government will cap the private party's liability under the indemnity in respect of: (a) third party claims made against government (other than death and personal injury claims); (b) damage to government property; and (c) government economic losses. The project agreement will provide for appropriate procedures for dealing with claims. 396 See paragraph 5.2.7 in section 5 (Environmental issues) in respect of the private party's liability for third party claims and liability arising from contamination or pollution occurring on or emanating from the site. April 2008 153 Partnerships Victoria Updated Standard Commercial Principles • While there may be a nexus between such caps and the level of required insurances, these should not be expressly or directly linked. • If it is agreed that government will cap the private party's liability, this cap will not extend to any actions, claims or liabilities arising or brought against the private party by a third party. 34.1.2 Limitation of liability The private party will not be liable under the indemnity to the extent that a claim or liability is a consequence of fraudulent or negligent acts or omissions of government or its associates or a breach by government or its associates of any project document. 34.2 Representations and warranties 34.2.1 Representations by the private party The private party will provide a series of representations and warranties to government along the following lines:397 (a) it has corporate status to enter into the transaction and is solvent; (b) it has the power to own its property and enter into the transaction; (c) all authorisations to enter into the transaction have been obtained; (d) all obligations in the project documents are binding on it; (e) its compliance with the project documents will not cause any contravention of law, of any authorisation or undertaking, or of its own constitution; (f) it is not acting as a trustee of a trust except to the extent agreed by government in writing; 398 (g) no proceedings are current or pending which have a material adverse effect on its ability to perform its obligations; (h) all information given to government is true, accurate and not misleading; (i) no filings or taxes are needed to make the project agreement binding; (j) no default has occurred and is subsisting; (k) there are no security interests other than permitted security interests over its property; and (l) government has been provided with all material documents relating to financing. 397 The representations and warranties are listed in short form and are intended as examples and not as an exhaustive list. See paragraph 1.3.3 of section 1 (Contractual issues) for government warranties. 398 If the private party is acting as a trustee government will review and agree the trust deed and appropriate trustee representations, warranties and undertakings will be included in the project agreement. April 2008 154 Partnerships Victoria 34.2.2 Updated Standard Commercial Principles Private party's acknowledgment, waiver and indemnity • The private party must acknowledge and agree that government and its associates have not made any representation, advised or given any warranty or undertaking (other than as expressly set out in the project agreement) in respect of the project documents, any transactions contemplated by the project or financing documents or any other matter relevant to the private party's decision to enter into the project or finance documents. • The private party will also acknowledge and agree the following:399 (a) disclosed information and intellectual property rights will remain the property of government and/or its associates; (b) disclosed information did not constitute an invitation, recommendation or offer by government and/or its associates; (c) disclosed information was provided to assist in preparing and lodging a proposal for the project; (d) disclosed information did not purport to contain all information required by the private party; (e) government and/or its associates has not and is not obliged to verify the accuracy or completeness of the disclosed information; (f) government and/or its associates has not made any representation or warranty as to the accuracy or completeness of the disclosed information; and (g) the private party has not relied on the disclosed information but on its own investigations in entering into the transaction. • To the extent permitted by law, the private party will waive all rights it has to bring any action against government or its associates for misrepresentation or misleading or deceptive conduct in providing the disclosed information. • The private party will indemnify government and its associates against all claims or liabilities in breach of these provisions. 34.2.3 Reliance on representations The private party must acknowledge that government enters into the project agreement in reliance on the representations, warranties, acknowledgments and agreements made by the private party and that these survive the execution and completion of the transactions contemplated in the project documents. 399 The items listed are in short form and intended as examples and not as an exhaustive list. April 2008 155 Partnerships Victoria 34.2.4 Updated Standard Commercial Principles Repetition of representations and warranties The representations, warranties and acknowledgments are repeated by the private party on each anniversary of financial close with reference to the facts and circumstances subsisting at that date.400 34.3 Non-exclusivity of remedies The rights and remedies provided in the project agreement are in addition to and do not exclude or limit any right or remedy of government provided by law or equity or by any agreement.401 400 This is subject to any written disclosures made by the private party to government and waived by government at or before the time of repetition. 401 See paragraph 14.8 of section 14 (Service requirements and specifications) and in particular footnote 125. April 2008 156 Partnerships Victoria Updated Standard Commercial Principles 35. Restrictions on private party Principle The private party must obtain prior government consent to any: (a) business conduct other than implementation of the project; (b) amendment of the project agreement or other agreements to which government is a party and amendment of the financing documents and key subcontracts; (c) assignment or disposal of its interests in the project agreement or other agreements to which government is a party; or (d) disposal of any interest in the project land or facility. 35.1 Restrictions on business The private party must not conduct any business other than the implementation of the project without obtaining government's prior consent. 35.2 Restrictions on amending certain documents The private party must not: (a) amend or terminate the project agreement or other agreements to which government is a party without obtaining government's prior consent (which consent will be given or refused within a specified period of the private party's request); or (b) terminate, or make or permit any amendment to, any financing or equity document or subcontract, other than in accordance with the provisions set out in sections 33 (Re-financing gain) and 20 (Subcontractors), respectively. 35.3 Restrictions on assignment 35.3.1 No assignment without consent Other than a permitted security interest402 or where a replacement private party has been appointed by a financier under the funder's direct agreement, the private party must not 402 Permitted security interest will be defined as a security interest to which government has provided its prior consent or which is created under an agreement with government or a lien which arises solely by operation of law in the ordinary course of ordinary business. April 2008 157 Partnerships Victoria Updated Standard Commercial Principles dispose of any of its rights or interests in the project agreement or other agreements to which government is a party, without obtaining government's prior consent (to be provided at its discretion).403 35.4 Restrictions on sale or lease Other than granting a permitted security interest or otherwise acting in accordance with provisions in the project agreement, the facility lease or construction licence, the private party must not dispose of the project land or the facility without the prior consent of government. 403 Depending on the nature of the project, this restriction may also extend to the private party procuring that specified major subcontractors do not dispose of their interest in the relevant subcontract. April 2008 158 Partnerships Victoria Updated Standard Commercial Principles 36. Records Principle The private party must maintain and provide government with all financial and other records, statements and documentation necessary to enable government to monitor and assess the private party's financial capacity and its performance of its obligations under the project agreement and to allow for transparency of costs. 36.1 Maintenance of audited records • The private party must keep proper accounts and all other financial records expected of a prudent and competent person undertaking obligations similar to those of the private party.404 In particular, the private party must maintain a full record of the costs of delivering the contracted services (including construction, operation and funding costs) and details of funds held to cover such costs. • All such financial statements must be audited annually. 36.2 Availability of audited records All the above accounts and records must be available to government (or any party it nominates) for examination, audit, inspection, transcription and copying. 36.3 Accounting records 36.3.1 Annual business plans The private party must (on an annual basis) provide government with a copy of its business plan for the following financial year and its budget for the next two financial years. 36.3.2 • Six-monthly records The private party must provide on a half-yearly basis the following unaudited documents for the financial year to date: (a) statement of financial performance, cash flow statement and statement of financial position; 404 Depending on the creditworthiness of the key subcontractors (and their relationship to the private party) and the level of information provided by the private party's records, the private party may also be required to ensure that key subcontractors keep and make available to government the same accounts and financial records required of the private party and all requirements applying to the provision of the private party's records will apply equally to the subcontractor records (e.g. warranty, financial audit etc). To the extent that government requires this of subcontractors, it will only apply in relation to their involvement in the project. April 2008 159 Partnerships Victoria Updated Standard Commercial Principles (b) comments on any material variations between actual and budgeted to date results; and (c) details of all the private party's indebtedness and changes to its financing arrangements.405 • Government requires audited financial statements of the private party to be submitted to it following the end of the financial year. • All books of account are to be kept in accordance with best accountancy practice and must show in detail the private party's administrative overhead costs, payments to subcontractors and capital and revenue expenditure.406 36.4 Provision of other details 36.4.1 Consortium details The private party must notify government of any change to the consortium details for any consortium member as provided at financial close.407 36.4.2 Other information and records The private party must provide government with any other information, records or documents government reasonably requires in relation to the facility and its operation (including copies of any documents issued to the private party's members, lodged with ASIC or relevant stock exchange, or any information provided to the private party's financiers). 36.5 Warranty All information given by the private party is to be warranted as being true, correct and complete at the time provided. 36.6 Financial audit 36.6.1 Audit requirements • At any time up to six months after the end of the contract term, government may (at its cost) require an independent audit of any financial statements or accounts provided in respect of the private party to verify their accuracy, correctness and completeness. 405 Where the project provides for third party revenue, government may also require details of any third party revenue earned by the private party in respect of which government may have a financial interest. 406 This information allows government to verify expenditure proposed by the private party arising from government-initiated modifications, compensable events, qualifying changes in law, benchmarking and market testing. 407 Required information includes the name of the parties' auditors, directors, company secretary and chief executive, any business name under which they operate, any persons holding a relevant interest in 20 per cent or more of the shareholding in each of the parties or who are able to control each party. The relevant consortium members will depend on the corporate structure relevant to the particular project. April 2008 160 Partnerships Victoria • Updated Standard Commercial Principles The private party must make available for the audit all its financial statements and accounts and, if necessary, an appropriately trained and qualified member of its staff to provide accounting system information relevant for audit. 36.6.2 False information • If the audit shows that any of the statements or accounts are not accurate, complete and correct, then the private party must rectify the problem and the cost of the financial audit will be for the private party's account. • If the inaccuracy has affected any payment made to the private party, the next scheduled payment will be reduced or increased by an appropriate adjustment amount (as determined by government). • Where the financial audit discloses any fraud or false, misleading or negligent reporting, this will constitute an Event of Default.408 36.7 Maintenance of non-financial records The private party must maintain a full record of all incidents relating to health, safety, security and pollution of the environment occurring during the contract term and of all maintenance procedures carried out during the contract term.409 Such records must be available to government for inspection and copying. 36.8 Period for retaining records All records and statements must be retained for at least five years after the private party's obligations under the contract have ended. 36.9 Confidentiality All records, statements and documentation referred to above are subject to the confidentiality and disclosure provisions.410 408 See paragraph 27.2.2(e) in section 27 (Default). 409 Depending on the nature of the project, it may be necessary to include additional specific record keeping requirements in the project agreement - e.g. where there are information privacy or health record issues. See Appendix H of the Partnerships Victoria Contract Management Guide for further information in relation to privacy legislation in Victoria. 410 See section 38 (Confidentiality and disclosure). April 2008 161 Partnerships Victoria Updated Standard Commercial Principles 37. Probity Principle The private party is responsible for reversing or otherwise addressing the effects of any probity event to government's satisfaction. Government may require the private party to carry out probity investigations to ensure those involved with the project are fit and proper to have such involvement. 37.1 Notification of a probity event The private party must notify government as soon it becomes aware that a probity event has occurred or is likely to occur. 37.2 Meaning of probity event A probity event includes any event or thing which: (a) has a material adverse effect on the character, integrity or honesty of an associate411 of the private party; (b) relates to the private party or an associate and has a material adverse effect on the public interest or public confidence in the project; or (c) involves a material failure by the private party or an associate (where it is a corporation) achieving or maintaining reasonable standards of ethical behaviour, good corporate citizenship, avoidance of conflicts of interest or other standards of conduct that would otherwise be expected of a party involved in a government project. 37.3 Consequences following notice of a probity event 37.3.1 Parties to endeavour to agree course of action • Within a specified period following notice of a probity event, the parties will meet with a view to agreeing a course of action to reverse the effect of the probity event on the project or otherwise cure it. • The private party must take within the specified time any action agreed with government. 411 This will generally be defined to include any related body corporate of the private party and any officer, employee, agent, contractor, consultant or adviser of a member of the private party group for the particular project. April 2008 162 Partnerships Victoria 37.3.2 Updated Standard Commercial Principles Parties unable to agree • Where, within a specified period, the parties are unable to agree a course of action (including where the private party fails to meet with government to agree a course of action), the private party must take any action required by government to address the adverse effect of or cure the probity event.412 • Actions government may require of the private party include:413 (a) where the corporation triggering the probity event has control over the private party or relevant associate, that the corporation ceases to have control; and (b) procuring that a person triggering the probity event ceases to have any involvement, shares, entitlement or significant influence, power or control over any relevant company (being the private party or an associate of the private party) or the project and removing such person from any involvement in the project. 37.4 Costs of cure The private party will bear all costs associated with the above action required by government as set out in paragraph 37.3. 37.5 Probity investigations 37.5.1 Government requirement for probity investigations Government may require the private party at any time to conduct probity investigations in respect of an associate of the private party (or any proposed associate). 37.5.2 Type of probity investigations Government may require such probity, criminal and security investigations into the character, honesty and integrity of a person or a corporation as are necessary to ensure that they are fit and proper for their intended involvement in the project. 37.5.3 Consents The private party must procure all relevant consents from the party in respect of which government requires probity investigations. 37.5.4 Costs of probity investigation The private party will bear the costs reasonably incurred by government in carrying out the initial investigation in respect of each relevant party or event. The private party will not be liable for any further probity or security investigations required by government. 412 This is subject to the private party's right to refer a government determination to dispute resolution if it considers that the required action will not address the adverse effects of the probity event. To the extent that financiers exercise their step-in rights, they may be able to cure the relevant probity event by appointing a receiver. 413 This is not intended to be an exhaustive list of the action government may require. April 2008 163 Partnerships Victoria 37.6 Updated Standard Commercial Principles No appointment without government consent The private party will not appoint an associate unless such party has been approved by government following a probity investigation and other investigations required by government. April 2008 164 Partnerships Victoria Updated Standard Commercial Principles 38. Confidentiality and disclosure Principle Government will be entitled to publish the project agreement and associated transaction documentation, subject to limited exceptions for commercially sensitive information. 38.1 State disclosure Government will be entitled to disclose (on the internet or otherwise): (a) the terms and conditions of the project agreement and any associated transaction document; and (b) any documents or information arising out of or connected to the agreement or transaction documents (including the performance of those agreements), except to the extent that any documents or information are agreed by the parties to be confidential.414 38.2 Confidentiality 38.2.1 Agreement The project agreement will identify any matters which are subject to a confidentiality obligation on both parties.415 The confidentiality of such matters is subject to government's legislative disclosure obligations set out in paragraph 38.3.1. 38.2.2 Requirement for consent Any matter which the parties agree should remain confidential must not be disclosed to any person by either party without the prior written consent of the other, except in specific circumstances including: (a) any disclosure required by law or legally binding statutory approval; (b) information already in the public domain; (c) any disclosure required by any applicable stock exchange listing rules; 414 See paragraph 38.2.1. 415 This will generally be commercially sensitive material (e.g. innovative construction methods or payment and price mechanisms) which the private party wishes to remain undisclosed, or material relevant to national security, which government wishes to remain undisclosed. Generally, only information that is exempt from disclosure under the Freedom of Information Act 1982 (Vic) will be brought under such a confidentiality obligation. April 2008 165 Partnerships Victoria Updated Standard Commercial Principles (d) any disclosure to solicitors, barristers or other professional advisers under a duty of confidentiality; (e) any disclosure to a banker or other financial institution relevant to a party, to the extent required for the purpose of raising funds or maintaining compliance with credit agreements or in respect of a permitted syndication; (f) any disclosure by the private party to a related body corporate of the private party as necessary for the related body corporate to perform its obligations under the project agreement or other project documents, subject to the related body corporate providing a covenant to maintain confidentiality which is satisfactory to government; (g) any disclosure of information to any prospective or actual permitted assigns or investors in, or shareholders of, the private party (and their respective financiers), subject to such purchaser providing a covenant to maintain confidentiality which is satisfactory to government; (h) any disclosure required in connection with permitted re-tendering or any benchmarking or market testing; (i) any disclosure amongst permitted government parties; and (j) any disclosure necessary for the registration or recording of documents where required. 38.3 Legislative disclosure obligations 38.3.1 Legal requirement of disclosure The private party will acknowledge and agree that disclosure by government may be required: (a) under the Freedom of Information Act 1982 (Vic); (b) under the Ombudsman Act 1973 (Vic); or (c) to satisfy the disclosure requirements of the Victorian Auditor General under the Audit Act 1994 (Vic) or of Parliamentary accountability or in the case of a Minister to fulfil his or her duties of office. 38.3.2 Obligation The private party must, at its own cost and expense, use all reasonable endeavours to assist government in meeting government's legislated disclosure obligations. April 2008 166 Partnerships Victoria Updated Standard Commercial Principles 39. Intellectual property Principle The private party is responsible for the costs of intellectual property required by the project (including costs resulting from infringements subject to any government warranties and indemnities in respect of intellectual property brought to the project by government). Government must be able to use any intellectual property required to provide the services in the event that it takes over the service, whether during or beyond the end of the contract term. 39.1 • Warranties The private party must warrant that, in performing its obligations under the project agreement: • (a) it will not breach the intellectual property (IP) rights or moral rights of any person; (b) subject to paragraph 39.3 it has authority to grant to government the licence or other rights to be granted under the project agreement; and (c) neither the use nor exercise of those rights by government (or any party authorised by government) will infringe any IP or moral rights of any person. If government brings IP to the project, the scope of this warranty will be adjusted to exclude matters warranted by government.416 39.2 Grant of licences Subject to paragraph 39.3, the private party will grant government (and where necessary ensure the grant by third parties of) non-exclusive but irrevocable, perpetual, transferable and royalty-free licences with the right to sub-licence, use and exercise all IP rights in or used in the project including: (a) the design of the works; (b) the design documentation and final design documentation; (c) methods of working and materials used in the construction and commissioning of the works; and (d) operation of the facility as required for government to exercise its rights under the project agreement (including step-in) and, where applicable, to allow for the 416 See section 39.7. April 2008 167 Partnerships Victoria Updated Standard Commercial Principles continuation of the project services following the termination of the agreement or expiry of the contract term.417 39.3 Obligation Where, after having used its reasonable endeavours, the private party is unable to grant government any of the licences it is required to grant, government and the private party will negotiate in good faith with respect to the private party obtaining such rights or arrangements for government's benefit as government reasonably requires having regard to government's rights as set out in section 39.8. 39.4 Moral rights In addition to obtaining all copyright and patent consents required for the project, the private party will be required to obtain, for the benefit of government, the consent of the authors of all copyrighted works of which use is made for the purposes of the project. 39.5 Survival of rights The IP and moral rights granted to government survive: (a) any frustration, suspension, termination or expiry of the project agreement; and (b) government exercising its rights of step-in. 39.6 Indemnity Subject to the exclusion of any matters warranted by government under section 39.7, the private party will indemnify government against claims or liabilities arising from any infringement of a person's IP or moral rights by: (a) the private party and any subcontractor; or (b) government or government's authorised representatives, where the infringement arises as a result of the private party's failure to comply with its obligations under paragraphs 39.2, 39.3 or 39.4. 39.7 IP rights passed from government If government contributes IP which the private party is either required or entitled to use for the project, government will provide a licence to the private party that is specifically restricted to the project and for the term of the project agreement. In such a case, government may consider appropriate intellectual property and moral rights warranty and/or indemnity provisions. 417 Government may require that the licence to use IP developed for the project be extended to use in other projects. April 2008 168 Partnerships Victoria Updated Standard Commercial Principles 39.8 Rights to IP on expiry of term 39.8.1 Government rights The project agreement will provide that: (a) if the private party has not been able to grant the licence under clause 39.2 for use of third party IP rights beyond the expiry or earlier termination of the project agreement, the private party will procure a novation of any IP licences from those third parties to government and that the private party will be obliged to ensure that the IP licences it obtains for the benefit of government make provision for this; or (b) if the requirements in paragraph (a) prove impossible, the private party must secure government's right to obtain those licences at commercial rates. These obligations survive in the same manner as in paragraph 39.5. 39.8.2 Indemnity The private party must indemnify government against any costs incurred through nonavailability of the IP necessary for the continuation of the services. 39.8.3 Provision of data To ensure government's immediate ability to operate the facility, the private party may be required to provide any data (including source code for software) that is necessary for operation to an independent party to be held in escrow for release in appropriate circumstances. April 2008 169 Partnerships Victoria Guidance Material - Updated Standard Commercial Principles www.partnerships.vic.gov.au
Documentos relacionados
Disclosure and management of conflict of interest for advisers
1 Treasury Place, Melbourne Victoria 3002 Australia Telephone: +61 3 9651 5111 Facsimile: + 61 3 9651 5298 Website: www.partnerships.vic.gov.au Published by the Department of Treasury and Finance ©...
Leia mais